Response to the Housing and Community Safety Sub-Committee's Review of Unfinished Security Works on Four Squares Estate
NotedExecutive2 papers
AI summarySouthwark Cabinet accepted the Housing and Community Safety Scrutiny response on unfinished security work at Four Squares Estate [D]. The Major Works Monitoring Group will monitor the action plan and progress [D], while £5m was identified for Marden and Layard security works [P44].
Written from the decision and the officer reportPDF Pro
OutcomeNotedThe group will monitor the action plan and progress [D]
MoneyNo resource implications [P48]Delivering the recommendations has no resource implications [P48]
What happens nextQuarterly and annual monitoring [P13]Cabinet Member receives quarterly reports; Cabinet receives annual review [P13]
Who it affectsTenants, leaseholders and residents [P8]Changes focus on delivery, transparency and resident communication [P12] [P35]
What was decided
Southwark Cabinet acknowledged and accepted the scrutiny response covering unfinished security work at Four Squares Estate. Report P1
The action plan and delivery progress will be monitored through the Major Works Monitoring Group. Report P2
The group will approve quarterly reports for the Cabinet Member for Housing and annual reports for Cabinet. Report P17
Why
Housing services accepted all 10 recommendations arising from significant contract management issues identified by the scrutiny review. Report P7, P10, P21
Earlier cost overruns meant the security works could not be delivered, and residents were not told clearly about programme changes. Report P8
The response combines open programme monitoring, a separate major works team and resident involvement to improve contract management. Report P12, P14, P15, P19
What happens next
The first quarterly monitoring report is due in July 2011, with an annual report also going to Cabinet. Report P23
Cabinet is due to agree the draft five year capital programme in October 2011 after further consultation with residents. Report P39
The Strategic Director of Communities, Law and Governance will prepare a report for the next Standard Committee meeting. Report P41
The money
£5m Resources identified for security works at Marden and Layard Squares Report P44
over £50,000 Additional housing expenditure highlighted to the Cabinet Member Report P29
£1 million or more Finance Director approval threshold for contract variations, with the proposed variation above 10% Report P26, P55
over £3.9 million Previous European Union threshold for contract variation arrangements Report P26, P55
£250,000 or more Forecast variance requiring reports to the Finance Director and Cabinet after the threshold was reduced from 15%, with 10% or more also required Report P56
in the region of £14,700 each Expected leaseholder service charges for communal works Report P59
a total of just over £1.1 million Expected total leaseholder service charges Report P59
about £12,300 Service charges invoiced under previous phases at Lockwood and New Place Squares Report P59
Options considered
Chosen: Quarterly reporting, spending controls and capital virements. Quarterly reporting and Cabinet engagement were agreed, with contract and financial standing orders applied. Report P22, P23, P24, P25, P28, P29, P52
Chosen: Professional contract monitoring. The Major Works Monitoring Group meets monthly and monitors expenditure, performance and delivery timing. Report P30, P31
Chosen: Early action on significant overspend. Quarterly and monthly reviews should identify issues early and prompt action. Report P32, P33
Chosen: Timely communication of scheme changes. A communication plan will explain the reason, impact and proposed action with timescales. Report P34, P35
Chosen: Resident involvement in project teams. Each new major works scheme will include residents, officers and the contractor from design through site monitoring. Report P36, P37
Chosen: Member approval of programme changes. After the programme is agreed, changes will need member approval and appear in quarterly reports. Report P38, P39
Chosen: Review of the member and officer protocol. A report will be prepared for the next Standard Committee meeting. Report P40, P41
Chosen: Resources for Marden and Layard Squares. Cabinet identified £5m to complete the security works from 2012/13. Report P42, P44
Implications
Financial: Delivering the recommendations has no resource implications. Report P48, P54
Financial: Most of the £5 million budget is for communal works, and leaseholders can expect service charges in the region of £14,700 each, a total of just over £1.1 million. Report P59
Legal: A section 20B notice is required for extra rechargeable costs, and section 20 consultation is required for previously unspecified additional works before authorisation where possible. Report P60, P61, P62
Legal: Further changes to Contract Standing Orders require Council Assembly agreement. Report P51
Staffing: A new Head of Major Works is being appointed and a new major works team is being put in place. Report P14
Risk: Closer monitoring will identify issues early and challenge contractors on quality, budget and value for money. Report P16, P33
Equalities: The major works service is universal for all tenants and residents of the borough, with a stronger customer focus. Report P46
Other: Working groups and project teams will involve residents in shaping and monitoring major works. Report P15, P37
Who and where
Tenants and leaseholders affected by housing major works contract management Report P8
Four Squares residents affected by unfinished security work and later programme changes Report P8, P35
Council residents receiving major works under the five year housing investment programme Report P12
26 leaseholders in Layard Square, 16.7% of 156 flats Report P59
49 leaseholders in Marden Square, 26.5% of 185 flats Report P59
Leaseholders facing extra rechargeable costs or previously unspecified additional works Report P60, P61, P62
Contractors subject to closer monitoring and ongoing challenge on quality and value Report P16, P18
Cabinet Members receiving reports, notifications and decisions on significant spending Report P22, P23, P24, P26, P29
Timeline
April 2011: The sub committee completed its investigation into unfinished security work. Report P4
Monday 18 April 2011: The Overview and Scrutiny Committee agreed the final scrutiny report. Report P4
May 2011: Council Assembly agreed changes to contract standing orders. Report P25, P51
31st May 2011: Cabinet approved the draft five year capital programme and identified £5m for Marden and Layard security works. Report P39, P44
July 2011: The first quarterly monitoring report is due. Report P23
October 2011: Cabinet is due to agree the capital programme after further resident consultation. Report P39
2012/13: Security works at Marden and Layard Squares are due to commence. Report P44
2026-05-28: Cabinet considered and accepted the scrutiny response.
Plain English for the jargon
Major works: Housing work managed separately from day to day repairs and maintenance [P14]
Major Works Monitoring Group: Senior officers who monitor delivery and approve reports for the Cabinet Member and Cabinet [P17]
Contract Standing Orders: Council rules setting approval and notification thresholds for contract changes [P25] [P51]
Capital virement: A budget change controlled through financial standing orders [P29] [P52]
Partnering team: A project team including residents, officers and the contractor [P37]
Quarterly Capital Monitoring Report: The report setting out budget spending, work timing and contractor performance [P13] [P28]
Section 20B notice: A notice required where extra costs can be recharged to leaseholders [P61]
Service charge: A charge to leaseholders for communal works [P59]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12
Resolved
That the response to the recommendations of the housing and community safety scrutiny sub-committee’s investigation into the unfinished security work on the Four Squares Estate be noted and agreed. 2. That the ongoing monitoring of the action plan and progress take place at the major works monitoring group chaired by the strategic director for housing services.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 8 pages
Recommendations
1. Note and agree the response to the recommendations of the Housing and Community Safety Scrutiny sub-committee’s investigation into the unfinished security work on the Four Squares Estate.
2. Agree that the ongoing monitoring of action plan and progress takes place at the Major Works Monitoring Group chaired by the Strategic Director for Housing Services.
BACKGROUND INFORMATION
3. In April 2011, the Housing and Community Safety Scrutiny sub-committee completed its investigation in to the unfinished security work on the Four Squares Estate. Overview and scrutiny committee considered and agreed the final scrutiny report at its meeting on Monday 18 April 2011. The report was presented to Cabinet by the Cabinet Member for Housing on 17 May 2011 where it was 1 resolved that the Cabinet Member would report back in more detail to a future Cabinet.
4. As part of their review the sub-committee interviewed all the relevant parties to the previous works involved in the contract.
Report summary
5. The sub-committee identified significant issues with the contract management of the scheme and made a series of key recommendations.
6. The quality of the contract management of major works is an issue that concerns both tenants and leaseholders. The primary concern of residents at Four Squares was that they felt that a commitment had been reneged upon because of cost- overruns on earlier works which meant that the security works could not be delivered. In addition, there had been a lack of communication with residents about changes to the programme.
7. The report sets out a number of recommendations, not only to address the immediate concerns of Four Squares residents about the security works, but also to improve the contract management arrangements moving forward.
8. All the recommendations made by the sub-committee have been accepted by the housing services department. This report contains a detailed response to each of the recommendations and a summary action plan is included in Appendix 1.
Response to recommendations
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.