AI summarySouthwark Cabinet agreed a two year housing programme covering door security, estate action days, external redecoration, communal heating efficiency and repairs compliance. It noted £4m from the heating account surplus for communal heating energy efficiency.
Money£4m heating account surplusFor communal heating energy efficiency measures.
What happens nextDelivery through existing contractsSeparate approvals apply if this is not possible.
Who it affectsResidents, tenants and leaseholdersCharges may rise for new door entry systems.
What was decided
Cabinet noted the consultation responses from residents, staff and unions. Report P2
Cabinet noted £4m from the heating account surplus for communal heating energy efficiency measures. Report P3, P29, P31
Cabinet agreed a two year programme covering door entry and security, estate action days, external redecoration, communal heating energy efficiency measures and Communal Repairs Compliance Officers. Report P4, P9, P45, P46, P47, P48, P49, P50
Why
Most door entry systems were original and nearing the end of their lifecycle, with parts becoming hard to obtain or obsolete. The proposal would upgrade 51 systems and install 20 new systems. Report P13, P14
Estate action days were popular and dealt with communal repairs, housing management and community issues together. Adding external redecoration to planned works was the most cost effective approach and could achieve cost avoidance of up to 50%. Report P17, P22
Communal repairs management was fragmented and sometimes inconsistent, leading to resident concerns and lost cost recovery. The heating measures were intended to improve reliability, reduce energy use and lower carbon emissions. Report P27, P30, P42
What happens next
The proposed works would be delivered through existing contracts. If that was not possible, separate approvals would be required. Report P51
The Communal Repairs Compliance Officer proposal required separate delegated approval from the Head of Human Resources and Strategic Director of Housing and Community Services. It would also have to follow the council's reorganisation procedures. Report P51, P77
Further analysis would assess savings for future budget setting and reporting. External redecoration in the later programme year would follow surveys, with blocks in greatest need included up to the £1m budget. Report P22, P80
The money
£4m Proposed one off use of heating account funding for communal heating energy efficiency Report P29, P31, P59
£726,000 per annum Door entry and security programme Report P12
£307,000 per annum Estate action days environmental improvements programme Report P16
£1m per annum External redecoration programme Report P19
£428,000 per annum Communal Repairs Compliance Officers Report P24
£6m Larger package considered in the HRA rent setting and budget report Report P58
£5.5m Current accumulated heating account surplus Report P31
68 pence per week Additional service charge for new door entry systems Report P13
Options considered
Chosen: Door entry and security programme. It balances upgrades based on breakdowns and obsolete parts with new systems based on formal requests, known incidents and police support. Report P14, P46
Chosen: Estate action days. There was general support, with requests for better coordination and additional estates and street properties. Report P18, P47
Chosen: External redecoration. The proposal was generally supported, although the budget size caused concern. The later programme year depended on surveys, with blocks in greatest need included within the budget. Report P22, P23, P48
Chosen: Communal Repairs Compliance Officers. Consultation views were mixed. The proposal remained subject to the council's reorganisation procedure, full consultation and separate delegated approval. Report P28, P49, P51, P77
Chosen: Communal heating energy efficiency measures. The programme had general support and was expected to improve reliability, reduce costs and save energy. Report P42, P43, P50
Rejected: A stand alone external decorations programme. Adding decoration to existing planned works was the most cost effective approach and could achieve cost avoidance of up to 50%. Report P22
Rejected: CCTV as an alternative security measure. It was not selected for this programme and was suggested for consideration in a future security programme. Report P15, P46
Implications
Financial: Except for heating, programme funding sits in the base budget and is subject to demand, priorities and the wider HRA financial position. The measures are expected to reduce repeat repairs and create future efficiencies. Report P58, P80
Financial: Heating efficiency funding is ring fenced and available for one off use. It aims to reduce future charge pressure from energy price volatility, and reserve movements need approval from the Strategic Director of Finance and Corporate Services. Report P59
Legal: Communal works can be recharged to home owners. Where an individual charge would be more than £250, statutory consultation under section 20 of the Landlord and Tenant Act 1985 is required. Report P60, P82
Staffing: The proposed team would have 18 full time staff. Six posts would use existing resources and 12 would come from redirection, with estates inspected at least six times each week. Report P27
Climate: Heating efficiency measures were expected to reduce energy use and carbon emissions. The new remote control system would allow continuous monitoring and instant warnings of possible failure. Report P30, P38
Equalities: A scoping exercise found no differential effect on any community or protected group. Work specifications would mitigate adverse impacts, while tenant service charges remained eligible for housing benefit. New door entry charges may create difficulties for people on low incomes. Report P55
Risk: Approximately 70% of district plant failures arise within boiler houses. Obsolete burners create a risk of failure that may not be fixed, leaving residents without service. Report P30, P35
Other: The proposed works were to be delivered through existing contracts. Separate approvals would be needed if that delivery route was unavailable. Report P51
Who and where
Council housing residents Report P13, P30, P53
Tenants Report P13, P55, P63
Home owners and leaseholders Report P40, P64, P82
Residents of blocks and street properties Report P17, P18
Housing and Community Services staff Report P28, P44, P65
Unison Report P28, P65
Communal repairs contractors Report P27, P51
Area Housing Forums, Tenants Council and Home Owners Council Report P10, P62, P63, P64
Timeline
29 January 2013: Cabinet approved the HRA rent setting and budget report. Report P6
11 March 2013 to 28 March 2013: Staff and unions were consulted on the Communal Repairs Compliance Officer proposal. Report P65
26 February to 19 March 2013: Area Housing Forums considered the five housing proposals. Report P10, P62
25 March 2013: Tenants Council considered the Area Housing Forum responses. Report P10, P63
24 April 2013: Home Owners Council considered the programme proposals. Report P10, P64
by 2016: The WDS programme aimed for all Southwark homes to meet the minimum decent homes standard. Report P21
24 months after its introduction: Home Owners Council requested an evaluation of the new compliance team's effectiveness. Report P64
2026-05-28: Cabinet agreed the programme and noted the consultation results and the £4m heating account proposal.
Plain English for the jargon
HRA: Housing Revenue Account
CRCO: Proposed role leading communal repairs inspection, contract management, ordering, training and resident engagement.
BEMS: A common remote system for monitoring and controlling communal heating plant.
WDS: The council's Warm, Dry & Safe investment programme.
Dirt Separation: Removing dirt from a heating system using specialist equipment.
Section 20 consultation: Statutory consultation for rechargeable service charges on leasehold properties.
Estate action day: A single day combining communal repairs, housing management and community issue work.
Minimum decent homes standard: A standard the WDS programme aimed for all Southwark homes to meet by 2016.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11
Resolved
That the results of the consultation with residents, staff and unions be noted. 2. That the proposed use of £4m from the heating account surplus on communal heating energy efficiency measures as set out in paragraph 22 of the report be noted. 3. That the proposed programme for door entry and security, estate action days, external redecoration, communal heating energy efficiency measures and the introduction of communal repairs compliance officers as set out in paragraph 31 of the report be agreed.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 12 pages
Recommendations
Cabinet is asked to:
1. Note the results of the consultation with residents, staff and unions.
2. Note the proposed use of £4m from the heating account surplus on communal heating energy efficiency measures as set out in paragraph 22.
3. Agree the proposed programme for door entry and security, estate action days, external redecoration, communal heating energy efficiency measures and the introduction of Communal Repairs Compliance Officers as set out in paragraph 31.
BACKGROUND INFORMATION
4. The 2013/14 Housing Revenue Account (HRA) Rent Setting and Budget Report was approved by cabinet on 29 January 2013. In taking its decision, cabinet recommended that a number of areas identified for the HRA redirection of resources were of particular importance and should be developed into detailed
1 programmes and considered in more detail by residents then be brought back to cabinet in May 2013 for decision.
5. Five areas were identified for further discussion. These were door entry and security, estate action days (environmental improvements), external redecoration, communal repairs compliance officers (to include staff views) and investment in communal heating energy efficiency measures.
6. Each of the above five areas is examined in detail below along with a summary of the feedback received. Where appropriate a two year programme of works to 2015 is attached as Appendices 1A-D. It is worth noting that redirected resources are in the base budget (save for the communal heating efficiency measures), it is therefore possible that further programmes will be developed from 2015-16 and beyond.
7. Consultation commenced with Area Housing Forums on 26 February and concluded on 19 March 2013. Their feedback is attached as Appendix 2. Tenants Council met on 25 March and Home Owners Council on 24 April 2013. A summary of their views is set out in paragraphs 42 and 43 below.
KEY ISSUES FOR CONSIDERATION
Door entry and security - £726,000 per annum
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.