AI summarySouthwark Cabinet approved its Lakanal coroner response report, defined high rises as above 30m, and commissioned a sprinkler feasibility study. The estimated sprinkler retrofit investment was in the region of £59m, but Cabinet commissioned only the feasibility study. [D] [P2] [P4] [D] [P4] [P38]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedFinal Rule 43 response delegated to the chief executive. [P5]
Money£59m retrofit estimate [P38]Possible retrofit cost. No Housing Investment Programme provision exists. [P49]
What happens nextSurvey and feasibility work [D]Sprinkler findings due to Cabinet by November 2013. [P4]
Who it affectsCouncil housing residents [P47]Recommendations affect all residents of the housing stock. [P47]

What was decided

Southwark Cabinet approved the report setting out its proposed response to the Coroner's Rule 43 letter of 28 March 2013. It defined high rise buildings as those above 30m, equating to 10 storeys and above. Report P1, P2

The coroner's recommendations will apply to known lower storey complex blocks with more than one means of escape, along with sheltered housing schemes and temporary accommodation units. Officers will investigate how a full internal stock condition survey could cover the housing stock, including properties sold leasehold. Report P3

Officers will carry out a full feasibility study into sprinkler retrofits in high rise blocks and report to Cabinet by November 2013. The full Rule 43 response is delegated to the chief executive. Report P4, P5

Why

Rule 43A requires the council to respond within 56 days of the report being sent to the chief executive. The response must detail action taken or proposed, or explain why no action was taken. Report P12, P13

Officers said a decision based on the survey of 3 blocks would be premature because the scale and implications were substantial. They recommended a full feasibility study covering each block in Appendix 3. Report P42

Sprinkler guidance in BS 9991:2011 defines high rise buildings as above 30m. The council also recognised that height is not the only fire safety factor and that some sheltered housing residents are vulnerable. Report P26, P60

What happens next

The chief executive is responsible for preparing the full response to the Rule 43 letter. Report P5, P14

Officers will investigate how a full internal stock condition survey could include sold leasehold properties. Report P3, P32

Officers will complete a full feasibility study of sprinkler retrofits, considering block design and existing fire safety features, and report to Cabinet by November 2013. Report P4, P42

The money

  • in the region of £59m Potential investment if all properties had requirements similar to the 3 surveyed blocks. Report P38, P71
  • £7500 per dwelling Estimated average unit cost for works to each of the 3 blocks surveyed. Report P38
  • £3.5m per annum Base budget within the Housing Revenue Account for Fire Risk Assessment testing and remedial works. Report P50
  • £17.5m over five years Base budget available over five years within the Housing Revenue Account. Report P50
  • £14.3m Planned programmes and commitments over the next 5 years against the Fire Risk Assessment budget. Report P50
  • £48m Spent or committed to date on prioritised Fire Risk Assessment works. Report P8
  • £2m Fire safety works tendered for blocks with atriums, including sprinklers. Report P60

Options considered

  • Chosen: Carry out a full feasibility study before recommending sprinkler retrofits. A sample of 3 blocks could not support a programme recommendation. Report P4, P42
  • Rejected: Recommend a sprinkler retrofit programme from the 3 block survey. The scale of the task and its full implications made an immediate recommendation premature. Report P42
  • Chosen: Continue the current strategy for inspecting internal layouts. In dwelling inspection is outside current legislation, and national guidance was still being sought. Report P20, P21, P24
  • Chosen: Investigate a full internal stock condition survey, including sold leasehold property. The council lacks legal access to leasehold interiors, so officers must consider an effective method. Report P3, P32
  • Chosen: Apply recommendations beyond buildings above 30m to known complex and vulnerable housing. Height is not the only fire safety factor, and some sheltered housing residents are vulnerable. Report P3, P60
  • Chosen: Define high rise buildings as above 30m. Sprinkler guidance supports this threshold. Report P2, P26

Implications

  • Financial: Retrofit works would require capital funding with no current Housing Investment Programme provision, plus an unquantified ongoing maintenance commitment. Existing Fire Risk Assessment budget headroom could be used, but only by reprofiling committed programmes. Report P49, P50, P72
  • Financial: The estimated investment is in the region of £59m if all properties had similar requirements to the 3 surveyed blocks. Report P38
  • Financial: Installation and maintenance costs would be service chargeable to leaseholders, and sprinkler work would be rechargeable to leaseholders. Report P31, P39, P54
  • Legal: The council has no automatic right to enter sold leasehold dwellings for sprinkler work. It would need written cooperation and consent from all leaseholders in a block. Report P31, P32
  • Legal: In dwelling inspection is outside current legislation, and the council cannot check leasehold layouts. The council must maintain suitable risk assessments and fire precautions within its control. Report P20, P21, P63, P65
  • Risk: Without sprinkler coverage in every individual property, a system could leave parts of a block unprotected, in some cases up to 50% of the block. Report P31
  • Risk: Building and electrical work would be disruptive. Asbestos would be likely to be disturbed and would need careful management. Report P35, P36
  • Equalities: The recommendations affect all residents of the council's housing stock. Some sheltered housing residents are vulnerable, so low rise units can be a high priority. Report P47, P60

Who and where

  • Residents of lower storey complex blocks, sheltered housing schemes and temporary accommodation units Report P3
  • All residents of the council's housing stock Report P47
  • Leaseholders in sold properties Report P53, P54, P59
  • Occupiers of high rise blocks Report P56
  • Other social housing landlords Report P19
  • London Fire Brigade Report P8, P18
  • Council staff Report P18
  • People whose first language is not English Report P18

Timeline

  • 03 July 2009: The Lakanal fire occurred and six people died. Report P7
  • April 2010: The programme of Fire Risk Assessments for all blocks of five storey and above was completed. Report P8
  • 14 January 2013: The inquest into the Lakanal fire commenced. Report P9
  • 28 March 2013: The jury returned narrative verdicts, and the coroner wrote the Rule 43 letter to Southwark. Report P9, P10
  • 16 April 2013: Initial responses to the recommendations were presented to Cabinet. Report P14
  • 2 May 2013: The final version of the report was dated. Report P77
  • Within 56 days: The council must respond to the coroner, setting out action or explaining why no action was taken. Report P12, P13
  • November 2013: Officers are due to report sprinkler feasibility findings to Cabinet. Report P4

Plain English for the jargon

  • Rule 43: The process through which the coroner sent recommendations to Southwark on 28 March 2013. [P10] [P11]
  • Rule 43A: The requirement for the council to respond within 56 days of the report being sent to the chief executive. [P12]
  • High rise building: A building above 30m, equating to 10 storeys and above. [D] [P2]
  • Fire Risk Assessment: A suitable assessment used to identify appropriate fire precautions for each premises. [P65]
  • Stock condition survey: A full internal survey of housing stock, including sold leasehold property. [P3] [P32]
  • Sprinkler retrofit: Installing sprinkler systems in existing high rise blocks. [P25] [P29]
  • Fire compartmentation: Fire separation features that may be compromised if internal walls have been moved. [P32]
  • Leasehold: A sold property where the council has no automatic right of access and the leaseholder is responsible for the interior. [P31] [P59]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

That the contents of the report which provides detailed information and considerations which will shape the response to the Coroner’s Rule 43 letter of 28 March 2013 be noted and approved. 2. That high rise buildings be defined as being those above 30m, equating to those of 10 storeys and above. 3. That the coroner’s recommendations also apply to known lower storey but complex blocks, i.e. those with more than one means of escape, along with the council’s sheltered housing schemes and temporary accommodation units. 4. That officers investigate how a full internal stock condition survey of the council’s housing stock, that includes those sold leasehold, would be possible. 5. That officers carry out a full feasibility study into the retro-fitting of sprinklers into high rise blocks and report back to cabinet on the findings by November 2013. 6. That the full response to the Rule 43 letter be delegated to the chief executive.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 10 pages

Recommendations

1. That Cabinet notes and approves the contents of this report which provides detailed information and considerations which will shape the response to the Coroner’s Rule 43 letter of 28 March 2013.

2. That the council defines high rise buildings as being those above 30m, equating to those of 10 storey and above.

3. That the coroner’s recommendations also apply to known lower storey but complex blocks, i.e. those with more than one means of escape, along with the council’s sheltered housing schemes and temporary accommodation units. 1 4. That officers investigate how a full internal stock condition survey of the council’s housing stock, that includes those sold leasehold, would be possible.

5. That officers carry out a full feasibility study into the retro-fitting of sprinklers into high rise blocks and report back to cabinet on the findings by November 2013.

6. That Cabinet delegates the full response to the rule 43 letter to the Chief Executive.

BACKGROUND INFORMATION

7. The Lakanal fire on 03 July 2009 in which six people died was a dreadful tragedy and one of the darkest days in Southwark’s recent history. In response to the fire the council made a number of improvements to its management of fire safety, including:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Coroners Rule 43 LetterAppendix 1 3 pages Download
PDF
Proposed detailed response with timescalesAppendix 2 11 pages Download
PDF
List of 10+ storey blocks, other know lower complex blocks, sheltered housing schemes and temporary accommodation unitsAppendix 3 3 pages Download
PDF
Report: Lakanal Inquiry: Coroner's RecommendationsReport 10 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
CH
Councillor Claire HicksonCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, apologies
VW
Councillor Veronica WardCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. Lakanal Inquiry - Coroner's RecommendationsThis decision
  2. Lakanal Inquiry - Coroner's RecommendationsNoted
  3. Lakanal Inquiry - Sprinkler Feasibility StudyNoted
  4. Lakanal Inquiry - Progress with Coroners RecommendationsNoted

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open