Response to the Housing, Environment, Transport and Community Safety Scrutiny Sub-Committee on the Review of Major Works at Draper House

Noted Executive 1 paper

AI summarySouthwark Cabinet agreed nine scrutiny responses on Draper House major works [P1][P6]. The new framework will include termination at will clauses, with payment checks, monthly complaints reviews, capped Draper House leaseholder charges, extra project resources and planned resident communications [P8][P14][P15][P20][P22][P27][P30].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNine recommendations on Draper House major works [P6]
MoneyNot stated
What happens nextImplementation work will proceed [P36]Legal services will support recommendations 4(a) and 4(c) [P36]
Who it affectsDraper House and major works [P3]Leaseholder charges, project management and resident communications [P22][P27][P30]

What was decided

Cabinet noted and agreed the responses to all nine recommendations from the scrutiny investigation into major works at Draper House. Report P1, P3, P6

The agreed responses set rules for contract termination, default notices, subcontractor payment checks and contractor selection. They also require complaints logs and cap leaseholder charges unless new works are added. Contractor performance can be raised through procurement networks and recorded through the Approved List. Report P8, P10, P14, P15, P16, P18, P20, P22, P24

Complex schemes will receive extra project management resources, supported by training and ongoing assessments. New Warm Dry Safe schemes will use planned resident communications, including meetings, newsletters, resident project teams and satisfaction surveys. Report P27, P28, P30, P31, P32

Why

The review followed the mutual conclusion of the Breyer Group PLC contract and concerns raised by residents and leaseholders. Report P3

Effective contract management and monitoring are presented as the best way to secure good contractor performance, compare contracts and identify poor performance. Report P25

Complaint logs and communication routines are intended to prioritise unresolved issues and keep residents informed during major works. Report P20, P30

What happens next

Officers from the contracts team in legal services will work with relevant project teams to implement the agreed responses, particularly 4(a) and 4(c). Report P36

Legal services will investigate a standard subcontractor payment clause for all future contracts. Monthly checks will list subcontracting companies and confirm payments, and quantity surveyors will seek proof before issuing payment. Report P14, P15, P16

The Contractors' framework being procured will include termination at will clauses. Project teams will keep complaints logs current and continue the Warm Dry Safe communications process. Report P8, P20, P30

The money

  • £ 4.3m Threshold above which larger projects require quality evaluation Report P24

Options considered

  • Chosen: Termination at will clauses. New framework contracts will include them. Other contracts will be considered case by case because the clause can increase costs. Report P7, P8
  • Chosen: Default notices for poor performance. Default notices are issued immediately when performance does not meet expectations and are supported by contractor meetings. Report P9, P10
  • Chosen: Standard subcontractor payment terms. Legal services will investigate a standard clause. Monthly checks will review subcontracting and payment, with quantity surveyor proof sought before council payments. Report P13, P14, P15, P16
  • Chosen: Breyer bids and contractor performance information. Qualifying bids must be considered under procurement rules. Existing networks and the Approved List support performance information, with fair and consistent evaluations required for larger projects. Report P17, P18, P23, P24
  • Chosen: Detailed project complaints logs. All projects have a site based complaints log. It is reviewed at monthly site meetings and updated with issues raised by email and other communications. Report P19, P20
  • Chosen: A cap on Draper House leaseholder charges. Leaseholders will not be charged more than the value of the original notices unless new works are added to the contract. Report P21, P22
  • Chosen: Additional project management resources. Complicated schemes will receive extra resources, with a training schedule and individual assessments. An experienced team was appointed at Draper House. Report P26, P27, P28
  • Chosen: Planned resident communications. Every new Warm Dry Safe scheme has a communications process covering letters, survey appointments, team contact details, public meetings, resident teams, newsletters and surveys. Report P29, P30, P31, P32

Implications

  • Financial: Termination at will clauses may increase contract costs where contractor investment is needed. Effective contract management is intended to maintain or reduce costs. Report P8, P25
  • Financial: Draper House leaseholders will not pay more than original notice values unless new works are added to the contract. Report P22
  • Legal: Qualifying bids must be considered under procurement rules unless specific grounds for exclusion apply. Report P18
  • Equalities: Applicants for larger projects must be treated equally and scored consistently without discrimination. PQQ review is limited to submitted information, except objective external information. Report P24
  • Risk: Documentary evidence, performance bonds or parent company guarantees, and liquidated damages can support contract management and protect the council from risk. Report P25
  • Staffing: Complicated schemes will receive additional project management resources, with training and ongoing assessments overseen by the Head of Major Works. Report P27
  • Legal: No additional legal implications were identified. The contracts team in legal services will support implementation. Report P36
  • Other: Complaints logs are reviewed monthly, and Warm Dry Safe schemes include resident meetings, newsletters, project teams and satisfaction surveys. Report P20, P31, P32

Who and where

  • Leaseholders at Draper House Report P21, P22
  • Residents in the Warm Dry Safe programme Report P30, P31, P32
  • Breyer Group Plc and other suppliers meeting selection requirements Report P17, P18
  • Partnering contractors Report P10, P11, P16
  • Subcontractors working on council contracts Report P14, P15, P16
  • Contractors and consultants on the Approved List Report P24
  • Southwark major works project teams Report P27, P28, P33
  • Contracts team in legal services and relevant project teams Report P36

Timeline

  • May 2013: The scrutiny sub-committee completed its Draper House investigation. Report P4
  • 10 June 2013: The Overview and Scrutiny Committee agreed the final scrutiny report. Report P4
  • 16 July 2013: Cabinet received the report and resolved that the Deputy Leader and Housing Management Cabinet Member would report back at a future meeting. Report P4
  • Over the last 9 months: Default notice use increased across the partnering contracts. Report P10
  • 28 November 2013: The final officer report was dated. Report P42

Plain English for the jargon

  • Termination at will: A contract provision whose inclusion can increase costs, particularly where contractor investment is required. [P8]
  • Default notice: A notice issued immediately when contractor performance does not meet expectations. [P10]
  • Partnering contracts: Contracts under which partners work with the council on the housing works programme. [P3][P11]
  • PQQ: Pre Qualification Questionnaire stage, limited to submitted returns except objective external information. [P24]
  • Approved List: List of works contractors and consultants whose performance information can be recorded and supplied to officers. [P24]
  • RPT: Resident Project Team that reviews site progress, spending and quality issues. [P31]
  • Liquidated damages: A set weekly loss, agreed in advance, that the council can claim for project delay. [P25]
  • Performance bond and parent company guarantee: Protections that can be executed to protect the council from risk. [P25]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

That the responses to the recommendations of the housing, environment, transport and community safety scrutiny sub-committee’s investigation into the major works at Draper House be noted and agreed.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 7 pages

Recommendation

1. Cabinet to note and agree the responses to the recommendations of the Housing, Environment, Transport and Community Safety Scrutiny sub- committee’s investigation into the Major Works at Draper House.

BACKGROUND INFORMATION

2. Following the mutual conclusion of the contract with Breyer Group PLC and concerns raised by residents and leaseholders which were brought to the attention of the Chair of the Housing, Environment, Transport and Community Safety Scrutiny Sub-Committee, it was agreed that the committee would carry out a review into the Project Management of Draper House prior to the mutual conclusion and the letting of contracts for housing works under the partnering arrangements.

3. In May 2013, the Housing, Environment, Transport and Community Safety sub- committee completed its investigation. Overview and Scrutiny Committee considered and agreed the final scrutiny report at its meeting on 10 June 2013. The report was presented to Cabinet on the 16 July 2013 where it was resolved that the Deputy Leader and Cabinet Member for Housing Management would report back in more detail to a future meeting.

RECOMMENDATIONS FROM SUB-COMMITTEE/RESPONSE

4. The sub-committee made 9 recommendations, the responses to which are set out below.

a. Termination at will clauses: All major works contracts issued by Southwark council should contain termination at will clauses.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report: Response to the Housing, Environment, Transport and Community Safety Scrutiny Sub-Committee on the Review of Major Works at Draper HouseReport 7 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 11 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. Response to the Housing, Environment, Transport and Community Safety Scrutiny Sub-Committee on the Review of Major Works at Draper HouseThis decision
  2. Response to the Report of the Housing Scrutiny Commission:The Council's work with social landlord partners; the Fair Street/Devon Mansions, Canada and Kirby Estates QHIP major works projects; the revised resident engagement strategy; and temporary accommodation in properties awaiting demolitionNoted
  3. Response to the Housing and Community Safety Sub-Committee's Review of Housing Repairs Key Performance IndicatorsNoted
  4. Response to the Housing and Community Safety Sub-Committee's Review of Unfinished Security Works on Four Squares EstateNoted
  5. Updated Response to the Housing and Community Safety Scrutiny Sub-Committee's Review of Housing Repairs Key Performance Indicators (KPIs)Noted
  6. Response to the Housing and Community Safety Scrutiny Sub-Committee on the Fire Safety Works at Canada EstateNoted

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies