Update on the Proposed Pipeline for the Delivery of 1,500 New Council Homes by 2018

Noted Executive 6 papers

AI summarySouthwark Cabinet noted progress towards 1,500 new council homes by 2018, agreed target rents and the existing property service charge rate, and delegated land and housing acquisitions. An existing £1m regeneration acquisition budget was reported [D][P190].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedTarget rent, current charges and delegated purchases apply [D][P7][P10][P11]
Money£1m regeneration acquisition budget [P190]Already approved for property acquisition [P190]
What happens nextVehicle due 1 April 2015 [D]HRA appraisal results due January 2015 [P4][P5]
Who it affects1,500 new council homes [D]Interim target within the 11,000 programme [D][P3]

What was decided

Cabinet noted progress on the Direct Delivery programme, including the interim target of 1,500 new council homes by 2018 within the 11,000 home commitment over 30 years from 2013 to 2043. It also noted the combined delivery and asset management team, oversight capacity, the completed HRA appraisal, work on a council owned vehicle, the identified sites, the completed community conversation and the Futures Steering Board [D][P3][P4][P5][P6][P12][P13]. Report P3, P4, P5, P6, P12, P13

Authority to acquire land and housing for direct council housing delivery was delegated to the director of regeneration, in consultation with the strategic director of housing and community services and strategic director of finance and corporate services, as a Part 3C scheme. Any proposal to appropriate general fund land to the housing revenue account must return to Cabinet [D][P7][P8]. Report P7, P8

All new build rents will be set at target rent without exception. Fixed tenant service charges will apply at the prevailing rate for existing properties [D][P10][P11]. Report P10, P11

Why

The 2014 Strategic Housing Market Assessment continued to show a need for affordable housing. It recorded an average 2 bedroom flat sold for £360k in 2013 and 18,547 overcrowded households at the 2011 census [P179]. Report P179

The rent and service charge policy was intended to ensure equity among residents and the programme's financial viability. New homes have greater thermal efficiency and lower maintenance and running costs, while realisation of target rents is central to programme viability [P51][P68][P76]. Report P51, P68, P76

Delivery risks include site availability, funding capacity, and skills and expertise. A wholly owned and controlled company is the preferred model for containing financial risk within a separate delivery vehicle [P175][P177]. Report P175, P177

What happens next

The HRA appraisal and a long term housing strategy were to be presented in January 2015, with the draft renewed asset management strategy completed by the end of January 2015. Local options appraisals would follow in consultation with residents during 2015 [P4][P48][P130]. Report P4, P48, P130

Officers were establishing a wholly owned and controlled council vehicle, due to be operational from 1 April 2015 [D][P5][P94]. Report P5, P94

Feasibility work was to establish the capacity of identified sites, while officers identified further sites and developed proposals with residents. The borough wide principles consultation was due to run from January 2015 to September 2015 [P87][P88][P89][P145]. Report P87, P88, P89, P145

The money

  • £1m Approved budget for regeneration property acquisition [P190] Report P190
  • 4.60 / 4.70 Estate Cleaning charge, actual 2014/15 and proposed 2015/16, £pw [P80] Report P80
  • 1.09 / 1.11 Grounds Maintenance charge, actual 2014/15 and proposed 2015/16, £pw [P80] Report P80
  • 1.17 / 1.20 Communal Lighting charge, actual 2014/15 and proposed 2015/16, £pw [P80] Report P80
  • 0.68 / 0.70 Door Entry System Maintenance charge, actual 2014/15 and proposed 2015/16, £pw [P80] Report P80
  • £99.07 and £108.80 Average actual rent and average target rent in 2014/15 [P57] Report P57
  • £4.32 million (£4,322,013) Current OJEU threshold for procurement of works [P109] Report P109
  • £100,000 Market value level above which acquisitions are reserved to Cabinet outside agreed schemes [P187] Report P187

Options considered

  • Chosen: Set all new build rents at target rent without exception. Target rent levels are central to the programme's financial viability [D][P76]. Report P76
  • Rejected: Allow regeneration and under occupancy exemptions for new build rents. No exemptions were proposed for new build stock because financial viability depends on target rent levels [P76]. Report P76
  • Chosen: Apply fixed tenant service charges at the prevailing existing property rate. The policy is intended to ensure equity and financial viability [D][P51][P78]. Report P51, P78
  • Chosen: Delegate site acquisitions through a Part 3C scheme. The council has adequate legal powers, and the scheme allows individual acquisitions to be delegated [D][P7][P187]. Report P7, P187
  • Chosen: Establish a wholly owned and controlled funding vehicle. It is intended to secure future funding capacity, with the preferred model containing financial risk within a separate vehicle [D][P5][P94][P177]. Report P5, P94, P177

Implications

  • Financial: Financial viability depends in large part on realising target rent levels, so no regeneration or under occupancy exemptions were proposed for new build stock [P76]. Report P76
  • Financial: All development costs to date have been contained within the Housing Revenue Account. The report says there are no immediate resource implications from it, although future financial implications will be significant [P182][P192]. Report P182, P192
  • Legal: The Part 3C scheme is intended to allow individual acquisitions to be delegated. Decisions outside an agreed scheme where market value is more than £100,000 remain reserved to full Cabinet [P7][P187]. Report P7, P187
  • Legal: Further legal advice will be provided on any appropriation of land, and any appropriation remains a matter for Cabinet [P187]. Report P187
  • Equalities: The rent and service charge policy is intended to ensure equity among residents while maintaining financial viability [P51]. Report P51
  • Climate: New homes have greater thermal efficiency and lower maintenance and running costs. The New Southwark Plan also sets environmental standards for noise, air quality and the natural environment [P68][P98]. Report P68, P98
  • Risk: Key delivery risks are site availability, funding capacity, and skills and expertise. Officers are developing mitigation measures, and a wholly owned company is preferred to contain financial risk [P175][P177]. Report P175, P177
  • Staffing: The new homes delivery team has 10 established posts, with 2.5 posts vacant. A temporary manager was appointed for 6 months from January 2015 [P27]. Report P27

Who and where

  • Future council tenants Report P10, P11
  • Existing tenants and leaseholders Report P15
  • Residents near new council developments Report P161
  • Tenants and homeowners involved in engagement Report P13, P17
  • Council housing delivery staff Report P27, P123
  • Small and medium sized construction operators Report P110
  • Developers and promoters of private developments Report P90
  • People needing affordable homes in Southwark Report P179

Timeline

  • 2013 to 2043: Commitment period for 11,000 new council homes [D][P3] Report P3
  • 10 October 2014: Housing delivery team formally transferred into the major works team [P26] Report P26
  • 18 November 2014: Cabinet agreed the Charter of Principles [P142] Report P142
  • January 2015: HRA appraisal and long term housing strategy due; borough wide consultation due to start [P4][P130][P145] Report P4, P130, P145
  • 1 April 2015: Council owned delivery vehicle due to become operational [D][P5][P94] Report P5, P94
  • during 2015: Local options appraisals with residents [P48] Report P48
  • September 2015: Borough wide principles consultation due to end [P145] Report P145
  • 2018: Interim target of 1,500 new council homes due [D][P2] Report P2

Plain English for the jargon

  • Direct Delivery programme: Council programme to build new council homes directly [P19][P22]
  • Housing Revenue Account (HRA): Council housing account used for assets, budgets, borrowing and programme costs [P30][P79][P121][P182][P189]
  • Target rent: Rent based on bedroom count, property market value discounted to January 1999, and a local earnings index uplifted by inflation [P64]
  • Futures Steering Board (FSB): Sounding board providing tenant and homeowner perspectives [P13]
  • OJEU: Value threshold above which OJEU compliant procurement applies for works [P109][P111]
  • Part 3C: Constitutional scheme used to delegate land and property acquisitions [P7][P187]
  • Council owned delivery vehicle: Wholly owned and controlled body intended to secure funding capacity and contain financial risk [P5][P94][P177]
  • Local Housing Allowance (LHA): Allowance rates shown for comparison with new build rents [P68]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

That the progress in the direct delivery programme as part of the council’s commitment to build 11,000 new council homes and especially the interim target, of 1,500 homes to be delivered by 2018 be noted. 2. That the continued progress underway within the direct delivery programme, that forms part of the commitment to build 11,000 new council homes over 30 years from 2013 to 2043 be noted, including, as instructed to the strategic director of housing and community services through the 22 July 2014 cabinet report that: · the future programme delivery for new council homes and the ongoing asset management of the existing housing stock has been brought together under the head of major works · the necessary capacity to oversee further programme delivery has been put in place · a comprehensive appraisal of the overall performance of current Housing Revenue Account (HRA) assets has taken place and will be presented to cabinet in January 2015 · work is in progress to establish a wholly owned and controlled council ‘vehicle’ to secure future funding capacity for the programme and subsequent protection and proper use of assets created, to be operational from 1 April 2015. 3. That the identified sites in the schedule and map at Appendix 2 detailed in paragraphs 52-62 of the report be noted. 4. That authority be delegated to t he director of regeneration, in consultation with the strategic director of housing and community services and strategic director of finance and corporate services to acquire land and housing for the direct delivery of new council housing and this be considered as a scheme pursuant to Part 3C of the council's constitution. 5. That it be noted that officers may wish to recommend the appropriation of land held within the general fund to the housing revenue account for the delivery of new council homes and will bring forward these proposals to cabinet for approval. 6. That it be agreed: · that rents for all new build properties will be set at the council’s target rent without exception · to apply fixed tenant service charges for new build properties developed by the council at the prevailing rate for existing properties. 7. That the results of the completed community conversation already reported to November 2014 cabinet on a ‘Charter of Principles’ for governing our approach to engagement on housing investment and renewal be noted. 8. That the continuing role of the futures steering board (FSB) as a valued sounding board, providing important tenant and homeowner perspectives on the delivery of the 11,000 new council homes be noted.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 21 pages

Recommendations

That cabinet:

1. Notes progress in the Direct Delivery programme as part of the council’s commitment to build 11,000 new council homes and especially the interim target, of 1,500 homes to be delivered by 2018.

2. Notes the continued progress underway within the Direct Delivery programme, that forms part of the commitment to build 11,000 new council homes over 30 years from 2013 to 2043, including, as instructed to the strategic director of housing and community services through the 22 July 2014 cabinet report that:

• the future programme delivery for new council homes and the ongoing asset management of the existing housing stock has been brought together under the Head of major works • the necessary capacity to oversee further programme delivery has been put in place • a comprehensive appraisal of the overall performance of current Housing Revenue Account (HRA) assets has taken place and will be presented to cabinet in January 2015

1 • work is in progress to establish a wholly owned and controlled council ‘vehicle’ to secure future funding capacity for the programme and subsequent protection and proper use of assets created, to be operational from 1 April 2015.

3. Notes the identified sites in the attached schedule and map at appendix 2 detailed in paragraphs 52-62.

4. Delegates authority to the director of regeneration, in consultation with the strategic director of housing and community services and strategic director of finance and corporate services to acquire land and housing for the direct delivery of new council housing and this be considered as a scheme pursuant to Part 3C of the council's constitution.

5. Note that officers may wish to recommend the appropriation of land held within the general fund to the housing revenue account for the delivery of new council homes and will bring forward these proposals to cabinet for approval.

6. Agrees:

• that rents for all new build properties will be set at the council’s target rent without exception.

• to apply fixed tenant service charges for new build properties developed by the council at the prevailing rate for existing properties.

7. Notes the results of the completed community conversation already reported to November 2014 cabinet on a ‘Charter of Principles’ for governing our approach to engagement on housing investment and renewal.

8. Notes the continuing role of the Futures Steering Board (FSB) as a valued sounding board, providing important tenant and homeowner perspectives on the delivery of the 11,000 new council homes.

BACKGROUND INFORMATION

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Major works organisational structure chartAppendix 1 1 pages Download
PDF
Direct Delivery SitesAppendix 2 2 pages Download
PDF
Direct Delivery Appraisal SummaryAppendix 3 1 pages Download
PDF
Indicative Rents for Phase 1 SchemesAppendix 4 1 pages Download
PDF
Consultation PlanAppendix 5 13 pages Download
PDF
Report: Pipeline for the Delivery of 1500 New Council HomesReport 21 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 12 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-Fyle MBECommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
DM
Councillor Darren MerrillCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
MS
Councillor Michael SituCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies