Albion Street Regeneration

Noted Executive 7 papers

AI summarySouthwark Cabinet approved a conditional release of 2,260sqm of Albion Primary School land for council homes and made £12m (including fees and contingency) available for a replacement school. [D][P2][P5] It extended the regeneration framework to land around 71 to 75 Albion Street. [D][P7]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNoted2,260sqm may become council homes with Secretary of State consent. [P2][P5]
Money£12m (including fees and contingency) [P2]Budget to replace the school on the remaining site. [P2]
What happens nextNot stated
Who it affectsNot stated

What was decided

Cabinet agreed that 2,260sqm of the Albion Primary School site would be released from education use, subject to Secretary of State consent. £12m (including fees and contingency) would be made available to replace the school on the rest of the site. [D][P2] Report P2

Subject to that consent, the land is to be used for new council homes. The decision authorises its appropriation from Education to Housing. [D][P5] Report P5

Cabinet extended the Albion Street Regeneration Framework to include land around 71 to 75 Albion Street, with a view to a development combining new council homes with other uses. It also noted the consultation response and progress on regeneration. [D][P6][P7][P8][P36] Report P6, P7, P8, P36

Why

The current school site is poorly laid out, inefficient and wasteful of land. It is much larger than needed for a two form entry school, and the rebuild could increase usable external space while reducing running costs. [P18][P19] Report P18, P19

The value of the released land must be used for education purposes as part of the consent process. For this scheme, it will part fund a new two form entry Albion Primary School. [P3] Report P3

The six week consultation on releasing school land had an overwhelmingly positive response. The wider regeneration programme aims to revitalise Albion Street and address the area's declining commercial centre. [P10][P24][P55] Report P10, P24, P55

What happens next

An application for specific consent will be submitted to the Secretary of State following the prescribed six week consultation. The consultation outcome and responses to issues raised will form part of that application. [P6][P74] Report P6, P74

The strategic director of finance and corporate services will source appropriate funding for the new school and update Cabinet through quarterly monitor reports. [P4] Report P4

If consent is granted, officers will appropriate the land from Education to the HRA for new council homes. Historic debt equal to the market value of the land would move from the General Fund to the HRA, which would then meet the related debt charges and eventual repayment. [P5][P62] Report P5, P62

The money

  • £12m (including fees and contingency) Budget to build the new two form entry Albion Primary School. Report P2, P20, P78

Options considered

  • Chosen: Release 2,260sqm from education use for new council homes. Conditional on Secretary of State consent, with £12m (including fees and contingency) provided for the replacement school. Report P2, P5
  • Chosen: Use the released land value for education purposes. The consent process requires the value to part fund a new two form entry Albion Primary School. Report P3
  • Chosen: Extend the framework to land around 71 to 75 Albion Street. The enlarged site could deliver new council homes and other uses. Report P7, P36

Implications

  • Financial: The new school is in the current School Places Strategy capital programme, but the wider primary expansion programme faces a potential funding shortfall. [P60][P61] Report P60, P61
  • Financial: Appropriation would move historic debt equal to the land's market value from the General Fund to the HRA. The HRA would then be responsible for debt charges and eventual repayment. [P62][P81] Report P62, P81
  • Legal: Specific Secretary of State consent is required under Section 77 of the Schools Standards and Framework Act 1998 and Schedule 1 of the Academies Act 2010. There is no guidance on processing time and no guarantee of the outcome. [P21][P23][P71] Report P21, P23, P71
  • Legal: Appropriation is conditional on a declaration of surplus and remains subject to other people's rights in the land. [P70] Report P70
  • Other: Reducing the school site area could affect the quality of pupils' educational experience. The design and land release were consulted on with the school community, whose response was overwhelmingly positive. [P54][P55] Report P54, P55
  • Other: The released land is intended for new council homes. The extended framework is intended for council homes and other uses. [P5][P7][P36] Report P5, P7, P36
  • Financial: Most of the work has no new resource implications and will use existing identified resources. Financial effects for 71 to 75 Albion Street depend on later development proposals. [P57][P59][P63] Report P57, P59, P63
  • Staffing: Staffing and other connected costs will be contained within existing departmental revenue budgets. [P83] Report P83

Who and where

  • Albion Primary School and its pupils Report P2, P54
  • Parents, staff and school governors Report P24, P26, P55
  • Future residents of new council homes Report P5, P52
  • Local residents and people in Rotherhithe Report P10, P48
  • Albion Street Health Centre Report P29, P30, P31
  • Shop tenants on the Albion Street parade Report P30
  • The Finnish Church Report P32, P33
  • The Norwegian Church Report P43, P47

Timeline

  • December 2012: Cabinet agreed the mandate for the Albion Street Regeneration Framework. Report P10
  • October 2013: Cabinet included the former library in the programme for new council homes. Report P28
  • March 2014 and 22 July 2014: The School Places Strategy was reported to include Albion Primary's expansion from one to two forms of entry. Report P17
  • 25 September 2014 to 6 November 2014: The six week public consultation on releasing school land took place. Report P24
  • October 2014: Cabinet agreed to buy the freeholds of three houses at 71 to 75 Albion Street. Report P37
  • 27 November 2014: The report was dated as final. Report P102
  • December 2014; spring of 2015; autumn of 2015: Public consultation, a planning application and building completion were planned for St Olav’s Square. Report P45, P46
  • May 2015; 2016/17 academic year: Final procurement commitment was anticipated, followed by delivery of the new school. Report P26

Plain English for the jargon

  • SoS: Secretary of State for Education, whose consent is required for the land change. [P21][P22]
  • HRA: Housing Revenue Account. It receives the appropriated land and related borrowing costs. [P62][P81]
  • DfE: Department for Education. [P21][P23]
  • SSFA: Schools Standards and Framework Act 1998, cited for school land consent requirements. [P21][P71]
  • CPO: Compulsory purchase order for site assembly. [P44]
  • Appropriation: Changing council land from education to housing under the council's legal powers. [P16][P70]
  • Playing fields: Land in the open air provided for physical recreation. Guidance covers playgrounds, paved areas, seating and teaching areas. [P73]
  • School Places Strategy: The strategy that includes Albion Primary's expansion from one to two forms of entry. [P17]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

That a section of 2,260sqm of the site of the Albion Primary School, shown outlined on the plan at Appendix 1 to the report, be released from education use subject to consent of the Secretary of State and that a budget of £12m (including fees and contingency) be made available to replace the school on the rest of the site. 2. That it be noted that as part of the Secretary of State consent process for change of use of education land, the value of the released land must be used for education purposes, which in this case, for consent purposes, shall be to part fund the provision of a new two form entry Albion Primary School. 3. That the sourcing of appropriate funding to deliver the new Albion School be delegated to the strategic director of finance and corporate services and to update cabinet through the quarterly monitor reports. 4. That subject to the outcome of an application for the consent of the Secretary of State for Education to change the use of the released land, it be agreed that the land shall be used for the delivery of new council homes and to that end the appropriation of the land from education to housing be authorised. 5. That the outcome of the recent public consultation exercise into the principle of releasing the school land and the response to issues raised be noted, which are set out in Appendix 2 to the report, which shall become part of the application for Secretary of State consent. 6. That the scope for the Albion Street Regeneration Framework be extended to include land around 71-75 Albion Street, shown on the plan at Appendix 3 to the report, with a view to delivering a mix use development including new council homes. 7. That progress with delivery of the regeneration of Albion Street as set out in the body of the report be noted.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 11 pages

Recommendations

That cabinet:

1. Agree that a section of 2,260sqm of the site of the Albion Primary School, shown outlined on the plan at Appendix 1, shall be released from education use subject to consent of the Secretary of State and that a budget of £12m (including fees and contingency) shall be made available to replace the School on the rest of the site.

2. Note that as part of the Secretary of State consent process for change of use of education land, the value of the released land must be used for education purposes, which in this case, for consent purposes, shall be to part fund the provision of a new two form entry Albion Primary School.

3. Delegate to the strategic director of finance and corporate services the sourcing of appropriate funding to deliver the new Albion School and to update cabinet through the quarterly monitor reports.

4. Subject to the outcome of an application for the consent of the Secretary of State 1 for Education to change the use of the released land, agree that the land shall be used for the delivery of new council homes and to that end authorises the appropriation of the land from Education to Housing.

5. Note the outcome of the recent public consultation exercise into the principle of releasing the School land and the response to issues raised, which are set out in appendix 2, which shall become part of the application for Secretary of State consent.

6. Agree that the scope for the Albion Street Regeneration Framework is extended to include land around 71-75 Albion Street, shown on the plan at appendix 3, with a view to delivering a mix use development including new council homes.

7. Note progress with delivery of the regeneration of Albion Street as set out in the body of the report.

BACKGROUND INFORMATION

8. The decline of Albion Street as a commercial centre is a matter of concern to people in the area. For several years the council has been working with the local community to address this. The policy background for this work is contained in the adopted Canada Water Area Action Plan, the emerging revised Canada Water Area Action Plan and a report to Cabinet dated December 2012 that agreed the mandate for a project, the Albion Street Regeneration Framework, to revitalise this part of Rotherhithe.

9. The Albion Street Regeneration Framework is structured around four themes:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Albion Primary schoolAppendix 1 1 pages Download
PDF
ConsultationAppendix 2 7 pages Download
PDF
Plan of land around 71-75 Albion StreetAppendix 3 1 pages Download
PDF
Plan of former library Albion StreetAppendix 4 1 pages Download
PDF
Project MandateAppendix 5 12 pages Download
PDF
Plan of St. Olav's SquareAppendix 6 1 pages Download
PDF
Report: Albion StreetReport 11 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 12 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-Fyle MBECommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
DM
Councillor Darren MerrillCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
MS
Councillor Michael SituCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. Albion Street RegenerationThis decision
  2. Disposal of the Rotherhithe Library, Albion Street, London SE16 7HYAgreed
  3. Albion Street Project MandateAgreed
  4. St. Olav's Public Convenience Site, Albion Street resolution to make Compulsory Purchase Order for Site Assembly PurposesAgreed
  5. Acquisition of Freehold Interest in 71, 73 and 75 Albion Street, SE16 and 18 Brunel Road SE16Approved
  6. Rotherhithe Civic Centre, Albion Street, London SE16 7BSDecided

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open