Financial Appraisal Process for Home Owners Affected by Regeneration Schemes
NotedExecutive4 papers
AI summarySouthwark Cabinet noted the revised financial appraisal process for leaseholder rehousing support, with no significant additional capital costs expected. [D] [P16] Applicants will control how their savings are used, and the approach will be included in new regeneration schemes. [D]
Written from the decision and the officer reportPDF Pro
OutcomeNotedApplicants choose how their savings support rehousing options [D]
MoneyNo significant added capital costs [P16]Leasehold acquisition costs are outside this report [P16]
What happens nextPartner action on schemes [D]Reflect it in new schemes; seek agreement for current schemes [D]
Who it affectsHeygate owner occupier leaseholders [P1]Leaseholders affected by regeneration may receive added rehousing options [P1] [P14]
What was decided
The revised financial appraisal process for determining rehousing support options for individual leaseholders affected by regeneration schemes was noted. [D]
Individual applicants will determine how their own savings are applied to their rehousing options. [D]
The approach will be included in arrangements for delivering new regeneration schemes with development partners. [D] Existing development partners will be asked to agree to the approach for current regeneration schemes. [D]
Why
Leaseholders said they needed several workable options to meet differing needs and circumstances. [P8] Report P8
The proposals intend to provide housing options above those in compulsory purchase legislation. [P1] They also aim to put leaseholders in a position to find suitable accommodation on reasonable terms. [P16] Report P1, P16
Six leaseholder meetings were held for Heygate. [P7] A working group met four times and helped develop the proposed policy and assessment criteria. [P9] Report P7, P9
What happens next
The approach will be reflected in arrangements for delivering new regeneration schemes with development partners. [D]
Representations will be made to existing development partners to seek their agreement for current regeneration schemes. [D]
Further reports will go to the Executive setting out costs and allocations between the Council and the commercial development partner. [P16] Report P16
Implications
Financial: The proposals are not expected to create significant additional capital costs. [P16] Report P16
Financial: Leasehold acquisition costs are outside this report, and further reports will set out costs and allocations between the Council and the commercial development partner. [P16] The Heygate decant policy would base Council housing for leaseholders demonstrably unable to secure alternative accommodation on compensation due to be paid by the Council. [P14] Report P16, P14
Legal: Before compulsory acquisition, the Council may use its general power under the Local Government Act 1972 to acquire land, including leasehold interests, by agreement. [P13] Report P13
Legal: Central government confirmation of a compulsory purchase order requires a compelling public interest case. [P2] Public benefit must outweigh private loss, with authorities balancing public intentions against the concerns of people whose land is taken. [P4] [P5] Report P2, P4, P5
Equalities: The proposals directly affect owner occupiers of residential leasehold properties on the Heygate Estate. [P1] There are no implications for business premises. [P1] Report P1
Equalities: The policy concerns households likely to represent a cross section of the community. [P6] Individual rights are considered within the compulsory purchase framework. [P6] Report P6
Other: The proposals are intended to increase the options available to leaseholders who cannot buy on the open market. [P14] They are consistent with the Council's powers as a local housing authority. [P14] Report P14
Risk: Existing development partners are asked to agree to the approach for current regeneration schemes, while new schemes will have it included in delivery arrangements. [D]
Who and where
Individual leaseholders affected by regeneration schemes [D]
Owner occupiers of residential leasehold properties on the Heygate Estate [P1] Report P1
Heygate leaseholders unable to buy on the open market [P14] Report P14
Heygate leaseholders demonstrably unable to secure alternative accommodation [P14] Report P14
Development partners for new and current regeneration schemes [D]
Timeline
April 2004: A smaller leaseholder working group was formed to examine options in more detail. [P8] Report P8
18th May 2004: The Executive agreed early acquisition of Heygate leasehold interests at leaseholders' request. [P7] Report P7
October 2004: The last of the six leaseholder meetings took place. [P7] Report P7
over the last two years: Leaseholder information was available at general exhibition sessions for Heygate residents. [P10] Report P10
31st January 2005: The final version of the report was dated. [P20] Report P20
2026-05-28: Cabinet noted the process, confirmed applicant control of savings, and directed action with development partners. [D]
Since the end of 2002: Six Heygate leaseholder meetings were held, with all estate leaseholders invited. [P7] Report P7
Plain English for the jargon
Financial appraisal: The process for determining suitable rehousing support for each leaseholder [D]
Compulsory purchase order: An acquisition order that central government must confirm on a compelling public interest case [P2]
Decant policy: The Heygate policy offering Council housing to leaseholders who cannot secure alternative accommodation [P14]
Circular 02/03: Guidance requiring public benefit to outweigh private loss where land is taken compulsorily [P2] [P5]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item16
Resolved
That the revised process of financial appraisal to determine the appropriate re-housing support options for individual leaseholders affected by regeneration schemes be noted. 2. That individual applicants should determine the application of their own savings towards their rehousing options be confirmed. 3. That it be ensured that this approach is reflected in the delivery arrangements with development partners for new regeneration schemes, and that representations are made to existing development partners to seek their agreement to adopt the approach for current regeneration schemes.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Ward(s) or groups affected: East Walworth Heygate Estate Leaseholders
From: Strategic Director of Regeneration Strategic Director of Housing
RECOMMENDATION(S)
1. That the Council adopt the policy set out within this report in relation to Leaseholders on the Heygate Estate subject to the terms outlined in paragraphs 18 to 27 of this report.
2. That Officers put the policy into effect with leaseholders on the Heygate Estate; in the case of the comparative value scheme outlined in paragraph 27, further Executive approval to be sought if more than 20 transactions are required.
BACKGROUND INFORMATION
3. The proposals outlined in this report are in support of the regeneration of the Elephant and Castle. The proposed policy is a new approach to Leaseholder issues and relates only to the Heygate Estate, which is central to the regeneration scheme.
4. The proposals follow a series of Council decisions in support of the overall programme which was initiated by the Executive decision of 23rd July 2002 “A fresh start for the Elephant and Castle”. In summary the Council has since that date approved the following matters;
• An initial survey of public attitudes towards the Elephant and Castle and the prospects for its regeneration. • Publication of initial framework for development establishing the Council’s general objectives for achieving comprehensive and sustainable redevelopment of the core area. • An extensive programme of in depth consultation and opinion testing accompanied by an intensive technical testing and development of the framework. • Initial scoping of the early housing programme including identification and consultation upon possible sites. • Adoption in February 2004 of the revised, detailed framework as Supplementary Planning Guidance. • Approval in July 2004 to proceed with procurement of RSL partners to develop the early housing sites. • Approval of commencement of Commercial Partner Selection process.
1 5. In October 2004 the Council issued an invitation to Housing Associations to tender for the development in two or three packages of the early housing sites identified to meet the immediate re-housing needs of the Heygate. The second stage of this selection (due to commence in February 2005) will ask Housing Associations to provide detailed proposals to assist leaseholders affected by the demolition of the Heygate. It is therefore essential that the Council is in a position to include a leaseholder re-housing policy within the stage 2 pack.
6. It follows from this that the policy proposals agreed now by the Executive may have to be varied in light of the responses received from the Housing Associations but the intention is to negotiate an arrangement as close as possible to the terms proposed herein.
KEY ISSUES FOR CONSIDERATION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.