London Borough of Southwark
Cabinet (decommissioned, for the Executive after, Thursday 28 May 2026 at 4.00pm

The Charter School East Dulwich Development Strategy

Agreed Executive 4 papers

AI summarySouthwark Council approved an Education Funding Agency agreement to oversee procurement and construction of The Charter School East Dulwich, with £5,000,000 from its existing capital programme. Procurement needs a separate gateway report, and the director of regeneration may approve the risk transfer agreement.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedCouncil oversees delivery and has approved funding
Money£5,000,000Existing capital programme funding for TCSED
What happens nextSeparate procurement gateway reportRisk transfer approval delegated to director of regeneration
Who it affectsPupils, families, staff and residentsSchool capacity, disability access and equality

What was decided

Southwark Council will enter an Education Funding Agency agreement to oversee and manage procurement and construction delivery of the new school. The site is the existing Dulwich Community Hospital at East Dulwich Grove, London SE22 8PT. Report 1.1

The council approved the use of £5,000,000 from its existing capital programme for the TCSED project.

Authority was delegated to the director of regeneration to formally approve the risk transfer agreement.

Why

The school census and capacity projections showed a shortfall in secondary school places. Without the new school, choice was projected to be severely limited by 2017/18, and demand to exceed supply by 2018/19. Report P11

The new site is planned to be fully wheelchair and disability accessible. The report expects particular benefits for pupils and staff with physical disabilities. Report P13

The equality analysis identified no negative impacts. It recorded no mitigating actions and no equality objectives. Report P34, P36

What happens next

Enter the Education Funding Agency agreement for the school project.

Seek approval for procurement services and works through a separate gateway report.

Formally approve the risk transfer agreement under the director of regeneration's delegated authority.

The money

  • £5,000,000 From the council's existing capital programme for the TCSED project

Implications

  • Financial: The approved TCSED allocation is £5,000,000 from the existing capital programme.
  • Legal: The council will oversee and manage procurement and construction delivery through the EFA agreement. Approval for procurement services and works will follow through a separate gateway report.
  • Risk: The director of regeneration is delegated to approve the risk transfer agreement.
  • Equalities: The project adds secondary school capacity and gives young people, parents and carers more choice. Report P11
  • Equalities: The new site is planned to be fully wheelchair and disability accessible. Report P13
  • Equalities: The new building is expected to advance equality and good relations across ethnic and religious groups. The school's intake area will cover more than the local ward and is intended to benefit all ethnic groups equally. Report P19, P24
  • Equalities: The school will teach boys and girls together and increase mixed gender places without reducing single gender places. Report P28
  • Equalities: The school is expected to have robust policies on homophobic and transphobic bullying, with monitoring by school authorities. Report P31

Who and where

  • Young people in Southwark Report P9
  • Parents and carers Report P9
  • School staff Report P9
  • Pupils with SEND Report P13
  • Pupils and staff with physical disabilities Report P13
  • Transgender, gay, lesbian or bisexual parents and carers Report P15, P31
  • Residents across ethnic and religious groups Report P19, P24
  • Education Funding Agency Report P9

Timeline

  • March 2015: The Department for Education approved the applicant's application to open a new secondary school in East Dulwich. Report 1.1
  • November 2015: The equality analysis was undertaken. Report P5
  • September 2016: The new school was planned to open. Report P15, P31
  • September 2016 to September 2021: The stated period for the permanent facilities contract. Report 1.1
  • 2017/18: Without the school, secondary school choice was projected to be severely limited. Report P11
  • 2018/19: Without the school, projected demand was expected to exceed supply. Report P11
  • January 2019: The report said TCSED would be fully open by this point. Report P28
  • 2026-05-28: Cabinet decided on the EFA agreement, £5,000,000 capital allocation and delegated authority.

Plain English for the jargon

  • TCSED: The Charter School East Dulwich school and project.
  • EFA: Education Funding Agency.
  • SEND: The report's term for a pupil group positively affected by the school development.
  • Gateway report: The separate approval route for procurement services and works.
  • Risk transfer agreement: The agreement delegated to the director of regeneration for formal approval.
  • Equality analysis: The assessment of possible positive and negative impacts on equality groups.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17

Resolved

That the council enter into an agreement with the Education Funding Agency (EFA) for the council to oversee and manage the procurement and construction delivery of the new The Charter School East Dulwich (TCSED) which is to be developed on the site of the existing Dulwich Community Hospital (East Dulwich Grove, London SE22 8PT) on the terms described in paragraphs 13-19 of the report. The approval for procurement of services and works for TCSED project will take place under a separate gateway report. 2. That the use of £5,000,000 from within the council’s existing capital programme for the TCSED project as described in paragraph 35 of the report be approved. 3. That authority be delegated to the director of regeneration to formally approve the risk transfer agreement as described in paragraph 19 of the report.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 10 pages

Equality analysis

The Charter School East Dulwich development strategy and procurement strategy November 2015

1 Section 1: Equality analysis details

Proposed policy/decision/business plan The Charter School East Dulwich development strategy to which this equality analysis relates and procurement strategy

Equality analysis author Ric Euteneuer, Principal Strategy Officer x 55018 David Quirke-Thornton, Strategic Director of Children’s and Adults’ Strategic Director: Services Department Children’s & Adults’ Services Division Pupil Access Period analysis undertaken November 2015 Date of review November 2016 Sign-off Position Date

Section 2: Brief description of policy/decision/business plan

1.1Brief description of policy/decision/business plan In March 2015, the Department for Education (DfE) approved The Charter School Educational Trust’s application to open a new secondary school in East Dulwich. Cabinet are being asked to approve the Council entering into an Agreement with the Education Funding Agency (EFA) to oversee and manage the procurement and construction delivery of the new The Charter School East Dulwich (TCSED) which is to be developed on the site of the existing Dulwich Community Hospital; the plan also requests that Cabinet approve the appointment of design consultants in order to develop a master plan scheme for the whole of TCSED site, approve a procurement strategy for demolition works to enable the temporary and permanent facilities for TCSED development, and for temporary school accommodation for TCSED, and for permanent facilities for TCSED development contract for the period of September 2016 to September 2021.

Section 3: Overview of service users and key stakeholders consulted

2. Service users and stakeholders Key users of the department or Young people in Southwark service Parents and carers Parents and carers School staff Key stakeholders were/are Governors involved in this policy/decision/ Children’s and Adults’ Services Staff business plan Council Members Education Funding Agency (EFA) Section 4: Pre-implementation equality analysis

This section considers the potential impacts (positive and negative) on groups with ‘protected characteristics’, the equality information on which this analysis is based and any mitigating actions to be taken.

Age - Where this is referred to, it refers to a person belonging to a particular age (e.g. 32 year olds) or range of ages (e.g. 18 - 30 year olds). Potential impacts (positive and negative) of proposed policy/decision/business plan A greater amount of choice for young people (11-18), parents (18+) and carers in the area around the school, as the procurement and development of the school adds capacity to local secondary provision. Equality information on which above analysis is based Schools Census 2015, pupil roll projections and existing school capacity show that there will be a shortfall of places. The table below shows that, without the Charter School East Dulwich opening, choice will be severely limited by 2017/18 and demand will exceed supply by 2018/19 if the school does not open as scheduled. GLA projections 2015 2015 2016 2017 2018 2019 2020 2021 Difference in year 7 classes between 10 5 1 -4 -6 -14 -11 supply and projected demand

2 Mitigating actions to be taken No negative impacts identified, so no mitigating actions required

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Background document: Equality Analysis TCSEDReport 10 pages DownloadRead as text
PDF
Background document: TCSED Proposed Programme and phasingReport 1 pages Download
PDF
Full page version of the table: Charter School East Dulwich: Project Management groups structureReport 1 pages Download
PDF
Report: The Charter School East DulwichReport 11 pages Download

At this meeting

Whole meeting

Who was there

10 of 13 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
SC
Councillor Stephanie CryanCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
DM
Councillor Darren MerrillCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
MS
Councillor Michael SituCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
DC
Deborah CollinsOfficer, expected
EK
Eleanor KellyOfficer, expected

All 13 on the meeting page

On this subject at Southwark

Search all
  1. The Charter School East Dulwich Development StrategyThis decision
  2. Gateway 2 - Contract Award Approval - The Charter School East Dulwich (TCSED) - Phase 1 works contractApproved
  3. Report on retrospective decision for The Charter School East Dulwich (TCSED) - Enabling worksNoted

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open