CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Southwark
Cabinet (decommissioned, for the Executive after, Thursday 28 May 2026 at 4.00pm

Major Works Status Report incorporating Warm, Dry and Safe

Noted Executive 2 papers

AI summaryCabinet noted WDS progress, commitments and the kitchen and bathroom guarantee's first year. [D] The housing stock's decency level was 91.3%, over 30,000 properties had received or were receiving works, and over £130m in Greater London Authority funding had been drawn down. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCurrent WDS commitments were also noted. [D]
Moneyover £130m GLA funding [D]Drawn down to help deliver the programme. [D]
What happens nextSend report after approval [D]Home Owners’ Council, Tenant Council and Future Steering Board. [D]
Who it affectsCouncil housing stock [D]Over 30,000 properties had received or were receiving works. [D]

What was decided

Cabinet noted the status of the housing investment programmes at the end of March 2016, with particular reference to the WDS standard. It also noted the current WDS commitments and the first year of the kitchen and bathroom guarantee being delivered alongside WDS investment.

Cabinet noted that the housing stock stood at a 91.3% decency level at the end of 2015/16, compared with the pre-WDS figure of 56% in April 2010. It also noted that over 30,000 properties had received works or were in the process of receiving works at the end of March 2016.

Cabinet noted that over £130m of Greater London Authority funding had been drawn down to help deliver the programme.

Why

Most WDS schemes planned to 2014/15 were complete or on site, and most of the remaining schemes were on site. Report P26, P28

At Four Squares, a structural survey identified work outside the original funding estimate, so additional HINE money was agreed. Report P4

The individual heating programme was brought forward to replace inefficient boilers, deliver earlier savings and tackle fuel poverty. Report P12

What happens next

After Cabinet approval, the report will be sent to Home Owners’ Council, Tenant Council and Future Steering Board.

The first year of the kitchen and bathroom guarantee will be delivered alongside WDS investment.

Heating works for Leysdown Boiler House boiler, Soane House Boiler House boiler and Acorn Mains were to be committed in 2016/17. Report P17, P23

The money

  • over £130m Greater London Authority funding drawn down to help deliver the programme.
  • £226.1m Actual spend to March 2016 on WDS estates and WDS street properties. Report P28
  • £82.8m Partnering contracts ending, which caused delays in the two year programme. Report P72
  • £26.6m Originally set aside for Four Squares, including HINE funding. Report P4
  • £20.7m Individual heating boiler replacement programme. Report P13
  • £16.1m District heating programme. Report P17
  • £15.1m Minor voids programme. Report P61, P64
  • £11.1m Lift refurbishment programme. Report P60

Options considered

  • Chosen: Enhanced refurbishment scheme at Four Squares. It followed an options appraisal, and a later condition survey found structural problems. Report P4
  • Chosen: Disposal of void properties at Four Squares. It was to contribute to the value of £9m. Report P4

Implications

  • Financial: Over £130m of Greater London Authority funding had been drawn down to help deliver the programme.
  • Other: At the end of 2015/16, the housing stock's decency level was 91.3%, and at the end of March 2016 over 30,000 properties had received works or were in the process of receiving works.
  • Financial: At Four Squares, structural work outside the original funding estimate required additional HINE money, which was agreed. Report P4
  • Risk: Some two year programme works were delayed by the ending of £82.8m partnering contracts. Report P72
  • Risk: All substantial fire risk blocks and the higher risk medium blocks were complete. Report P76
  • Equalities: More efficient boilers were intended to deliver earlier savings and tackle fuel poverty. Report P12
  • Other: The first year of the kitchen and bathroom guarantee was to be delivered alongside WDS investment.
  • Risk: All scheduled lifts were complete, and the programme was intended to improve lift performance and reliability. Report P58, P59, P60

Who and where

  • Council housing stock
  • Over 30,000 properties
  • Residents in WDS estates and WDS street properties Report P24, P25, P28
  • Residents at Four Squares (New Place Estate) Report P3, P4, P5
  • Residents in historic blocks covered by fire risk assessments Report P73, P74, P76
  • Residents facing fuel poverty Report P12
  • Residents served by district heating Report P14, P15, P17
  • Residents affected by lift service failures Report P58

Timeline

  • April 2010: The pre-WDS housing stock figure was 56%.
  • end of 2015/16: Housing stock stood at a 91.3% decency level.
  • end of March 2016: Over 30,000 properties had received works or were in the process of receiving works.
  • end of March 2016: Over £130m of Greater London Authority funding had been drawn down.
  • 2016/17: Heating works for Leysdown Boiler House boiler, Soane House Boiler House boiler and Acorn Mains were to be committed. Report P17, P23
  • 2016/17: Aylesbury Phase 2 was due to complete. Report P31
  • 2016/17: Sidmouth House was due to start. Report P79
  • 2017/18: Acorn Estate regeneration proposals were to be finalised before full works. Report P31

Plain English for the jargon

  • Warm, Dry and Safe (WDS): The housing investment programme and standard covering works to homes and blocks. [P2] [P24] [P25] [P28]
  • Kitchen and bathroom guarantee: The guarantee whose first year was to be delivered alongside WDS investment. [D]
  • High Investment Needs Estate (HINE): An estate designation used for additional funding for major works. [P3] [P4]
  • Building Management Systems (BEMS): Systems that monitor and control services such as heating for maximum efficiency and economy. [P20] [P21]
  • Fire Risk Assessment (FRA): A review of issues in historic blocks, divided into substantial and moderate categories. [P73] [P74] [P75]
  • Greater London Authority (GLA): The funding body whose support was drawn down to help deliver the programme. [D]
  • Decency level: The reported figure for the housing stock, 91.3% at the end of 2015/16. [D]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14

Resolved

That the status of the housing investment programmes at the end of March 2016 with particular reference to achieving the Warm, Dry and Safe (WDS) standard be noted. 2. That the current warm, dry, safe (WDS) commitments and that the first year of delivering the kitchen and bathroom guarantee being delivered alongside the WDS investment be noted. 3. That it be noted that at the end of 2015/16 the housing stock stood at a 91.3% decency level. The pre-WDS figure was 56% in April 2010. 4. That it be noted that over 30,000 properties had received works or were in the process of receiving works to their homes or blocks at the end of March 2016 as part of the WDS programme. 5. That it be noted that over £130m of Greater London Authority (GLA) funding has been drawn down to help deliver the programme. 6. That it be noted this report will be sent to Home Owners’ Council, Tenant Council and Future Steering Board following cabinet approval.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 35 pages

Pictures of the programmes APPENDIX 1

1 2 3 APPENDIX 2 A review of the WDS programme up to March 2016.

Four Squares (New Place Estate) Status: On site Type of works: WDS plus additional funding as a High Investment Needs Estate (HINE)

Comment: Four Squares is a High Investment Needs Estate. A total of £26.6m was originally set aside to be invested including HINE funding. An options appraisal exercise to determine the scale of works required to the estate and the different approaches that could be taken was carried out. It was decided that an enhanced refurbishment scheme would be undertaken and that void properties on the estate would be disposed of to contribute to the value of £9m. Following the decision, a condition survey was undertaken, and a number of structural problems came to light, including brick slips falling from the towers and the instability of several gable ends. As a result, the Council commissioned a comprehensive structural survey of the Estate which recommended a number of structural works particularly to the south west stair towers of Layard and Marden. The funding estimate for this estate did not include these additional structural works. Additional High Investment Needs (HINE) money has been agreed to carry out the additional work indentified from the structural surveys including structural work to the stair towers and brickwork at roof level, additional concrete repairs, asphalt on balconies and extensive works to waterproof garages (major removal and reinstatement of soft landscaping and boundary walls not originally specified).

Actual spend Area to March 2016 Progress Status / Comments Four Squares Security and On site Four squares started in 2012/13 as WDS (New Place Estate) scheduled. The externals started in early (completion delayed 2014/15 following agreement of additional due to increased scope of works) funding to complete the work identified £13.0m (£25.1m through structural surveys and will be HINE) completed in 2016.

4 Elmington Estate (Drayton / Langland only)

Status: On site Type of works: WDS and additional works to Drayton / Langland only

Comment: This scheme has completed as outlined in the original agreed programme. The schemes budget had been revised and agreed through delegated approval to £2.1m with the additional funding coming from the contingency allowed in the programme but costs are under that budget.

Actual spend Area to March 2016 Progress Status / Comments Elmington Completed Completed. £1.8m

Landlord Obligations (Individual Heating)

Status: Ongoing programme of boiler replacements Type of works: To support the capitalisation of heating works undertaken via the term contractors as part of the ECON contract.

Comment: Additional money was brought forward from our 2015/16 individual heating programme into 2012/13 meaning inefficient boilers were replaced with more efficient models helping to deliver earlier savings for residents and tackle fuel poverty. Around 9,000 boilers have been replaced from WDS funding. Tadworth House heating has also been completed.

Actual spend Area to March 2016 Progress Status / Comments Landlord Obligations On going There is an on going programme of individual (Individual Heating) £20.7m boiler replacement

5 Landlord Obligations (District Heating)

Status: Ongoing programme of district heating works Type of works: District Heating Works

Comment: The district Heating Programme is substantially committed.

Actual spend Area to March 2016 Progress Status / Comments Landlord Obligations On going All the planned schemes up to the end of (District Heating) 2014/15 are completed. The remaining 15/16 schemes requiring works have been committed with the following exceptions that are to be committed in 2016/17:  Leysdown Boiler House boiler & Soane House Boiler House boiler £16.1m  Acorn Mains

Individual Scheme progress (district heating 2011/12-2015/16)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendices 1 and 2: Major WorksReport 35 pages DownloadRead as text
PDF
Report: Major Works Status Report incorporating Warm Dry and SafeReport 13 pages Download

At this meeting

Whole meeting

Who was there

10 of 12 attended
PJ
Councillor Peter John OBEChair, present
SC
Councillor Stephanie CryanCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
MA
Councillor Maisie AndersonCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
JS
Councillor Johnson SituCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
IW
Councillor Ian WingfieldCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. Major Works Status Report incorporating Warm, Dry and SafeThis decision
  2. Response to the Report of the Housing Scrutiny Commission:The Council's work with social landlord partners; the Fair Street/Devon Mansions, Canada and Kirby Estates QHIP major works projects; the revised resident engagement strategy; and temporary accommodation in properties awaiting demolitionNoted
  3. Report of the Housing Scrutiny Commission: The Council's work with social landlord partners; the Fair Street/Devon Mansions, Canada and Kirby Estates QHIP major works projects; the revised resident engagement strategy; and temporary accommodation in properties awaiting demolitionNoted
  4. Four Squares Estate - Major Works UpdateNoted
  5. Major Works Status Report incorporating Warm, Dry and SafeNoted
  6. Report into Major Works at Draper House (Housing, Environment, Transport and Community Safety Scrutiny Sub-Committee)Noted

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies