Major Works Status Report incorporating Warm, Dry and Safe
NotedExecutive2 papers
AI summaryCabinet noted WDS progress, commitments and the kitchen and bathroom guarantee's first year. [D] The housing stock's decency level was 91.3%, over 30,000 properties had received or were receiving works, and over £130m in Greater London Authority funding had been drawn down. [D]
Written from the decision and the officer reportPDF Pro
OutcomeNotedCurrent WDS commitments were also noted. [D]
Moneyover £130m GLA funding [D]Drawn down to help deliver the programme. [D]
What happens nextSend report after approval [D]Home Owners’ Council, Tenant Council and Future Steering Board. [D]
Who it affectsCouncil housing stock [D]Over 30,000 properties had received or were receiving works. [D]
What was decided
Cabinet noted the status of the housing investment programmes at the end of March 2016, with particular reference to the WDS standard. It also noted the current WDS commitments and the first year of the kitchen and bathroom guarantee being delivered alongside WDS investment.
Cabinet noted that the housing stock stood at a 91.3% decency level at the end of 2015/16, compared with the pre-WDS figure of 56% in April 2010. It also noted that over 30,000 properties had received works or were in the process of receiving works at the end of March 2016.
Cabinet noted that over £130m of Greater London Authority funding had been drawn down to help deliver the programme.
Why
Most WDS schemes planned to 2014/15 were complete or on site, and most of the remaining schemes were on site. Report P26, P28
At Four Squares, a structural survey identified work outside the original funding estimate, so additional HINE money was agreed. Report P4
The individual heating programme was brought forward to replace inefficient boilers, deliver earlier savings and tackle fuel poverty. Report P12
What happens next
After Cabinet approval, the report will be sent to Home Owners’ Council, Tenant Council and Future Steering Board.
The first year of the kitchen and bathroom guarantee will be delivered alongside WDS investment.
Heating works for Leysdown Boiler House boiler, Soane House Boiler House boiler and Acorn Mains were to be committed in 2016/17. Report P17, P23
The money
over £130m Greater London Authority funding drawn down to help deliver the programme.
£226.1m Actual spend to March 2016 on WDS estates and WDS street properties. Report P28
£82.8m Partnering contracts ending, which caused delays in the two year programme. Report P72
£26.6m Originally set aside for Four Squares, including HINE funding. Report P4
Chosen: Enhanced refurbishment scheme at Four Squares. It followed an options appraisal, and a later condition survey found structural problems. Report P4
Chosen: Disposal of void properties at Four Squares. It was to contribute to the value of £9m. Report P4
Implications
Financial: Over £130m of Greater London Authority funding had been drawn down to help deliver the programme.
Other: At the end of 2015/16, the housing stock's decency level was 91.3%, and at the end of March 2016 over 30,000 properties had received works or were in the process of receiving works.
Financial: At Four Squares, structural work outside the original funding estimate required additional HINE money, which was agreed. Report P4
Risk: Some two year programme works were delayed by the ending of £82.8m partnering contracts. Report P72
Risk: All substantial fire risk blocks and the higher risk medium blocks were complete. Report P76
Equalities: More efficient boilers were intended to deliver earlier savings and tackle fuel poverty. Report P12
Other: The first year of the kitchen and bathroom guarantee was to be delivered alongside WDS investment.
Risk: All scheduled lifts were complete, and the programme was intended to improve lift performance and reliability. Report P58, P59, P60
Who and where
Council housing stock
Over 30,000 properties
Residents in WDS estates and WDS street properties Report P24, P25, P28
Residents at Four Squares (New Place Estate) Report P3, P4, P5
Residents in historic blocks covered by fire risk assessments Report P73, P74, P76
Residents served by district heating Report P14, P15, P17
Residents affected by lift service failures Report P58
Timeline
April 2010: The pre-WDS housing stock figure was 56%.
end of 2015/16: Housing stock stood at a 91.3% decency level.
end of March 2016: Over 30,000 properties had received works or were in the process of receiving works.
end of March 2016: Over £130m of Greater London Authority funding had been drawn down.
2016/17: Heating works for Leysdown Boiler House boiler, Soane House Boiler House boiler and Acorn Mains were to be committed. Report P17, P23
2016/17: Aylesbury Phase 2 was due to complete. Report P31
2016/17: Sidmouth House was due to start. Report P79
2017/18: Acorn Estate regeneration proposals were to be finalised before full works. Report P31
Plain English for the jargon
Warm, Dry and Safe (WDS): The housing investment programme and standard covering works to homes and blocks. [P2] [P24] [P25] [P28]
Kitchen and bathroom guarantee: The guarantee whose first year was to be delivered alongside WDS investment. [D]
High Investment Needs Estate (HINE): An estate designation used for additional funding for major works. [P3] [P4]
Building Management Systems (BEMS): Systems that monitor and control services such as heating for maximum efficiency and economy. [P20] [P21]
Fire Risk Assessment (FRA): A review of issues in historic blocks, divided into substantial and moderate categories. [P73] [P74] [P75]
Greater London Authority (GLA): The funding body whose support was drawn down to help deliver the programme. [D]
Decency level: The reported figure for the housing stock, 91.3% at the end of 2015/16. [D]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14
Resolved
That the status of the housing investment programmes at the end of March 2016 with particular reference to achieving the Warm, Dry and Safe (WDS) standard be noted. 2. That the current warm, dry, safe (WDS) commitments and that the first year of delivering the kitchen and bathroom guarantee being delivered alongside the WDS investment be noted. 3. That it be noted that at the end of 2015/16 the housing stock stood at a 91.3% decency level. The pre-WDS figure was 56% in April 2010. 4. That it be noted that over 30,000 properties had received works or were in the process of receiving works to their homes or blocks at the end of March 2016 as part of the WDS programme. 5. That it be noted that over £130m of Greater London Authority (GLA) funding has been drawn down to help deliver the programme. 6. That it be noted this report will be sent to Home Owners’ Council, Tenant Council and Future Steering Board following cabinet approval.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 35 pages
Pictures of the programmes APPENDIX 1
1 2 3 APPENDIX 2 A review of the WDS programme up to March 2016.
Four Squares (New Place Estate) Status: On site Type of works: WDS plus additional funding as a High Investment Needs Estate (HINE)
Comment: Four Squares is a High Investment Needs Estate. A total of £26.6m was originally set aside to be invested including HINE funding. An options appraisal exercise to determine the scale of works required to the estate and the different approaches that could be taken was carried out. It was decided that an enhanced refurbishment scheme would be undertaken and that void properties on the estate would be disposed of to contribute to the value of £9m. Following the decision, a condition survey was undertaken, and a number of structural problems came to light, including brick slips falling from the towers and the instability of several gable ends. As a result, the Council commissioned a comprehensive structural survey of the Estate which recommended a number of structural works particularly to the south west stair towers of Layard and Marden. The funding estimate for this estate did not include these additional structural works. Additional High Investment Needs (HINE) money has been agreed to carry out the additional work indentified from the structural surveys including structural work to the stair towers and brickwork at roof level, additional concrete repairs, asphalt on balconies and extensive works to waterproof garages (major removal and reinstatement of soft landscaping and boundary walls not originally specified).
Actual spend Area to March 2016 Progress Status / Comments Four Squares Security and On site Four squares started in 2012/13 as WDS (New Place Estate) scheduled. The externals started in early (completion delayed 2014/15 following agreement of additional due to increased scope of works) funding to complete the work identified £13.0m (£25.1m through structural surveys and will be HINE) completed in 2016.
4 Elmington Estate (Drayton / Langland only)
Status: On site Type of works: WDS and additional works to Drayton / Langland only
Comment: This scheme has completed as outlined in the original agreed programme. The schemes budget had been revised and agreed through delegated approval to £2.1m with the additional funding coming from the contingency allowed in the programme but costs are under that budget.
Actual spend Area to March 2016 Progress Status / Comments Elmington Completed Completed. £1.8m
Landlord Obligations (Individual Heating)
Status: Ongoing programme of boiler replacements Type of works: To support the capitalisation of heating works undertaken via the term contractors as part of the ECON contract.
Comment: Additional money was brought forward from our 2015/16 individual heating programme into 2012/13 meaning inefficient boilers were replaced with more efficient models helping to deliver earlier savings for residents and tackle fuel poverty. Around 9,000 boilers have been replaced from WDS funding. Tadworth House heating has also been completed.
Actual spend Area to March 2016 Progress Status / Comments Landlord Obligations On going There is an on going programme of individual (Individual Heating) £20.7m boiler replacement
5 Landlord Obligations (District Heating)
Status: Ongoing programme of district heating works Type of works: District Heating Works
Comment: The district Heating Programme is substantially committed.
Actual spend Area to March 2016 Progress Status / Comments Landlord Obligations On going All the planned schemes up to the end of (District Heating) 2014/15 are completed. The remaining 15/16 schemes requiring works have been committed with the following exceptions that are to be committed in 2016/17: Leysdown Boiler House boiler & Soane House Boiler House boiler £16.1m Acorn Mains
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.