Report into Major Works at Draper House (Housing, Environment, Transport and Community Safety Scrutiny Sub-Committee)

Noted Executive 2 papers

AI summaryCabinet noted the Draper House major works recommendations [P1]. Relevant Cabinet members must bring back a report within eight weeks, and Cabinet will review housing works contract letting and the effectiveness of partnering arrangements [P1] [P2].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet response due within eight weeks [P1]
MoneyNot stated
What happens nextReport within eight weeks [P1]Relevant Cabinet members must bring it [P1]
Who it affectsResidents and leaseholders [P5] [P13]Draper House contracts and project management [P2] [P15]

What was decided

Cabinet noted the recommendations from the review of major works at Draper House [D] [P1]. Report P1

Relevant Cabinet members must bring a report to Cabinet within eight weeks to respond to the overview and scrutiny committee [D] [P1]. Report P1

Cabinet will review how decisions are made when letting contracts for housing works under partnering arrangements and review the effectiveness of those arrangements [D] [P2]. Report P2

Why

The scrutiny review arose from extremely poor work by contractor Breyer and poor contract management by Southwark Council [P5]. Report P5

These failures caused significant distress and inconvenience for residents, long delays in completing the works, and additional costs for the council and the Housing Revenue Account [P5]. Report P5

A serious incident that threatened life occurred at the end of November 2012 because of the contractor's works [P5]. Report P5

What happens next

Relevant Cabinet members must bring a report to Cabinet within eight weeks to respond to the overview and scrutiny committee [P1]. Report P1

Cabinet must review decisions on letting contracts for housing works under partnering arrangements and the effectiveness of those arrangements [P2]. Report P2

Options considered

  • Chosen: Include termination at will clauses and use default notices for poor performance. Default notices should be the primary tool for escalating poor performance as soon as substandard performance becomes apparent. Report P9
  • Chosen: Require an acceptable period for primary contractors to pay subcontractors for completed work Report P10
  • Chosen: Consider all future Breyer Group Plc bids for Southwark work. EU Procurement law requires the council to consider them. Report P11
  • Chosen: Keep and regularly review detailed complaints logs during all major works projects. To prioritise issues that need to be resolved for residents. Report P12
  • Chosen: Do not force leaseholders to pay more than the value of the original notices. Council officers are understood to intend this approach. Report P13
  • Chosen: Investigate a formal network with other London Councils for contractor performance information Report P14
  • Chosen: Verify training, qualifications and skills before appointing complex project management teams. Senior managers must be certain that individuals have the required training, qualifications and skills. Report P15
  • Chosen: Strictly follow procedures for communicating with residents and treat failures as serious. New procedures have been put in place. Report P16

Implications

  • Financial: The failures led to additional costs for Southwark Council and the Housing Revenue Account [P5]. Report P5
  • Financial: No Draper House leaseholder should pay more than the value of the original notices they were consulted on [P13]. Report P13
  • Legal: EU Procurement law requires the council to consider all future Breyer Group Plc bids for work in Southwark [P11]. Report P11
  • Risk: Default notices should escalate poor performance early, while detailed complaints logs should be reviewed regularly to prioritise resident issues [P9] [P12]. Report P9, P12
  • Staffing: Senior managers should ensure complex project management team members have the required training, qualifications and skills before appointment [P15]. Report P15
  • Other: Residents experienced significant distress and inconvenience, and a serious incident that threatened life resulted from contractor works [P5]. Report P5
  • Other: Resident communication procedures are already in place, but failures to follow them should be treated as a serious matter by senior managers [P16]. Report P16
  • Other: The procurement team should investigate sharing contractor performance information with other London Councils [P14]. Report P14

Who and where

  • Draper House residents Report P5, P16
  • Leaseholders at Draper House Report P13
  • Southwark Council and its procurement team Report P2, P5, P14
  • The Housing Revenue Account Report P5
  • Major works contractors, including Breyer Group Plc Report P5, P9, P11
  • Subcontractors Report P10
  • Council project management teams Report P15
  • Other London Councils Report P14

Timeline

  • At the end of November 2012: A serious incident that threatened life occurred as a result of the contractor's works [P5]. Report P5
  • 4 February 2013: The issue came before the Overview and Scrutiny Committee [P5]. Report P5
  • 10 June 2013: The Overview and Scrutiny Committee considered and welcomed the final report, and agreed a further recommendation to Cabinet [P6]. Report P6
  • 19 June 2013: The final report was dated and sent to the Constitutional Team [P20]. Report P20
  • within eight weeks: Relevant Cabinet members must bring a report to Cabinet to respond to the overview and scrutiny committee [P1]. Report P1

Plain English for the jargon

  • Termination at will clauses: Clauses that should be included in all Southwark Council major works contracts [P9].
  • Default notices: A primary tool for escalating poor performance at the earliest opportunity [P9].
  • Partnering arrangements: Arrangements used for letting contracts for housing works [P2].
  • Complaints logs: Detailed records kept and regularly reviewed during major works projects [P12].
  • Housing Revenue Account: The council account that incurred additional costs because of the failures [P5].
  • Leaseholder charges: Amounts charged to leaseholders at Draper House [P13].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

That the recommendations of the review of m ajor works at Draper House be noted , and that the relevant cabinet members bring back a report to cabinet, in order to respond to the overview and scrutiny committee, within eight weeks. 2. That cabinet review decision-making for the letting of contracts for housing works under the partnering arrangements and generally review the effectiveness of those arrangements.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 3 pages

Recommendations

1. That the cabinet notes the recommendations of the review of Major Works at Draper House, and that the relevant cabinet members bring back a report to cabinet, in order to respond to the overview and scrutiny committee, within eight weeks.

2. That, in addition, the cabinet be invited to review decision-making for the letting of contracts for housing works under the partnering arrangements and generally review the effectiveness of those arrangements.

BACKGROUND INFORMATION

3. Attached is the final report arising from the scrutiny review of Major Works at Draper House.

4. The Housing, Environment, Transport & Community Safety Scrutiny Sub- Committee undertook to carry out this review after the issue came before the Overview & Scrutiny Committee on 4 February 2013. The primary reasons for the scrutiny arose from the extremely poor quality of the work carried out by the contractor (Breyer) and poor contract management by the council. These factors led to significant distress and inconvenience for residents and long delays in getting the works completed. In addition, the failures led to additional costs being incurred by the council and the Housing Revenue Account. At the end of November 2012, a serious and life-threatening incident occurred as a result of works being carried out by the contractor.

5. The Overview & Scrutiny Committee considered the report at its meeting on 10 June 2013. The committee welcomed the report and the valuable work of the sub-committee. It also agreed a further recommendation to cabinet in respect of the letting of contracts for housing works under the partnering arrangements (paragraph 2 above).

HOUSING, ENVIRONMENT, TRANSPORT & COMMUNITY SAFETY SCRUTINY SUB-COMMITTEE RECOMMENDATIONS

6. The sub-committee’s recommendations are listed below.

1. Termination at will clauses: All major works contracts issued by Southwark council should contain termination at will clauses. 2. Default notices: Default notices should be considered a primary tool for escalating poor performance at the earliest opportunity. Project managers should be encouraged to use them as a matter of course as soon as sub-standard performance becomes apparent.

3. Payment of sub-contractors: In all future contracts the council should stipulate an acceptable period within which the primary contractor must pay sub-contractors for completed work.

4. Breyer: The sub-committee is aware that, due to EU Procurement law, the council must consider all future bids from Breyer Group Plc for work in Southwark. However, the sub-committee recommends that the conclusions of this scrutiny report be kept at the forefront of officers' minds in considering these future bids. We hope that the implications of this recommendation are clear.

5. Complaints logs: During all major works projects, detailed complaints logs should be kept and reviewed on a regular basis to prioritise issues which need to be resolved for the benefit of residents.

6. Leaseholder charges: No leaseholder in Draper House should be forced to pay for more than the value of the original notices on which they were consulted. It is understood that this is already the intention of council officers, but the sub-committee felt it was important to underline this approach in our recommendations.

7. Sharing information: Southwark procurement team should investigate setting up a formal network with other London Councils to share information regarding the performance of construction contractors.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Scrutiny Sub-Committee ReportAppendix 1 12 pages Download
PDF
Report: Report into Major Works at Draper House (Housing, Environment, Transport and Community Safety Scrutiny Sub-Committee)Report 3 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, apologies
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies