AI summarySouthwark Cabinet approved moving council land from housing to planning, then back to housing. [P2] [P3] The change helps 109 new homes proceed, with people whose rights are affected eligible for compensation rather than able to stop work by injunction. [P9] [P17] [P23]
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSupports the scheme of 109 homes, which has planning consent. [P7] [P8]
MoneyNot stated
What happens nextProcure construction through OJEU [P10]The construction contract will use an OJEU process. [P10]
Who it affects109 homes and nearby occupiers [P8] [P29]74 council rented homes, 35 intermediate homes, minor lighting impacts. [P9] [P29]
What was decided
Cabinet confirmed that the council owned land is no longer needed for housing and approved appropriating it for planning purposes. The approval uses section 226 of the Town and Country Planning Act 1990 and section 122(1) of the Local Government Act 1972. Report P2
Cabinet approved appropriating the land back to housing once it is no longer required for planning purposes. The approval uses section 9 of the Housing Act 1985 and section 122(1) of the Local Government Act 1972. Report P3
Why
Minor departures from lighting recommendations create a risk that affected people could seek an injunction, stopping or delaying the scheme and deterring prospective bidders. Report P13, P14
The scheme provides 109 homes, including 74 for council rent and 35 for intermediate housing, supporting the Council's affordable homes commitment. Legal advice says the homes can contribute to economic, social and environmental wellbeing under section 226. Report P5, P8, P9, P53
Appropriation is intended to reduce delay, attract the maximum number of bidders and achieve a lower construction cost. Returning the land to housing also avoids adverse accounting implications. Report P25, P26, P27
What happens next
Complete the appropriation from housing to planning and then from planning back to housing. Report P21, P22, P23
Complete the planning section 106 agreement. The construction contract will be procured through an OJEU process. Report P7, P10
Make budget provision for diminution in value compensation claims and review the budget after the OJEU process is complete. Report P44
Options considered
Chosen: Appropriate from housing to planning. People cannot use an injunction to enforce third party rights over the land during this stage. Report P22
Chosen: Appropriate back from planning to housing. Housing construction can proceed and adverse accounting implications are avoided. Report P23, P27
Rejected: Keep the land for planning purposes. Holding the land for planning purposes may cause adverse financial implications. Report P19
Rejected: Insure against compensation claims. The report says insurance would be costly. Report P17
Rejected: Accept the risk of an injunction. The report says this may be fatal to development or cause significant unquantifiable costs. Report P17
Implications
Legal: After planning appropriation, section 203 can allow building work despite interference with third party rights. Affected people may claim compensation for loss of value but cannot seek an injunction to delay or stop development. Report P17, P54, P65
Financial: The appropriation is intended to have a neutral financial impact. The homes have a significant cost and an approved budget exists, but it will need to provide for compensation claims and be considered in future capital programme setting. Report P44, P69
Risk: The appropriation is intended to reduce delays, encourage the maximum number of bidders and achieve a lower construction cost. Report P25, P26
Risk: The development may have a minor adverse lighting impact on some nearby occupiers. Report P29
Legal: Compensation is based on diminution in value and is calculated under sections 7 and 10 of the Compulsory Purchase Act 1965. If agreement is not possible, the Upper Tribunal (Lands Chamber) determines it. Report P18, P65
Equalities: The council must have due regard to effects on groups sharing protected characteristics. It believes no particular such group will be adversely impacted. Report P42, P43
Financial: Appropriation from the housing revenue account to the general fund transfers debt between accounts. The later reverse appropriation reverses that transfer. Report P45
Legal: Where the land is open space, section 122 requires notice in a newspaper circulating locally for two consecutive weeks and consideration of objections before appropriation. Report P66
Who and where
People whose rights are affected by the development Report P17
Nearby occupiers Report P29
Households taking the 109 new homes Report P8, P9
People needing affordable homes in the borough Report P5
People taking council rented homes Report P9
People taking intermediate housing Report P9
Prospective construction bidders Report P26
Local residents in housing need Report P71
Timeline
22 October 2013: Cabinet approved the Phase 2 housing delivery report, which included this site. Report P6
around 1990: John Carter House was demolished during the North Peckham Estate regeneration. Report P4
25 February 2015: Council Assembly approved the current Council Plan. Report P5
13 July 2016: Section 203 of the Housing and Planning Act 2016 came into force. Report P54
21 April 2017: Planning consent was granted subject to a section 106 agreement for the regeneration. Report P7
25 April 2017: The final officer report was issued. Report P75
2026-05-28: Cabinet made the two stage land appropriation decision.
Plain English for the jargon
Appropriation: Changing the purpose for which a council holds its land. [P17]
Section 122: The Local Government Act 1972 power allowing a council to appropriate land it owns for an authorised purpose when the former purpose is no longer required. [P49] [P52]
Section 203: A Housing and Planning Act 2016 power allowing building work despite interference with rights when the stated conditions are met. [P54] [P65]
Right to light: An example of an unregistered third party right that appropriation can override, leaving a right to compensation. [P17]
Diminution in value: The loss in a property's value used to calculate compensation. [P18]
OJEU: The procurement process stated for the construction contract. [P10]
Section 106 agreement: A condition attached to the planning consent for the regeneration. [P7]
Upper Tribunal (Lands Chamber): The body that determines compensation if affected parties cannot agree. [P18]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12
Resolved
That it be confirmed that the land shown hatched on the plan at Appendix A of the report that is currently held for housing purposes is no longer required for those purposes and the appropriation of the land to planning purposes to facilitate the carrying out of the development proposals for the area in accordance with section 226 of the Town and Country Planning Act 1990 and section 122(1) of the Local Government Act 1972 be approved. 2. That it be confirmed that following completion of the appropriation at paragraph 1 the land shown hatched on the plan at Appendix A of the report will no longer be required for planning purposes and the appropriation of the land to housing purposes in accordance with section 9 of the Housing Act 1985 and section 122(1) of the Local Government Act 1972 be approved.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 8 pages
Recommendations
That Cabinet:
1. confirms that the land shown hatched on the plan at Appendix A that is currently held for housing purposes is no longer required for those purposes and approves the appropriation of the land to planning purposes to facilitate the carrying out of the development proposals for the area in accordance with section 226 of the Town and Country Planning Act 1990 and section 122(1) of the Local Government Act 1972.
2. confirms that following completion of the appropriation at paragraph 1 the land shown hatched on the plan at Appendix A will no longer be required for planning purposes and approves the appropriation of the land to housing purposes in accordance with section 9 of the Housing Act 1985 and section 122(1) of the Local Government Act 1972. BACKGROUND INFORMATION
3. The land in question is shown hatched on the plan at Appendix A. It is owned freehold by the council. It formerly contained six/seven storey high rise social council housing (John Carter House) but was demolished in around 1990 as part of the North Peckham Estate regeneration. Subsequently, it was reserved for the now cancelled cross-river tram project. Whilst undeveloped the land has been subject to fly-tipping and presents an unattractive vista to Commercial Way - an important access route to this part of Peckham.
4. On 25 February 2015 council assembly approved the current Council Plan. This sets out Fairer Future promises one of which is: quality affordable homes. Within this commitment is the policy to improve housing standards and build more homes of every kind. This promise was in fact reinforcing previous policy to directly provide additional housing to meet the need for affordable housing within the Borough.
5. In pursuit of this cabinet has received a number of reports both before and after the Council Plan adoption to deliver new housing sites and the subject site was included in the Phase 2 report approved by cabinet on 22 October 2013. This report contained proposals for around 277 new council homes and followed an earlier report to directly deliver 290 new homes. These initiatives form part of the Council’s aspiration to provide 1,500 new homes by 2018.
6. On 21 April 2017 planning consent was granted subject to the completion of a planning (s106) agreement for the regeneration of the site to provide the following:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Councillor Richard LivingstoneCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
JS
Councillor Johnson SituCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
IW
Councillor Ian WingfieldCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected
Hear about the next one first
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.