CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Southwark
Cabinet (decommissioned, for the Executive after, Thursday 28 May 2026 at 4.00pm

Gateway 1: Procurement Strategy Approval - Leasehold and Ancillary Properties Buildings Insurance

Approved Executive 2 papers

AI summarySouthwark Cabinet approved a strategy to undertake EU procurement for the leasehold and ancillary properties buildings insurance contract, with three years from 1 April 2018, two possible extensions and an estimated value of up to £18m. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFrom 1 April 2018: three years, plus two possible extensions. [D]
MoneyUp to £18m [D]Up to £3.6m per annum, including 12% insurance premium tax. [D]
What happens nextProcure insurance through EU tender [D]Authority delegated to the deputy leader and housing cabinet member. [D]
Who it affectsLeaseholders at 12,900 properties [P15] [P17]Leaseholders and a small number of freeholders. [P97]

What was decided

The Cabinet approved the strategy to undertake an EU procurement for the leasehold and ancillary properties buildings insurance contract.

The term is three years from 1 April 2018, with an option for two twelve month extensions. The total estimated contract value is up to £18m, and the annual estimate is up to £3.6m per annum including 12% insurance premium tax.

The Leader of the Council delegated authority to the deputy leader and cabinet member for housing to award the contract.

Why

Lease terms make Southwark the freeholder responsible for insuring buildings to full value or making suitable alternative arrangements. Report P9, P10

The new tender was needed to maintain cover from 1 April 2013, otherwise the council would breach 12,900 leases. Report P15, P141

Southwark wanted direct insurer relationships after adverse claims and major fires led to threatened price rises, while it had no control over Acumus's renewal process. Report P21, P22

What happens next

Complete TUPE due diligence before tendering, then run the EU open procedure and assess bids using a 70:30 price and quality ratio. Report P33, P83, P90

Before advertising, serve a Section 20 Notice of Intention on all leaseholders, allow 30 days for comments, and send Notices of Proposal before award. Report P63, P64

If tender bids are significantly higher than the current contract price, seek an Acumus price for an additional year and seek a separate Gateway 3 decision before extending. Report P3, P50, P51, P126

The money

  • £18m Total estimated contract value stated in the decision.
  • £3.6m per annum Estimated annual contract value in the decision, including insurance premium tax at 12%.
  • £17m Estimated total contract value in the officer report. Report P2, P14, P125
  • £3.4m per annum Estimated annual cost in the officer report, including insurance premium tax. Report P13
  • £10.2m Three year contract value in the officer report, including insurance premium tax at 6%. Report P13
  • £1.3 and £1.7m annually Reported annual claims experience, apart from the major fires year. Report P26
  • under £1.3m Projected claim costs for 2011/12. Report P27
  • £75,000 Contract standing order threshold for seeking at least 5 tenders. Report P127

Options considered

  • Chosen: EU open competitive tender. The contract is highly specialised with a limited market and must meet EU procurement rules. Report P30, P33, P129
  • Chosen: Contract with a single insurer. This provides a standard approach and funds claims while including claims handling and management. Report P11
  • Rejected: Extend the current Acumus contract. The current route was not preferred because Southwark wanted direct insurer relationships and could not control Acumus's renewal process. Report P21, P22
  • Rejected: Self insurance with a reserve pool. It would require extra specialist staff and leave the council exposed to claim costs and lease requirements. Report P36
  • Rejected: Joint procurement with other authorities. Their lease terms, stock and contract dates differ, and their claims experience could raise Southwark premiums. Report P35
  • Rejected: Do nothing. It would breach 12,900 leases. Report P37
  • Rejected: Allow leaseholders to nominate providers. Under the EU open procedure, leaseholders may suggest insurers during consultation but cannot nominate providers. Report P63, P101

Implications

  • Financial: The contract cost is recovered in full through annual service charges with a neutral Housing Revenue Account effect. The price includes commission for administration; the council pays the insurer in full at the start of the financial year and bears bad debt risk. Claims above a fixed contract sum fall on the insurer. Report P108, P117, P133
  • Risk: The decision states 1 April 2018, up to £18m and up to £3.6m per annum at 12% insurance premium tax, while the report states 1 April 2013, £17m and £3.4m per annum at 6% insurance premium tax. Report P2, P13, P80
  • Legal: All leaseholders must receive statutory Notices of Intention and Notices of Proposal. Leaseholders may also request a cover summary and reasonable facilities to inspect payment evidence. Report P63, P64, P118, P121
  • Legal: TUPE due diligence must be completed before tendering, with the results included in the tender pack. Report P83
  • Staffing: No additional resources are needed because existing Home Ownership staff administer the contract. Report P114, P115
  • Risk: Only four tenders were received previously, and the transition must allow old and new claims to be processed by different insurers. Report P30, P44, P55, P58
  • Equalities: Tenderers must submit equal opportunities, equality and diversity policies for assessment against council policies. Report P104
  • Climate: The report identifies no sustainability issues, and tender information exchanges are planned by email under the paper lite policy. Report P99, P106

Who and where

  • Leaseholders at 12,900 leasehold properties Report P15, P17
  • A small number of freeholders Report P97
  • Leaseholders' mortgagees Report P19
  • Southwark as freeholder and insured party Report P10, P19
  • Leaseholder representatives Report P18, P38, P92
  • Acumus, its underwriters and prospective insurers Report P22, P30
  • Council housing and Home Ownership staff Report P111, P114, P115
  • Local contractors chosen by leaseholders for internal repairs Report P102

Timeline

  • 15 February 2012: Home owners council was consulted. Report P120
  • 17 April 2012: Gateway 1 procurement strategy approval by Cabinet. Report P67
  • 2 May 2012: Issue Notice of Intention. Report P67
  • 6 June 2012: Advertise the contract. Report P69
  • 3 Aug 2012: Tender return deadline. Tender evaluation was due on 31 Aug 2012. Report P73, P75
  • 14 Jan 2013: Gateway 2 contract award report review. Report P76
  • 23 Feb 2013: Contract award. Report P79
  • 1 April 2013: Contract start. The contract completion date was 31 March 2016. Report P80, P81

Plain English for the jargon

  • Gateway 1: Approval of the procurement strategy before tendering. [P61] [P67]
  • Gateway 2: Approval stage for the contract award report. [P76] [P78]
  • Gateway 3: Separate approval route if the current contract is extended. [P3] [P126]
  • EU open procedure: Competitive tender route used for this contract under EU regulations. [P33] [P129]
  • MEAT: Most Economically Advantageous Tender, assessed 70:30 on price and quality. [P90]
  • OJEU: Public notice used to advertise the contract. [P88] [P101]
  • TUPE: Contractor transition issue requiring due diligence before tendering, with no implications for council staff. [P83]
  • Section 20 Notice of Intention: Statutory consultation notice giving leaseholders 30 days to comment. [P63]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item15

Resolved

Decision of the Cabinet 1. That the procurement strategy outlined in the report to undertake an EU procurement for the leasehold and ancillary properties buildings insurance contract for a period of three years commencing 1 April 2018 , with an option to extend for two twelve month extensions, making a total estimated contract value of up to £18m be approved. The estimated total contract value is up to £3.6m per annum (including insurance premium tax at 12%). This takes into account current variables of insurance premium tax. Decision of the Leader of the Council 2. That authority be delegated to the deputy leader and cabinet member for housing to award the contract for the reasons set out in paragraph 12 of the report.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 15 pages

Recommendations

Recommendations for the Cabinet

1. That the cabinet approves the procurement strategy outlined in this report for the leasehold and ancillary properties buildings insurance contract for a period of 3 years, with an option to extend for 2 twelve month extensions, making an estimated contract value of £17m.

2. That the cabinet notes in the event that tender bids are significantly higher than the current contract price, the option to extend the current contract may be exercised and would form the subject of a separate Gateway 3 report. Recommendation for the Leader

3. That the Leader of the council delegates authority to the cabinet member for housing management to award the contract for the reasons set out in paragraph 10.

BACKGROUND INFORMATION

4. The leaseholders and ancillary properties buildings insurance contract relates to flats and maisonettes sold by the council under long lease terms. There are (3) separate policies within the contract covering;

• The main policy where flats have been sold (under the Right to Buy scheme or through other disposals e.g. auction sales, social home buy) • A policy to insure under-leased blocks on a comprehensive basis (there are currently 3) • A much smaller policy relating to mortgaged housing properties - currently (3) premises - where the council is still providing a mortgage.

In addition, the council may need to nominate buildings insurers, as per the terms of houses sold on leases.

5. The terms of the current lease requires the council as the freeholder:

Clause 4 (6) “To insure the building to the full insurance value thereof against destruction or damage by fire, tempest, flood and other risks against which it is normal practice to insure, or to make other appropriate and adequate arrangements and in the event of destruction or, damage by any such risk as aforesaid to rebuild or reinstate the property and the building”

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Background document: Gateway 1 Approval 2012Report 15 pages DownloadRead as text
PDF
Report: Gateway 1: Procurement Strategy Approval Leasehold and Ancillary properties Buildlings InsuranceReport 14 pages Download

At this meeting

Whole meeting

Who was there

9 of 11 attended
PJ
Councillor Peter John OBEChair, present
SC
Councillor Stephanie CryanCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
JS
Councillor Johnson SituCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
IW
Councillor Ian WingfieldCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. Gateway 1: Procurement Strategy Approval - Leasehold and Ancillary Properties Buildings InsuranceThis decision
  2. Gateway 1 – Procurement Strategy Approval -The NestApproved
  3. Gateway 1 - Procurement Strategy Approval - Southwark and Lambeth Barristers FrameworkApproved
  4. Gateway 1 - Procurement Strategy Approval - Framework contracts to provide bailiff services to the Revenues & Benefits and Parking ServicesApproved
  5. Gateway 2: Contract Award Approval - Corporate Insurance Procurement (excluding Property Insurance)Approved
  6. Gateway 1 - Initial Procurement Strategy, Parking and Traffic Enforcement Services ContractAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies