Appointment of Keepmoat for Emergency Works at Ledbury Estate
NotedExecutive2 papers
AI summarySouthwark Cabinet noted Keepmoat's appointment for emergency works at the Ledbury Estate tower blocks. [D] Work includes electrical upgrades, temporary communal heating and hot water, and electric cookers, with a further Cabinet report on future options later in the year. [P10] [P7] [P2]
Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted Keepmoat's appointment for emergency works at Ledbury Estate. [D] [P1]
MoneyNot stated
What happens nextFurther report to Cabinet [D]Options for the towers will follow Arup's final structural report. [D] [P2]
Who it affectsNot stated
What was decided
Cabinet noted that Keepmoat had been appointed for emergency works at the Ledbury Estate tower blocks. Report P1
Cabinet noted that a further report would come later in the year, after Arup's final structural report, and would set out options for the towers. Report P2
Why
Thermal movement in the large concrete panels caused cracking, which broke the compartmentation required for fire safety. The council has used a temporary filling solution to address the problem. Report P4
Gas supplies were terminated as a precaution because potential structural issues could lead to a gas explosion. Report P4
A full electric heating, hot water and cooking solution was considered. The local network and block electrical infrastructure did not have capacity to progress it quickly. A district communal heating and hot water solution was then designed, while Arup's first report confirmed that the blocks were unsuitable for piped gas and bottled gas. Report P5, P6, P7, P13
What happens next
Keepmoat is upgrading the electrical rising mains in each block. This will enable immersion heaters for limited hot water and quick purchase and distribution of electric standalone cookers. Residents have been offered a choice of three cookers, while those with built in electric ovens and gas hobs will be offered an electric hob only. Report P10
Keepmoat will install the officer designed district heating system in each of the four blocks, with a target of completion and operation by mid October. A temporary large boiler will be sited outside the block, with pipework connected to the existing radiator and hot water circuit within each flat. Engineering colleagues are working with UKPN to upgrade, where possible, the local supply network. Report P7, P11, P12
Arup will continue its investigations throughout the blocks and submit a further report at the end of November. The report will detail strengthening during and after construction, any further strengthening required, costing and building life expectancy information. Officers will present a further detailed report to Cabinet after Arup's report, setting out options for future work on the estate. Report P14, P15
Options considered
Rejected: Full electric heating, hot water and cooking. The local network and the block's electrical infrastructure did not have capacity to progress this solution quickly. Report P5, P6
Chosen: District communal heating and hot water solution. Officers designed it for installation and operation by mid October, using a temporary large boiler outside the block and pipework connected to existing circuits. Report P7, P11
Rejected: Piped gas and bottled gas. Arup's first report confirmed that the blocks were unsuitable for a piped gas supply and other gas, including bottled gas. Report P13
Implications
Risk: Cracking in the large concrete panels has broken the required fire safety compartmentation. Report P4
Risk: Gas supplies have been terminated because potential structural issues could cause a gas explosion. Report P4
Risk: Arup considers the blocks unsuitable for piped gas and bottled gas. Report P13
Other: The rising mains upgrade will enable immersion heaters for limited hot water and quick purchase and distribution of electric standalone cookers. Residents have been offered a choice of three cookers. Report P10
Other: Temporary district heating and hot water is planned for each of the four blocks, with a target of operation by mid October. Report P7, P11
Financial: Arup's further report will include costing information. Report P14
Risk: Arup's further report will include building life expectancy information. Report P14
Other: Engineering colleagues are working with UKPN to upgrade the local supply network where possible. Report P12
Who and where
Residents of the four Ledbury Estate tower blocks Report P10, P11
Residents affected by termination of gas supplies Report P4
Residents with built in electric ovens and gas hobs Report P10
Residents offered three electric cookers Report P10
Existing radiator and hot water circuits in each flat Report P7
The four Ledbury Estate tower blocks Report P1, P10, P11
The local supply network Report P12
Timeline
10th August: Arup advised by letter that the blocks were unsuitable for piped gas. Its first report later confirmed that advice and also advised that bottled gas was unsuitable. Report P13
6 September 2017: The final officer report was dated and sent to the Constitutional Team. Report P19, P20
mid October: Target for installing and operating the district heating and hot water system in each of the four blocks. Report P7, P11
end of November: Arup due to submit a further report on strengthening, costing and building life expectancy. Report P14
later in the year: Further detailed Cabinet report due, setting out options for future work on the estate. Report P2, P15
Plain English for the jargon
Keepmoat: The contractor engaged for two pieces of work at the blocks. [P9]
Compartmentation: Fire safety arrangement broken by cracking in the tower blocks. [P4]
District heating: Heating and hot water using a temporary boiler and pipework. [P7]
Electrical rising mains: Electrical systems in each block that are being upgraded. [P10]
Immersion heaters: Heaters for limited hot water after the rising mains upgrade. [P10]
Arup: Carrying out structural investigations and preparing further reports. [P13] [P14]
UKPN: Working with engineering colleagues on possible local supply network upgrades. [P12]
Building life expectancy: Information due in Arup's further report. [P14]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item19
Resolved
That the appointment of Keepmoat for emergency works at the Ledbury Estate tower blocks be noted. 2. That it be noted that a further report will come to cabinet later in the year, following the final structural report from Arup, detailing options for the towers going forward.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 3 pages
Recommendations
1. That cabinet notes the appointment of Keepmoat for emergency works at the Ledbury Estate tower blocks.
2. That cabinet notes that a further report will come to cabinet later in the year, following the final structural report from Arup, detailing options for the towers going forward.
BACKGROUND INFORMATION
3. Cabinet will be aware that thermal movement of the large concrete panels has led to cracking in the tower blocks on Ledbury Estate, which has meant the breakdown of the required compartmentation for fire safety. The council has been, and continues to be, very proactive in dealing with these issues and has undertaken a temporary filling solution to this problem. 4. The blocks have also had their gas supplies terminated as a precautionary measure due to recently identified potential structural issues should there be a gas explosion in the blocks.
5. In seeking an alternative heating and cooking solution, and to bring a sense of normality to residents’ lives, officers considered a switch to full electric heating, hot water and cooking.
6. However, upon further investigation it was found that the local network and the block’s electrical infrastructures do not have the capacity to quickly progress this solution.
7. Officers have now designed a district (communal) heating and hot water solution that can be installed and in operation by mid-October. This will mean that the blocks will have a temporary large boiler sited outside the block on the ground floor. Pipework will be run from these boilers to the blocks and then internally up the blocks and connected to the existing radiator and hot water circuit within each flat.
Current status
8. Keepmoat, as the area major works partnering contractor, has been engaged to undertake two critical pieces of work.
9. Firstly, they are upgrading the electrical rising mains in each block to enable the installation of immersion heaters to provide limited hot water now. This will also enable the quick purchase and distribution of electric standalone cookers. Residents have been offered a choice of three cookers, while those with built in electric ovens and gas hobs will be offered an electric hob only.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.