CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Southwark
Cabinet (decommissioned, for the Executive after, Thursday 28 May 2026 at 4.00pm

Appointment of Keepmoat for Emergency Works at Ledbury Estate

Noted Executive 2 papers

AI summarySouthwark Cabinet noted Keepmoat's appointment for emergency works at the Ledbury Estate tower blocks. [D] Work includes electrical upgrades, temporary communal heating and hot water, and electric cookers, with a further Cabinet report on future options later in the year. [P10] [P7] [P2]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted Keepmoat's appointment for emergency works at Ledbury Estate. [D] [P1]
MoneyNot stated
What happens nextFurther report to Cabinet [D]Options for the towers will follow Arup's final structural report. [D] [P2]
Who it affectsNot stated

What was decided

Cabinet noted that Keepmoat had been appointed for emergency works at the Ledbury Estate tower blocks. Report P1

Cabinet noted that a further report would come later in the year, after Arup's final structural report, and would set out options for the towers. Report P2

Why

Thermal movement in the large concrete panels caused cracking, which broke the compartmentation required for fire safety. The council has used a temporary filling solution to address the problem. Report P4

Gas supplies were terminated as a precaution because potential structural issues could lead to a gas explosion. Report P4

A full electric heating, hot water and cooking solution was considered. The local network and block electrical infrastructure did not have capacity to progress it quickly. A district communal heating and hot water solution was then designed, while Arup's first report confirmed that the blocks were unsuitable for piped gas and bottled gas. Report P5, P6, P7, P13

What happens next

Keepmoat is upgrading the electrical rising mains in each block. This will enable immersion heaters for limited hot water and quick purchase and distribution of electric standalone cookers. Residents have been offered a choice of three cookers, while those with built in electric ovens and gas hobs will be offered an electric hob only. Report P10

Keepmoat will install the officer designed district heating system in each of the four blocks, with a target of completion and operation by mid October. A temporary large boiler will be sited outside the block, with pipework connected to the existing radiator and hot water circuit within each flat. Engineering colleagues are working with UKPN to upgrade, where possible, the local supply network. Report P7, P11, P12

Arup will continue its investigations throughout the blocks and submit a further report at the end of November. The report will detail strengthening during and after construction, any further strengthening required, costing and building life expectancy information. Officers will present a further detailed report to Cabinet after Arup's report, setting out options for future work on the estate. Report P14, P15

Options considered

  • Rejected: Full electric heating, hot water and cooking. The local network and the block's electrical infrastructure did not have capacity to progress this solution quickly. Report P5, P6
  • Chosen: District communal heating and hot water solution. Officers designed it for installation and operation by mid October, using a temporary large boiler outside the block and pipework connected to existing circuits. Report P7, P11
  • Rejected: Piped gas and bottled gas. Arup's first report confirmed that the blocks were unsuitable for a piped gas supply and other gas, including bottled gas. Report P13

Implications

  • Risk: Cracking in the large concrete panels has broken the required fire safety compartmentation. Report P4
  • Risk: Gas supplies have been terminated because potential structural issues could cause a gas explosion. Report P4
  • Risk: Arup considers the blocks unsuitable for piped gas and bottled gas. Report P13
  • Other: The rising mains upgrade will enable immersion heaters for limited hot water and quick purchase and distribution of electric standalone cookers. Residents have been offered a choice of three cookers. Report P10
  • Other: Temporary district heating and hot water is planned for each of the four blocks, with a target of operation by mid October. Report P7, P11
  • Financial: Arup's further report will include costing information. Report P14
  • Risk: Arup's further report will include building life expectancy information. Report P14
  • Other: Engineering colleagues are working with UKPN to upgrade the local supply network where possible. Report P12

Who and where

  • Residents of the four Ledbury Estate tower blocks Report P10, P11
  • Residents affected by termination of gas supplies Report P4
  • Residents with built in electric ovens and gas hobs Report P10
  • Residents offered three electric cookers Report P10
  • Existing radiator and hot water circuits in each flat Report P7
  • The four Ledbury Estate tower blocks Report P1, P10, P11
  • The local supply network Report P12

Timeline

  • 10th August: Arup advised by letter that the blocks were unsuitable for piped gas. Its first report later confirmed that advice and also advised that bottled gas was unsuitable. Report P13
  • 6 September 2017: The final officer report was dated and sent to the Constitutional Team. Report P19, P20
  • mid October: Target for installing and operating the district heating and hot water system in each of the four blocks. Report P7, P11
  • end of November: Arup due to submit a further report on strengthening, costing and building life expectancy. Report P14
  • later in the year: Further detailed Cabinet report due, setting out options for future work on the estate. Report P2, P15

Plain English for the jargon

  • Keepmoat: The contractor engaged for two pieces of work at the blocks. [P9]
  • Compartmentation: Fire safety arrangement broken by cracking in the tower blocks. [P4]
  • District heating: Heating and hot water using a temporary boiler and pipework. [P7]
  • Electrical rising mains: Electrical systems in each block that are being upgraded. [P10]
  • Immersion heaters: Heaters for limited hot water after the rising mains upgrade. [P10]
  • Arup: Carrying out structural investigations and preparing further reports. [P13] [P14]
  • UKPN: Working with engineering colleagues on possible local supply network upgrades. [P12]
  • Building life expectancy: Information due in Arup's further report. [P14]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item19

Resolved

That the appointment of Keepmoat for emergency works at the Ledbury Estate tower blocks be noted. 2. That it be noted that a further report will come to cabinet later in the year, following the final structural report from Arup, detailing options for the towers going forward.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 3 pages

Recommendations

1. That cabinet notes the appointment of Keepmoat for emergency works at the Ledbury Estate tower blocks.

2. That cabinet notes that a further report will come to cabinet later in the year, following the final structural report from Arup, detailing options for the towers going forward.

BACKGROUND INFORMATION

3. Cabinet will be aware that thermal movement of the large concrete panels has led to cracking in the tower blocks on Ledbury Estate, which has meant the breakdown of the required compartmentation for fire safety. The council has been, and continues to be, very proactive in dealing with these issues and has undertaken a temporary filling solution to this problem. 4. The blocks have also had their gas supplies terminated as a precautionary measure due to recently identified potential structural issues should there be a gas explosion in the blocks.

5. In seeking an alternative heating and cooking solution, and to bring a sense of normality to residents’ lives, officers considered a switch to full electric heating, hot water and cooking.

6. However, upon further investigation it was found that the local network and the block’s electrical infrastructures do not have the capacity to quickly progress this solution.

7. Officers have now designed a district (communal) heating and hot water solution that can be installed and in operation by mid-October. This will mean that the blocks will have a temporary large boiler sited outside the block on the ground floor. Pipework will be run from these boilers to the blocks and then internally up the blocks and connected to the existing radiator and hot water circuit within each flat.

Current status

8. Keepmoat, as the area major works partnering contractor, has been engaged to undertake two critical pieces of work.

9. Firstly, they are upgrading the electrical rising mains in each block to enable the installation of immersion heaters to provide limited hot water now. This will also enable the quick purchase and distribution of electric standalone cookers. Residents have been offered a choice of three cookers, while those with built in electric ovens and gas hobs will be offered an electric hob only.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report: Appointment of Keepmoat for Emergency Works at Ledbury EstateReport 3 pages DownloadRead as text
PDF
Report: Ledbury EstateReport 2 pages Download

At this meeting

Whole meeting
3Notice of Intention to conduct business in a closed meeting, and any representations receivedOn the agenda 6MinutesApproved 7Deputation RequestsOn the agenda 8Petition from Southwark Group of Tenant Organisations (SGTO) - Keep the Repairs Line FreeDecided 9Canada Water RegenerationAgreed 10Approval of the Council's Local Implementation Delivery Plan - Annual Spending Submission for 2018-19Agreed 11Review of the Local Offer for Care Leavers: Report from the Education and Children's Services Scrutiny Sub-CommitteeNoted 12Southwark School Scrutiny in a Day: Report from the Education and Children's Services Scrutiny Sub-CommitteeNoted 13Southwark GP Practices: Quality of Provision and Local Support Arrangements: Report from the Healthy Communities Scrutiny Sub-CommitteeNoted 14A Review of Further Education and Skills Provision in the London Borough of Southwark: A report from the Overview and Scrutiny CommitteeNoted 15Social Regeneration - Emerging Framework and Next StepsAgreed 16Gateway 1 and 2: Procurement Strategy and Contract Award Approval - Integrated Community Equipment Service ContractApproved 17Gateway 2: Contract Award Approval - Award of Contracts for the Provision of Sexual Health ServicesApproved 18Borough Wide Fire SafetyNoted
19Appointment of Keepmoat for Emergency Works at Ledbury EstateThis decision
19aLedbury Estate: Report from Overview and Scrutiny CommitteeNoted 20Gateway 3: Variation Decision - Housing Major Works ContractsApproved 21Update on the Delivery of the Housing Asset Management StrategyNoted 22Gateway 3: Variation Decision - Extension to the Consolidated Facilities Management ContractApproved 23Non-domestic Rates - Discretionary Rate Relief Policy for Revaluation Relief, Supporting Small Businesses Relief and Pubs ReliefNoted 24Policy and Resources Strategy: Capital Monitoring Report, including Capital Programme Update 2017-18 (Month 4)Noted 25Acquisition of Future Affordable Housing in BlackfriarsApproved 26Motions referred from Council AssemblyAgreed 27Ofsted Inspection of 'Services for Children in Need of Help and Protection, Children Looked After and Care Leavers' - Post Inspection Action PlanDecided 28Response to Review of Local Offer for Care LeaversApproved 29Gateway 1: Procurement Strategy Approval: Special Educational Needs and/or Disability (SEND) taxis for children, young people and vulnerable adultsOn the agenda 30Policy and Resources Strategy: Revenue Monitoring report, including Treasury Management 2017-18 (Month 4)Noted 32Exclusion of the Press and PublicDecided

Who was there

10 of 13 attended
PJ
Councillor Peter John OBEChair, present
SC
Councillor Stephanie CryanCommittee Member, present
MA
Councillor Maisie AndersonCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
JS
Councillor Johnson SituCommittee Member, present
IW
Councillor Ian WingfieldCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

All 13 on the meeting page

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies