Gateway 3: Variation Decision - Housing Major Works Contracts
ApprovedExecutive1 paper
Cabinet (decommissioned, for the Executive after approved this item on Thursday 28 May 2026. Below is the council's own wording, with the papers it was decided on.
That the variation of Contract area 3, Camberwell and Peckham contract to Keepmoat Regeneration (Apollo) Ltd (Keepmoat) to extend the term of the contract for a period of two years from 14 June 2018 at an estimated maximum cost of £45m per annum, making a revised contract value of £450m for ten years be approved. 2. That the variation of Contract area 4, Nunhead , Peckham Rye and Dulwich contract to A&E Elkins Ltd (A&E Elkins) to extend the term of the contract for a period of two years from 14 June 2018 at an estimated maximum cost of £24m per annum, making a revised contract value of £240m for ten years be approved. 3. That the variation of Contract area 5, Borough-wide street properties, temporary accommodation and major voids contract to Saltash Enterprises Ltd ( Saltash ) for a period of two years from 14 June 2018 at an estimated maximum cost of £6m per annum, making a revised contract value of £60m for ten years be approved.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 11 pages
Recommendations
1. That cabinet approves the variation of Contract area 3, Camberwell and Peckham contract to Keepmoat Regeneration (Apollo) Ltd (Keepmoat) to extend the term of the contract for a period of two years from 14 June 2018 at an estimated maximum cost of £45m per annum, making a revised contract value of £450m for ten years.
2. That cabinet approves the variation of Contract area 4, Nunhead, Peckham Rye and Dulwich contract to A&E Elkins Ltd (A&E Elkins) to extend the term of the contract for a period of two years from 14 June 2018 at an estimated maximum cost of £24m per annum, making a revised contract value of £240m for ten years.
3. That cabinet approves the variation of Contract area 5, Borough-wide street properties, temporary accommodation and major voids contract to Saltash Enterprises Ltd (Saltash) for a period of two years from 14 June 2018 at an estimated maximum cost of £6m per annum, making a revised contract value of £60m for ten years.
BACKGROUND INFORMATION
4. On 26 March 2010, the executive approved the award of five contracts for major works for a period of five years with the option to extend for a further five years,
1 subject to appropriate reviews of value for money and performance, although no reference was made as to the number of extensions that could be incorporated within this five years. Reserve contractor arrangements were also approved.
5. The contract areas were as follows:
Contract Contractor Contract area 1 – Borough and Bankside Breyer Group Plc Contract area 2 – Bermondsey and Rotherhithe Wates Construction Ltd Contract area 3 – Camberwell and Peckham Keepmoat (formerly Apollo Property Services Group Ltd) Contract area 4 – Nunhead, Peckham Rye and A&E Elkins Dulwich Contract area 5 – Borough-wide street properties, Saltash temporary accommodation and major voids
6. Two contracts were ended in 2012 and 2013. The reserve contractor arrangements were therefore put in place for the majority of the programmes to cover Contract areas 1 and 2 - A&E Elkins took over the majority of programmes for Contract area 1 with the remainder of the work being individually tendered and Keepmoat took over all the programmes for Contract area 2. The table is as follows:
Contractor Contract Area Main/Reserve Estimated contractor annual amount A&E Elkins 1 Borough and Bankside and Reserve £16m Walworth Keepmoat 2 Bermondsey and Rotherhithe Reserve £25m Keepmoat 3 Camberwell and Peckham Main £20m A&E Elkins 4 Nunhead, Peckham Rye and Main £8m Dulwich Saltash 5 Borough-wide street properties, Main £6m temporary accommodation and major voids
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.