Contract for refurbishment of Elmsleigh Centre Lifts - Key Decision

Decided Executive 1 paper

Cabinet decided this item on Wednesday 24 January 2018. Below is the council's own wording, with the papers it was decided on.

Item2444

Resolved

Resolved to 1. Authorise the Group Head Regeneration and Growth to determine the contractor to be appointed for refurbishment of the Elmsleigh Centre lifts (in consultation with the Cabinet Member for Planning and Economic Development and the Chief Finance Officer); and 2. Authorise the Head of Corporate Governance to enter into the legal documentation in order to appoint the contractor. Reasons for Decision The Council is in the process of running a tender to appoint a contractor to refurbish three lifts at the Elmsleigh shopping centre Due to the expected duration of the project, Cabinet is being asked to delegate the final decision to the Group Head Regeneration and Growth, Cabinet Member for Planning and Economic Development and the Chief Finance Officer so to ensure that the appointment allows time for the refurbishment works to be completed in advance of the Christmas 2018 trading period
Word for word from the decision Spelthorne published for this meeting. Source: democracy.spelthorne.gov.uk

Follow this further

Built from Spelthorne's papers

What the report saysPro

Report to Cabinet

Cabinet

24 January 2018

Title Contract for refurbishment of Elmsleigh Centre Lifts Purpose of the report To make a Key Decision Report Author Heather Morgan – Group Head Regeneration and Growth Cabinet Member Councillor Colin Barnard Confidential No Corporate Priority Financial Sustainability Recommendations Cabinet to: Authorise the Group Head Regeneration and Growth to determine the contractor to be appointed for refurbishment of the Elmsleigh Centre lifts (in consultation with the Cabinet Member for Planning and Economic Development and the Chief Finance Officer) Authorise the Head of Corporate Governance to enter into the legal documentation in order to appoint the contractor Reason for The Council is in the process of running a tender to appoint a Recommendation contractor to refurbish three lifts at the Elmsleigh shopping centre Due to the expected duration of the project, Cabinet is being asked to delegate the final decision to the Group Head Regeneration and Growth, Cabinet Member for Planning and Economic Development and the Chief Finance Officer so to ensure that the appointment allows time for the refurbishment works to be completed in advance of the Christmas 2018 trading period

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Contract for refurbishment of Elmsleigh Centre Lifts: Key DecisionDecisions 108 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 14 attended
IH
Councillor Ian HarveyLeader, present
TH
Councillor Tony HarmanDeputy Leader, present
MA
Councillor Maureen AttewellCommittee Member, present
CB
Councillor Colin BarnardCommittee Member, present
MF
Councillor Mark FrancisCommittee Member, present
NG
Councillor Nick GethingCommittee Member, present
TM
Councillor Tony MitchellCommittee Member, present
OR
Councillor Olivia RybinskiCommittee Member, present
HW
Councillor Howard WilliamsCommittee Member, present
DM
Daniel MouawadOfficer, present
TC
Terry CollierOfficer, present
LO
Lee O'NeilOfficer, present

All 14 on the meeting page

More from Spelthorne Cabinet

All decisions
MeetingDecisionOutcome
19 May 2021 Psychoactive substances public space protection order - Key DecisionResolved to 1) make a Public Space Protection Order (PSPO) relating to possession and use of Nitrous Oxide, in accord... Approved Open
19 May 2021 Interim Revenue Monitoring Report 2020/21 as at 31 March 2021Resolved to: Note the forecast outturn for 2020/21 as at 31 March 2021, and approve the following: 1. Appropriation o... Noted Open
19 May 2021 Interim Capital Monitoring Report 2020/21 - 31 March 2021Resolved to note the Interim Capital Monitoring Report 2020/21 as at 31 March 2021. Noted Open
19 May 2021 Spelthorne Finance Peer Review Action Plan March 2021Resolved to 1) approve the draft Action Plan, which will be maintained as a living document; 2) recommend that regula... Approved Open
19 May 2021 Community Letting PolicyResolved to: 1) approve the attached at Appendix 1 and the Stage 1 Further Information Form, Stage 1 Matrix Scoring F... Approved Open