Solar Canopies Over 'Eclipse' Leisure Centre Car Park

Decided Committee 4 papers

Corporate Policy and Resources Committee decided this item on Monday 9 September 2024. Below is the council's own wording, with the papers it was decided on.

Item103/24

Resolved

Committee resolved to: 1. Authorise a tender process to procure market solutions for the solar canopy carpark project; and 2. Note that the Sustainability Team and Assets Team will report the outcome of the tender process to this Committee with detailed proposals
Word for word from the decision Spelthorne published for this meeting. Source: democracy.spelthorne.gov.uk

Follow this further

Built from Spelthorne's papers

What the report saysPro

Report to Corporate Policy and Resources Committee

Schedule of Requirements Solar Carpark 1. The Requirement Spelthorne Borough Council (SBC) are constructing a new leisure centre and will be building a new carpark on the adjoining site. SBC wish to erect a solar canopy/solar carpark/solar carport over the new leisure centre carpark. The generated electricity would either be delivered to the grid or to be utilised in running the leisure centre. The solar carpark should provide a maximum supply of just under 1 megawatt. The lifespan of the project will be a minimum of 30 years, with options to extend the lifespan with replacement solar arrays on top of the canopy structure.

The new leisure centre carpark will be built in the first half of 2025.

The solar canopy provider must be an experienced provider with over 3 large scale solar installations within their portfolio and hold experience in working with public institutions.

We require that the solar canopy provider provide:

 The specification for all of the groundworks and foundation design by January 2025 so that the carpark provider can complete those preparations with their work to ensure the car park is fit for the solar canopy installation.  The full construction details of the canopy including both the specifications for a glulam timber frame and steel frame options.  A comparison between pricing, warranty, maintenance and life expectancy should be included between either frame option.

2. Scope of the Contract The scope of the contract will include any and all planning, design and project implementation works related to the development of a solar carpark on the leisure centre carpark. The dimensions and current specification of the carpark will be detailed below.

Bidders should explore the potential for a demand side response contract with the national grid and the potential for extending energy to alternative buildings in the area.

A specification and pricing breakdown will be required for both a Glulam timber frame option and a steel frame option. The successful bidder is expected to work in conjunction with the already appointed groundworks contractor to ensure the groundworks are meeting the specifications of the solar canopy. The provider should be able to work with our groundwork's contractor from January 2025.

3. Detailed Requirements 3.1 The solar canopy: The solar canopy is expected to cover 250 spaces on 4 central double rows within the carpark. The canopy must allow sufficient space for coaches to traverse around the outer road of the carpark by way of a fixed route. The supply from the canopies will need to have the capacity to feed either the leisure centre, other surrounding buildings or the grid.

Battery storage located on or near the carpark site should be included to enable handling of peak demands, potentially as a demand side response mechanism for the national grid. The canopies must have sufficient lighting, and CCTV as an option.

The canopies will cover the 4 double row areas that can be seen below highlighted in red: Suppliers can utilise the drawings provided as part of the initial planning application of the leisure centre to support their bids, found in appendix A

The panels should not have a high level of glint and glare, this will be a key part of a planning process due to proximity to Heathrow airport.

Bidders are required to provide estimated carbon dioxide savings for the lifespan of the product, in addition to estimated embodied carbon emissions associated with both a glulam timber frame option and a steel frame option.

3.2The solar canopy foundation specification: Bidders will provide their solar canopy foundation specification, detailing the construction design for supporting the solar canopy.

This construction design will consider:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Schedule of Requirements /24Report 356 KB DownloadRead as text
PDF
Solar Canopies Over 'Eclipse' Leisure Centre Car ParkReport 442 KB Download
PDF
View as HTML (103/24/2) 26 KBReport 26 KB Copy on its way
PDF
View item 103/24 as HTML 36 KBReport 36 KB Copy on its way

At this meeting

Whole meeting

Who was there

16 of 23 attended
JS
Councillor Joanne SextonChair, present
CB
Councillor Chris BatesonVice-Chair, present
MB
Councillor Malcolm BeecherCommittee Member, present
MB
Councillor Mary Bing DongCommittee Member, present
JB
Councillor John BoughtflowerCommittee Member, present
JB
Councillor Jon ButtonCommittee Member, apologies
SD
Councillor Sue DoranCommittee Member, present
RG
Councillor Rebecca GeachCommittee Member, present
MG
Councillor Michele GibsonCommittee Member, present
KG
Councillor Kathy GrantCommittee Member, present
KH
Councillor Karen HowkinsCommittee Member, apologies
ML
Councillor Matthew LeeCommittee Member, present

All 23 on the meeting page

On this subject at Spelthorne

Search all
  1. Solar Canopies Over 'Eclipse' Leisure Centre Car ParkThis decision
  2. Implementation of Solar Canopies Over the 'Eclipse' Leisure Centre Car ParkAgreed

More from Spelthorne Corporate Policy and Resources Committee

All decisions
MeetingDecisionOutcome
12 Oct 2026 Write Offs - Sundry Debts and Housing BenefitsCommittee resolved to approve the write-offs set out in the Appendix 1 and 2 of the report which totalled £52,026 and... Approved Open
12 Oct 2026 Proposed ICT Server ProcurementThe Committee resolved to: 1. Authorise the Council’s ICT Manager to commence a procurement process for the purchase ... Decided Open
12 Oct 2026 Governance Assurance Update - EDI and Financial ManagementThe Committee resolved to: 1. Note the current overall assurance level for the Governance Assurance Areas under the r... Noted Open
12 Oct 2026 Annual Commercial Property Report for Financial Year 2025/26The Committee received the Annual Commercial Property Report for Financial Year 2025/2026. The Committee resolved to:... Approved Open
12 Oct 2026 Procurement of resource to support the LGR transition and transformation processThe Committee resolved not to approve the procurement to modify the contract of the Head of LGR and Special Projects ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies