Strategic CIL

Approved Committee 5 papers

AI summaryThe Environment and Sustainability Committee approved CIL funding for town centre digital kiosks, resurfacing 10 play areas and two referred Local CIL applications. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved
MoneyNot stated
What happens nextNot stated
Who it affectsNot stated

What was decided

Visit Staines BID was approved for CIL funding to replace town centre digital kiosks.

Spelthorne Borough Council was approved for CIL funding to resurface 10 play areas across the borough.

Two Local CIL applications referred from Local CIL spending boards were approved. One is Footpath 7a, submitted by Surrey County Council. Report P4

Why

The Council's criteria outline how Strategic and Local CIL applications are assessed. Report P1

The applications followed Task Group consideration and a recommendation to the committee.

Members raised questions on 7 October, and applicant responses were recorded. Report P3

Options considered

  • Chosen: Visit Staines BID replacement of town centre digital kiosks. The application was approved following Task Group consideration and recommendation. [D]
  • Chosen: Spelthorne Borough Council resurfacing of 10 play areas across the borough. The application was approved following Task Group consideration and recommendation. [D]
  • Chosen: Two Local CIL applications referred from Local CIL spending boards. The applications were referred from spending boards and recommended for committee approval. [D] [P2] Report P2

Implications

  • Financial: The decision approved CIL funding for the kiosk replacement, play area resurfacing and two referred applications. [D]
  • Other: Footpath 7a has an improvement route shown in the supplied maps. [P4] Report P4
  • Other: Task Group questions and applicant responses were recorded with the application material. [P3] Report P3

Who and where

  • Visit Staines BID
  • Spelthorne Borough Council
  • Town centre digital kiosks
  • 10 play areas across the borough
  • Surrey County Council's Footpath 7a project Report P4
  • Applicants with the two referred Local CIL applications

Timeline

  • 2026-11-19: The Environment and Sustainability Committee approved the CIL funding applications. [D]
  • 7 October: Strategic CIL Task Group members raised questions about the applications, and applicant responses were recorded. [P3] Report P3

Plain English for the jargon

  • Community Infrastructure Levy: Council funding considered through applications using the Council's assessment criteria. [D] [P1]
  • Strategic CIL: Applications assessed using the Council's Strategic and Local CIL criteria. [P1]
  • Local CIL: Applications that may be referred from Local CIL spending boards for committee approval. [D]
  • Strategic CIL Task Group: The group that considered applications and raised questions before committee approval. [D] [P3]
  • Footpath 7a: The improvement route submitted by Surrey County Council. [P4]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

The Committee resolved to: 1. Approve Community Infrastructure Levy funding for the applications set out below, following consideration by the Task Group and recommendation to the Environment and Sustainability Committee: a) funding applications for: - Visit Staines BID – replacement of town centre digital kiosks - Spelthorne Borough Council – resurfacing 10 play areas across the borough b) Two Local CIL applications referred from Local CIL spending boards.
Word for word from the decision Spelthorne published for this meeting. Source: democracy.spelthorne.gov.uk

Follow this further

Built from Spelthorne's papers

What the report saysPro

Report to Environment and Sustainability Committee

Committee Report Checklist

Please submit the completed checklists with your report. If final draft report does not include all the information/sign offs required, your item will be delayed until the next meeting cycle.

Stage 1 Report checklist – responsibility of report owner ITEM Yes / No Date Councillor engagement / input from Chair prior to Yes Local CIL & briefing Strategic CIL meetings, 07/10/26 and several over July 2026 for Local wards. Commissioner engagement (if report focused on Yes Sent for issues of concern to Commissioners such as Finance, review Assets etc) on9/10/26 – no comments received. Relevant Group Head review Yes 9/10/26 MAT+ review (to have been circulated at least 5 Yes 9/10/26 working days before Stage 2) This item is on the Forward Plan for the relevant Yes 24/9/26 committee Reviewed by

Finance comments (circulate to Finance) B.Hanger 15/10/26 Risk comments (circulate to Lee O’Neil) L.O’Neil 15/10/26 Legal comments (circulate to Legal team) J Clare 15/10/26 HR comments (if applicable) N/A

For reports with material financial or legal implications the author should engage with the respective teams at the outset and receive input to their reports prior to asking for MO or s151 comments.

Do not forward to stage 2 unless all the above have been completed.

Stage 2 Report checklist – responsibility of report owner ITEM Completed Date by Monitoring Officer commentary – at least 5 working L.Heron 15/10/26 days before MAT S151 Officer commentary – at least 5 working days T.Collier 09/10/26 before MAT

Confirm final report cleared by MAT P. Moore Reviewed 20/10/26

2 Environment and Sustainability (E&S) Committee

19 November 2026

Title Approval of Community Infrastructure Levy (CIL) funding Purpose of the report To make a decision Report Authors Rupinder Gill – S106 CIL Officer – Monitoring & Spend Jane Robinson – Local Plans & Infrastructure Manager Ward(s) Affected All Wards Exempt No Exemption Reason N/A Corporate Priority Community Environment Recommendations Committee is asked to:

1. Approve Community Infrastructure Levy (CIL) funding for the applications set out below, following consideration by the Strategic CIL Task Group and recommendation to the Environment and Sustainability Committee:

i. Strategic CIL funding applications for:

o Visit Staines BID – replacement of town centre digital kiosks o Spelthorne Borough Council – resurfacing 10 play areas across the borough

ii. Two Local CIL applications referred from Local CIL spending boards.

Reason for To enable the appropriate spending of Strategic CIL funding Recommendation towards the provision, improvement, replacement, operation or maintenance of infrastructure required to support the development of its area. In line with Spelthorne’s CIL Governance, the above applications and amendments meet general criteria for CIL funding and following scrutiny and consideration by the relevant CIL Task Groups, are recommended for approval.

3 1. Executive summary of the report

What is the situation Why we want to do something • Following consideration by the • The Council is required by legislation relevant CIL Task Groups, four and national planning guidance to infrastructure schemes are allocate CIL funds collected from recommended to this committee for development to infrastructure projects approval. that will support growth and development in the area. Approving funding of the recommended infrastructure schemes will bring a range of local benefits to Spelthorne residents, businesses and community groups.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CIL Applications: Assessment Criteria and Scoring (sent to STG) CopyAppendix A 157 KB Download
PDF
Strategic CIL applications & referred Local CIL: Agreed for E&S approvalAppendix B 64 KB Download
PDF
Questions raised by Strategic CIL Task Group & responsesAppendix C 199 KB Download
PDF
LCIL06 Referred: SCC Footpath 7a mapsAppendix D 693 KB Download
PDF
Strategic CILReport 293 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 17 attended
JT
Councillor John TurnerChair, expected
JB
Councillor John BoughtflowerVice-Chair, expected
LB
Councillor Laura BarkerCommittee Member, expected
MB
Councillor Malcolm BeecherCommittee Member, expected
TB
Councillor Tony BurrellCommittee Member, expected
DC
Councillor Darren ClarkeCommittee Member, expected
JD
Councillor John DoranCommittee Member, expected
KG
Councillor Kathy GrantCommittee Member, expected
KH
Councillor Karen HowkinsCommittee Member, expected
AM
Councillor Anant MathurCommittee Member, expected
LN
Councillor Lawrence NicholsCommittee Member, expected
JS
Councillor Joanne SextonCommittee Member, expected

All 17 on the meeting page

More from Spelthorne Environment and Sustainability Committee

All decisions
MeetingDecisionOutcome
19 Nov 2026 Options paper alternative locations for a Multi-Use Games Area following the decision not to proceed at Memorial GardensThe Committee resolved to: 1. Note that the Environment and Sustainability Committee has resolved not to proceed with... Agreed Open
19 Nov 2026 Staines Masterplan – Adoption as an Interim Technical Note and progression as a Supplementary PlanThe Committee resolved to make a recommendation to Council to: 1. Approve the draft Staines Masterplan, attached at A... Approved Open
19 Nov 2026 Green Initiative Fund Request - Colne Valley Regional Park - Recommendation from Climate and Nature Working GroupThe Committee resolved to: 1. Approve Colne Valley Regional Park Trust application for Green Initiatives Fund funding... Approved Open
19 Nov 2026 Green Initiative Funding ApplicationThe Committee resolved to approve Green Initiative Fund funding of £16,000 towards the replacement of the existing al... Approved Open
19 Nov 2026 Environment and Sustainability Committee Q2 2026/27 Performance ReportThe Committee resolved to acknowledge the Q2 2026/27 Key Performance Indicators for Environment and Sustainability Co... Decided Open