AI summarySpelthorne Borough Council's Environment and Sustainability Committee approved £16,000 from the Green Initiative Fund for an air source heat pump at Ashford Cemetery Lodge, replacing all electric heating and lowering expected household energy costs. [D][P17]
Written from the decision and the officer reportPDF Pro
OutcomeApprovedReplaces all electric heating at Ashford Cemetery Lodge. [D]
Money£16,000 Green Initiative Fund funding [D]Covers installation and removal of the existing electric boiler. [P17]
What happens nextNot stated
Who it affectsTemporary accommodation household [P14]Expected lower heating costs and reduced fuel poverty risk. [P16][P17][P22]
What was decided
The Environment and Sustainability Committee approved £16,000 from the Green Initiative Fund towards replacing the existing all electric heating system at Ashford Cemetery Lodge, Ashford TW19 7AD, with an appropriately designed air source heat pump.
Why
The low income household faces high electricity running costs of c.£5,460 per annum, which the report describes as financially unsustainable. Report P12, P14
An air source heat pump can reduce electricity consumption, heating costs and operational carbon emissions. In 2024, alternatives were not appraised because an electric boiler had already been procured for £6,893, not because a heat pump was judged unsuitable. Report P14, P15
The property's 2024 refurbishment and insulation provide a suitable base for efficiency. The project supports the Council's net zero objectives by 2030 and is described as a pilot for wider use across Council properties. Report P14, P16
What happens next
Appoint the supplier and contractor under the Best Value Duty and the Council's Contract Standing Orders, with Legal Services support. Report P18, P21
Complete appropriate design, procurement, installation and post completion monitoring to manage the identified risks. Report P16
The implementation timetable remains to be confirmed. Report P25
The money
£16,000 Approved GIF funding towards complete installation, decommissioning, removal and compliant disposal of the existing electric boiler. Report P17
£16k Expected reduction in the remaining GIF reserve balance. Report P19
£1,184 to 1,423/year Indicative annual heating cost with the air source heat pump. Report P17
£4,043 to 4,282 Indicative annual saving for the Temporary Accommodation resident. Report P17
£16K Upfront equipment and setup cost for the preferred heat pump option. Report P15
c.£12K Upfront cost for the gas connection and dual system option. Report P15
£25,000 The project is below this Procurement Board approval threshold, inclusive of VAT. Report P21
Options considered
Chosen: Install an air source heat pump. Preferred because it can reduce electricity consumption, energy costs and operational carbon emissions over its lifetime. Disadvantages are high upfront cost and possible outdoor unit noise. Report P15
Rejected: Connect gas mains and install a dual gas and electricity system. It has high upfront costs, complex gas safety maintenance and greater fossil fuel dependence, making carbon reduction and net zero goals harder. Report P15
Rejected: Retain the existing electric heating. It avoids retrofit costs and indoor gas combustion risks, but retains high electricity use, higher household costs, fuel poverty risk and poor heating efficiency. Report P15
Implications
Financial: The recommendation can be fully funded from the GIF reserve, with the remaining balance reduced by £16k. Report P19
Financial: The report gives an existing heating cost of £5,460/year and an indicative ASHP cost of £1,184 to 1,423/year. Most savings accrue to the occupying household, while the Council gains improved asset performance, lower carbon emissions and futureproofing. Report P17
Climate: The air source heat pump is expected to improve efficiency and reduce the property's carbon footprint from 3.00 to 0.80 tonnes CO2. It also supports the target of net zero carbon emissions across the borough by 2030 and the wider decarbonisation strategy. Report P14, P23, P24
Legal: The project does not require Procurement Board approval because its value is below £25,000 inclusive of VAT. Supplier and contractor appointment must meet the requirements of the Best Value Duty and Contract Standing Orders, with Legal Services support required for the contract. Report P18, P21
Equalities: The proposal is expected to have a positive equality impact and is not expected to adversely affect any protected group under the Equality Act 2010. Occupants' specific needs will be considered during design, installation and commissioning. Report P22
Risk: High heating costs could create fuel poverty, energy hardship and financial pressure on the low income household. Reduced heating use could also lead to poor thermal comfort. Report P16
Risk: Installation risks include high upfront cost, poor system design, lower flow temperatures and operational noise. The report says these can be managed through design, procurement, installation, post completion monitoring and planned maintenance. Report P16
Other: The investment is property specific and recognises the potential transfer of assets, liabilities and responsibilities to West Surrey Council. Report P24
Who and where
The low income family occupying Ashford Cemetery Lodge as temporary accommodation Report P14
Spelthorne Borough Council as owner, funder and maintainer of the property Report P14, P16
West Surrey Council if assets, liabilities and responsibilities transfer Report P24
Future occupants of Ashford Cemetery Lodge Report P14
Other Council properties if the pilot is scaled up Report P16
Households on low incomes affected by high energy costs Report P22
Timeline
2021: The refurbishment was originally scheduled for 2021. Gas connection was not progressed because of significant cost and timescales, and an electric boiler had been purchased for the project. Report P14
2024: The property underwent major refurbishment into a four bedroom residential home. The air source heat pump was later reconsidered after review of ongoing energy costs. Report P14
10 September 2026: The Climate and Nature Working Group approved the application to proceed. Report P18
19 November 2026: The Environment and Sustainability Committee approved the £16,000 funding. Report P7
2030: The target year for net zero carbon emissions across the borough. Report P14
Timetable to be confirmed: Implementation timetable for the funded project. Report P25
Plain English for the jargon
ASHP: Air Source Heat Pump, a system that extracts heat from external air to provide space heating and domestic hot water. [P13][P14]
GIF: Green Initiative Fund, the source of the £16,000 approved for this project. [D][P9]
GIF reserve: The Green Initiative Fund balance from which the recommendation can be fully funded. [P19]
CNWG: Climate and Nature Working Group, which considers GIF applications and recommends them to the Committee. [P18]
TA: Temporary Accommodation, the use made of Ashford Cemetery Lodge for a low income family. [P12][P14]
Fuel poverty: Financial hardship caused by high heating costs, which can also lead to reduced heating and poor thermal comfort. [P16]
Best Value Duty: A requirement for supplier and contractor appointment under the Local Government Act 1999. [P18]
Contract Standing Orders: The Council procurement rules that the appointment must follow. [P18][P21]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9
Resolved
The Committee resolved to approve Green Initiative Fund funding of £16,000 towards the replacement of the existing all-electric heating system at Ashford Cemetery Lodge, Ashford TW19 7AD with an appropriately designed low carbon heating system – air source heat pump.
Word for word from the decision Spelthorne published for this meeting.Source: democracy.spelthorne.gov.uk
Report to Environment and Sustainability Committee
Committee Report Checklist
Please submit the completed checklists with your report. If final draft report does not include all the information/sign offs required, your item will be delayed until the next meeting cycle.
Stage 1 Report checklist – responsibility of report owner ITEM Yes / No Date Councillor engagement / input from Chair prior to briefing Relevant Group Head review JT 11/10 MAT+ review (to have been circulated at least 5 working days before Stage 2) This item is on the Forward Plan for the relevant committee Reviewed by Finance comments (circulate to Finance) AB 11/10 Risk comments (circulate to Lee O’Neil) LO 09/10 Legal comments (circulate to Legal team) JC 15/10 HR comments (if applicable)
For reports with material financial or legal implications the author should engage with the respective teams at the outset and receive input to their reports prior to asking for MO or s151 comments.
Do not forward to stage 2 unless all the above have been completed.
Stage 2 Report checklist – responsibility of report owner ITEM Completed Date rec’d by Monitoring Officer commentary – at least 5 working L Heron 15/10/26 days before MAT S151 Officer commentary – at least 5 working days T. Collier 11/10/26 before MAT Commissioner engagement J. Kingston 12/10/26
Delete as No issues applicable: Relevant MAT member sign-off LO for PM 16/10/26 Report reviewed by Management Team Environmental and Sustainability Committee Date of Meeting: 19 November 2026
Title Green Initiative Funding Application Purpose of the report To make a decision Report Author Alfred Osawe; Building Services and FM Manager Ward(s) Affected Ashford North and Stanwell South Exempt No Exemption Reason N/A Corporate Priority Community Addressing Housing Need Environment Services Recommendations Committee is asked to:
Approve Green Initiative Fund (GIF) funding of £16,000 towards the replacement of the existing all-electric heating system at Ashford Cemetery Lodge, Ashford TW19 7AD with an appropriately designed low carbon heating system - air source heat pump (ASHP).
Reason for Committee is being asked to take this decision based on the Recommendation following potential advantages Reduced carbon emission by 2.20 tonnes CO2. Achieve net-zero carbon emissions for its own operations and estate (Scope 1 and 2 emissions) by 2030. Reduced annual heating costs by of £4,163 (annual average) for the Temporary Accommodation resident. Increased property value and futureproofing against changing energy regulations. 1. Executive summary of the report (expand detail in Key Issues section below)
What is the situation Why we want to do something
Ashford Cemetery Lodge is a recently There is need to reduce carbon refurbished Council owned 4-bedroom emission while also reducing high property used as temporary energy bill resulting from an all-electric accommodation. powered heating and hot water system. There is no gas supply to the property and it currently relies entirely on electricity for space heating and domestic hot water. The existing electrical heating system results in significant electricity consumption and high running costs of c.£5,460 per annum, which for a TA resident is not considered sustainable. This is what we want to do about it These are the next steps
Replace existing all- electric heating Subject to GIF funding, the project is to install system with appropriately designed an appropriately sized ASHP system capable low carbon heating system – ASHP of providing the required space heating and which offers environmental and domestic hot water. energy efficiency benefits while supporting long-term sustainability objectives.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment and Sustainability Committee at Spelthorne and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.