The Executive considered a report which provided an update on the regeneration projects taking place in Stevenage Town Centre, and which sought an in principle agreement for the funding and design of a new bus interchange; approval to develop a business case and timetable for the development of enhanced leisure facilities; and approval to undertake an options appraisal for the Stevenage Arts and Leisure Centre. An additional recommendation was agreed, requesting the Leader and Chief Executive to raise the matter of the continued delay in Growth Deal 3 funding with representatives of the Ministry of Housing, Communities and Local Government (MHCLG) as part of their scheduled meeting in London on 19 December 2018. A further additional recommendation was agreed to ensure that the most appropriate procurement method was used for the new Bus Station project. The Strategic Director (TP) was requested to establish a Member Advisory Group regarding the composition and design of the proposed Public Sector Hub in the Town Centre. It was
Word for word from the decision Stevenage published for this meeting.Source: democracy.stevenage.gov.uk
2.1Note the progress on regeneration activity across the town.
2.2Note the delay in accessing Growth Deal 3 funding that has been allocated to Hertfordshire LEP to support the regeneration of Stevenage town centre, and the potential implications of this delay continuing.
2.3Agree the proposed approach to development and consultation for a new bus interchange.
2.4Agree to proceed with the next stages of the bus interchange project with an estimated cost in the region of £6.1m, and request Officers to bring forward funding options in the draft Capital Strategy in January 2019 should Growth Deal 3 funding continue to be delayed. This assessment should set out the implications of prioritising funding this infrastructure and mitigation available.
2.5Authority for the necessary purchase or lease of land, together with resolution of any current lease and restrictive covenant and other legal issues to enable
Executive report Part I Part I
the sites to be assembled is delegated to the Strategic Director (TP), having consulted with the Portfolio Holder for Environment and Regeneration.
2.6Approve the Council seeking delegated authority from Hertfordshire County Council to make Traffic Regulation Orders in order to facilitate the delivery of a new bus interchange facility.
2.7Delegates authority to the Strategic Director (TP), having consulted with the Portfolio Holder for Environment and Regeneration to authorise the sealing of Traffic Regulation Orders following the consultation period and consideration/resolution of any objections received.
2.8Gives approval to develop a business case and associated timetable for the development of a new and enhanced leisure facility to be located on St George’s Way.
2.9Approves the undertaking of an options appraisal for the Stevenage Arts & Leisure Centre with a view to developing the theatre and cultural offer within the town centre.
Background
3.1The regeneration of the Town Centre is the top priority for Stevenage’s residents, businesses, and for Stevenage Borough Council as highlighted within the Future Town Future Council (FTFC) Programme.
3.2The Council worked closely with its partners including Hertfordshire County Council, Hertfordshire Chamber Of Commerce and Industry, Hertfordshire Local Enterprise Partnership and Homes England to develop the Stevenage Central Framework (“the Framework”) which was approved by Executive on 24 July 2015.
3.3The Framework sets out a clear vision and the scale of opportunity within a regenerated town centre has been used as the basis for the development of planning policy, including the Local Plan as well as the foundation for developing subsequent regeneration schemes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Regeneration programme delivery updateThe Executive considered a report which provided an update on the projects within the Government’s Towns Fund program...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.