The following matters were raised: · Paragraph 4.1.10 – ICT expenditure – in response to a question regarding the anticipated 2018/19 underspend of £552,000, it was confirmed that slippage had occurred due to the time taken to appoint a new ICT Strategic Partnerships Manager and the scaling up of revenue resources to support the delivery of the required ICT capital projects. It was expected that this capital expenditure would take place in Quarter 1 of 2019/20. · Paragraph 4.1.21 – Boilers in community centres – officers were requested to provide an answer to Executive Members in respect of a suggested management programme of boiler replacements in community centres. · Paragraph 4.1.23 – Pedaloes at Fairlands Valley Park – SLL be asked to ensure that the new pedaloes were made available for public use on a more regular basis than was currently the case. · Commercial investments – officers undertook to consult with the Estates Team and report back to Executive Members on progress with the Acquisition Strategy ( ie . proposals to acquire commercial property inside and outside of the Borough). It was As contained in report. Other Options considered: As contained in report.
Word for word from the decision Stevenage published for this meeting.Source: democracy.stevenage.gov.uk
2.1That the 2018/19 General Fund capital programme net decrease in expenditure of £3.870Million be approved as summarised in section 4.1
2.2That the 2018/19 Housing Revenue Account capital programme net decrease in expenditure of £0.911Million be approved as summarised in section 4.2.
2.3That the 2019/20 General Fund increase in capital expenditure of £3.015Million (slippage from 2018/19) be approved, as summarised in paragraph 4.1.3.
2.4That the 2019/20 HRA increase in capital expenditure of £1.036Million (£911K slippage from 2018/19 and £125K vehicles) be approved. Part I Release to Press 3 BACKGROUND
3.1The latest 2018/19 capital programme was approved at Council on 27 February 2019. The 2018/19 programme totals for each fund were; General Fund £15,484,880 Housing Revenue Account £23,527,800
4 REASONS FOR RECOMMENDED COURSE OF ACTION AND OTHER OPTIONS
4.12018/19 General Fund Capital Programme
4.1.1 The 2018/19 General Fund capital programme of £15.485Million (detailed in backing document BD1) has reduced by £3.870Million to £11.615Million.
2018/19 General Fund budget v revised £'000 £16,000
£15,485
£11,615 £14,000 £12,000 £7,300
£10,000 £6,113
£8,000 £3,366
£6,000 £4,000 £2,294
£1,096
£1,512 £941
£276
£848 £295
£643
£225 £193
£997 £877 £83
£20 £20
£2,000 Wkg budget £0 revised Stevenage Direct Services
Housing Development
Finance & Estates
Customer Services & Technology
Housing & Investment
Regeneration
Communities & Neighbourhoods
Planning and Regulatory
Deferred Works
Total Schemes
4.1.2 The net reduction in projected spend by Business Unit is summarised below and £3.015Million of this relates to scheme slippage. Part I Release to Press
£3,015 £3,500 2018/19 Underspend and slippage £'000 £3,000 £2,500
£1,186 £2,000 £947
£844 £1,500
£653 £561 £1,000 £125
£140
£217
£120 -£155
£52
£21 £500 £0
£0
£0
£0 £0 -£8 Underspend Stevenage Direct Services
Housing Development
Finance & Estates
Customer Services & Technology
Housing & Investment
Regeneration
Communities & Neighbourhoods
Planning and Regulatory
Total Schemes -£500 Slippage
4.1.3 The main areas of scheme slippage are summarised in the following chart with explanations for the larger areas of slippage.
Scheme Slippage £'000 £792
£645 -£155
£800 £359
£600 £400 £130
£130
£105
£287
£174
£174 £96
£61
£57
£80
£80
£200 £0 -£200 Garages
Vehicle replacement
Housing development
Garage site assembly
ICT infrastructure
ICT customer account
Other ICT systems
Community centre works
Pavillions
Town Square improvements
Bus station
CCTV relocation
Public Sector Hub
MSCP lighting
Other
4.1.4 Garages- Two further pilot sites have been commenced in order to test and confirm operational arrangements with a view to the remainder of the works commencing in the new financial year. The works will be completed by the Major Repairs Contract (MRC) contractor. Part I Release to Press 4.1.5 Vehicles - The working budget was £1.872Million with 86% projected to be delivered in year with a further £130K or 7% of vehicle purchases slipping into the next financial year. The slippage relates to specialist grave digging equipment which, following demonstrations and site testing did not meet the council’s requirements resulting in the need to consider alternative products and a delay to an order being placed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Regeneration programme delivery updateThe Executive considered a report which provided an update on the projects within the Government’s Towns Fund program...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.