The Executive considered a report in respect of the Third Quarter Capital Programme monitoring 2022/23 for the General Fund and Housing Revenue Account (HRA). It was As contained in report. Other Options considered: As contained in report.
Executive (up to May 2024) decided this item on Wednesday 15 March 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
The Executive considered a report in respect of the Third Quarter Capital Programme monitoring 2022/23 for the General Fund and Housing Revenue Account (HRA). It was As contained in report. Other Options considered: As contained in report.
Part I – Release to Press
Meeting EXECUTIVE
Portfolio Area Resources, Transformation & ICT
Date 15 MARCH 2023
QUARTER 3 MONITORING REPORT (CAPITAL) - GENERAL FUND AND HOUSING REVENUE ACCOUNT KEY DECISION
Authors Belinda White Contributors Rhona Bellis / Senior Leadership Team Lead Officers Brian Moldon Contact Officer Clare Fletcher
1. PURPOSE 1.1 To provide Members with an update on the Council’s 2022/23 and 2023/24 capital programme as part of the quarterly review (Quarter three). 1.2 To seek approval for the revisions to the General Fund (GF) and Housing Revenue Account (HRA) capital programme.
2. RECOMMENDATIONS 2.1 That capital budget re-profiling of £9.006Million from 2022/23 to future years be approved.
2.2That an in year virement of £66K to reallocate unspent resources to the Deferred Works Reserve from underspends on vehicles within the SDS Capital Programme be approved.
2.3That an in year virement of £68K to reallocate unspent resources to the Deferred Works Reserve from underspends on the Finance & Estates Capital Programme be approved.
2.4That an in year virement of £10K to reallocate unspent resources to the Deferred Works Reserve from underspends on the Communities & Neighbourhoods Capital Programme
2.5That capital budget re-profiling of £12.781Million from 2023/24 to future years be approved.
3. BACKGROUND 3.1 The current 2022/23 capital programme was last approved at Council on 22 February 2023. The 2022/23 approved budget for each fund was: General Fund £26.2Million Housing Revenue Account £49.1Million
3. 2 This report provides an update on known changes to the programme since the Council meeting in February and includes revisions that were not known at the time of writing the Capital Strategy report to the February Executive.
4 REASONS FOR RECOMMENDED COURSE OF ACTION AND OTHER OPTIONS
4.1The total Capital Programme, detailing all programmes with the relevant approval to spend, is detailed in Appendix A and B. It shows the revised budget position.
4.2The capital budget for the current financial year is summarised in Table 1 below and provides the latest position reflecting updated programme expenditure profiles as advised by programme managers.
TABLE 1: Capital Programme with Spending Approval
Final 22/23 Actuals Scheme Capital Reprofiling Virement Forecast to 31 Strategy Q3 Jan 23 £'000 £'000 £'000 £'000 £'000 General Fund - Schemes Stevenage Direct Services 3,612 (237) (66) 3,309 2,495 Housing Development 2,425 (1,050) 0 1,376 748 Finance and Estates 2,861 (531) (68) 2,262 1,045 Digital & Transformation 418 0 0 418 129 Regeneration 14,610 0 0 14,610 9,107 Communities and Neighbourhoods 924 (374) (10) 540 180 Planning and Regulatory 275 (66) 0 209 160 Deferred Works Reserve 1,059 0 145 1,204 0 Total GF Schemes 26,185 (2,258) 0 23,927 13,863 HRA - Schemes Capital Programme Excl. New Build 23,469 0 0 23,469 16,597 (Housing Investment) Special Projects & Equipment 63 0 0 63 0 New Build (Housing Development) 25,060 (6,748) 0 18,312 14,652 Digital & Transformation 494 0 0 494 188 Total HRA Schemes 49,086 (6,748) 0 42,338 31,437 Total Capital Programme 75,271 (9,006) 0 66,265 45,300 2022/23 REVISED BUDGET
4.3Reprofiling
4.3.1 Reprofiling of budgets are changes regarding the forecast timing of expenditure from the approved programme, between financial years, with no reported increase or decrease in budget requirement.
4.3.2 At quarter three, £9.006Million is to be reprofiled from 2022/23 to future years (of which 87% relate to Housing Development schemes), £2.258Million of General Fund and £6.748Million of Housing Revenue Account (HRA) budgets.
4.3.3 There is also a request to reprofile £12.780Million of expenditure (relating to Housing Development schemes) from 2023/24 into future years, £8.559Million General Fund and £4.221Million HRA budgets. Table 2 below analyses the budget reprofiling, with explanations below the table for the significant items relating to 2023/24:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Cap: Appendix A: General Fund Q3Appendix | 353 KB | Download |
PDF |
Cap: Appendix B: HRA Q3Appendix | 576 KB | Download |
PDF |
THIRD QUARTER CAPITAL MONITORING REPORT 2022/23: GENERAL FUND AND HOUSING REVENUE ACCOUNTReport | 477 KB | DownloadRead as text |
Follow Executive (up to May 2024) at Stevenage and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Mar 2024 | Apologies for absence and declarations of interestApologies for absence were submitted on behalf of Councillors Richard Henry (Chair), Sandra Barr and [name removed]. ... | Decided | Open |
| 13 Mar 2024 | Minutes - 7 february 2024It was RESOLVED that the Minutes of the meeting of the Executive held on 7 February 2024 be approved as a correct rec... | Approved | Open |
| 13 Mar 2024 | Minutes of overview & scrutiny committee and select committeesThe Portfolio Holder for Environment and Performance thanked the Chair and Members of the Environment & Economy Selec... | Noted | Open |
| 13 Mar 2024 | Regeneration programme delivery updateThe Executive considered a report which provided an update on the projects within the Government’s Towns Fund program... | Agreed | Open |
| 13 Mar 2024 | Housing consumer standards - social housing (regulation) act 2023The Executive considered a report in respect of the Social Housing (Regulation) Act 2023, which introduced wide rangi... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.