Resolved
It was RESOLVED : 1. That the Internal Audit progress report be noted. 2. That the status of Critical and High Priority Audit Recommendations be noted.
Audit Committee noted this item on Tuesday 11 June 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
It was RESOLVED : 1. That the Internal Audit progress report be noted. 2. That the status of Critical and High Priority Audit Recommendations be noted.
Members are recommended to: a) Note the Internal Audit Progress Report b) Note the Status of Critical and High Priority Recommendations SIAS Internal Audit Progress Update Stevenage Borough Council
Contents
1 Introduction and Background 1.1 Purpose 1.2 Background
2 Audit Plan Update 2.1 Delivery of Audit Plan and Key Findings 2.4 Proposed Audit Plan Amendments 2.5 Critical and High Priority Recommendations 2.7 Performance Management
Appendices: A Progress against the 2019/20 Audit Plan B Implementation Status of Critical and High Priority Recommendations C Audit Plan Items (April 2019 to March 2020) - Indicative start dates agreed with management D Assurance Definitions / Priority Levels SIAS Internal Audit Progress Update Stevenage Borough Council
1 Introduction and Background Purpose of Report
1.1To provide Members with:
a) The progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s 2019/20 Internal Audit Plan as at 17 May 2019. b) The findings for the period 1 April 2019 to 17 May 2019. c) The proposed amendments required to the approved Internal Audit Plan. d) The implementation status of previously agreed audit recommendations. e) An update on performance management information as at 17 May 2019.
1.2Internal Audit’s Annual Plan for 2019/20 was approved by the Audit Committee at its meeting on 19 March 2019. The Audit Committee receive periodic updates against the Annual Internal Audit Plan.
1.3The work of Internal Audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit function is fulfilling its statutory obligations. It is considered good practice that progress reports also include proposed amendments to the agreed Annual Internal Audit Plan.
2 Audit Plan Update Delivery of Audit Plan and Key Audit Findings
2.1As at 17 May 2019, 8% of the 2019/20 Audit Plan days have been delivered (calculation excludes contingency days that have not yet been allocated).
2.2No final reports have been issued for audits from the 2019/20 Audit Plan. The following 2018/19 final reports and assignments have been issued or completed in the period since the last Audit Committee:
Date of Assurance Number of Audit Title Issue Level Recommendations
Debtors March 2019 Good One Low/Advisory
Payroll March 2019 Good Two Low/Advisory
Housing Rents March 2019 Good None One High, One Medium, Community Safety March 2019 Satisfactory One Low/Advisory TSS Improvement March 2019 Limited Two High, Three Medium
Page 1 SIAS Internal Audit Progress Update Stevenage Borough Council
Plan – Governance
Repairs & Voids April 2019 Satisfactory One Low/Advisory Service Follow up
Main Accounting April 2019 Satisfactory Six Low/Advisory
Cyber Security Two High, One Medium, April 2019 NA Follow up Two Low/Advisory
Incident Management April 2019 NA Three High, One Medium Follow up
Digital – Connecting Two Medium, One May 2019 Satisfactory to our Customers Low/Advisory
2.3The table below also summarises the position with regard to 2019/20 projects as at 17 May 2019. Appendix A provides a status update on each individual project within the 2019/20 Internal Audit Plan. Details of indicative start dates for the individual projects are also shown in Appendix C.
Status No. of Audits at this Stage % of Total Audits
Final Report Issued 0 0%
Draft Report Issued 0 0% In Fieldwork/Quality 3 8% Review In Planning/Terms of 5 14% Reference Issued Allocated 6 17%
Not Yet Allocated 22 61%
Deferred/Cancelled 0 0%
Total 36 100%
Proposed Audit Plan Amendments
2.4There has been no change to the Audit Plan since it was approved on 19 March 2019.
Critical and High Priority Recommendations
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
AUDIT PLAN 2019/20: PROGRESS REPORTReport | 173 KB | DownloadRead as text |
Follow Audit Committee at Stevenage and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jun 2026 | Sias annual assurance statement and internal audit report 2025/26RESOLVED that: · The Annual Assurance Statement and Internal Audit Annual Report 2025/26 be noted. · The results of t... | Noted | Open |
| 2 Jun 2026 | 2025/26 annual governance statement and local code of corporate governanceRESOLVED that the report be noted. | Noted | Open |
| 2 Jun 2026 | Annual report of the audit committeeRESOLVED that the report be noted. | Noted | Open |
| 2 Jun 2026 | Exclusion of public and pressRESOLVED : 1. That, under Section 100(A) of the Local Government Act 1972, the press and public be excluded from the ... | Decided | Open |
| 2 Jun 2026 | Strategic risk registerRESOLVED that the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.