Resolved
The Executive considered a report in respect of the First Quarter Capital Programme General Fund and Housing Revenue Account monitoring 2020/21. It was As contained in report. Other Options considered: As contained in report.
Executive (up to May 2024) decided this item on Wednesday 16 September 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
The Executive considered a report in respect of the First Quarter Capital Programme General Fund and Housing Revenue Account monitoring 2020/21. It was As contained in report. Other Options considered: As contained in report.
2.1That Executive approve the 2020/21 General Fund capital programme net decrease in expenditure of £1.4 Million as summarised in table one, para 4.1.1.
2.2That Executive approve the General Fund net increase (arising from slippage) of capital expenditure of £1.6 Million in 2021/22, also as summarised in table one, para 4.1.1.
2.3That Members note the net decrease of £705K in the capital expenditure for 2020/21 Housing Revenue Account, as summarised in table five, para 4.3.1.
2.4That Members note the net decrease (arising from slippage) of £10.9 Million in the capital expenditure for 2021/22 Housing Revenue Account, also as summarised in table five, para 4.3.1.
Executive 11 September 2019 Part I Release to Press 3.1 The 2020/21 capital programme was approved as part of the 2019/20 Outturn Report at the July Executive: General Fund £36.7 Million Housing Revenue Account £34.8 Million
4. REASONS FOR RECOMMENDED COURSE OF ACTION AND OTHER OPTIONS
4.12020/21 General Fund Capital Programme
4.1.1 The updated projected spend for 2020/21 General Fund capital programme (as detailed in Appendix A) is £35.3 Million, a net decrease of £1.4 Million which is mainly due to slippage in the garage programme. The detail for all schemes is shown in table one:
Table one: Changes to General Fund Capital Budget Increase Increase (Decrease) to (Decrease) to Capital Programme Change to 2020/21 Working Budget & 2020/21 2021/22 2021/22 Projected Budget Working Projected Budget Budget £’s £’s Slippage/Acceleration Garages Programme (1,422,070) 1,422,070 Kenilworth Housing Development - Retail (207,132) 207,132 Kenilworth Housing Development - Community Centre (162,218) (324,246) Commercial Properties Refurbishment (MRC Programme) (237,660) 237,660 Fairlands Valley Park Sailing Centre - Boathouse (12,000) 12,000 Boathouse works for dry rot (15,000) 15,000 Coreys Mill Lane - Additional Parking Capacity 2,000 (2,000)
Total Slippage (2,054,080) 1,567,616
Increases/(Decreases) to 2020/21 Budget Grants To Registered Providers 610,065 Replacement vehicle for LK10 FDJ - Toro LTF3000 Mower 39,350 Garage Site Assembly (40,000)
Total Increases/(Decreases) to 2019/20 Budget 609,415 0
Total Change in Working Budget and Projected Budgets (1,444,665) 1,567,616
4.1.2 Slippage:
The Garage Programme delivery pipeline has been reviewed with three schemes covering 150 garages due to start on site in Autumn 2020. A pilot site at Collinswood has been identified to create new garages and widen the offer to residents. Current feasibility studies and structural reviews will inform
Executive 11 September 2019 Part I Release to Press the next tranche of the programme which is expected to be delivered in 2021/21 (£1.4 Million slippage from the £3.5 Million 2020/21 budget).
The Kenilworth Housing Development retail and community centre elements have been re-phased to maximise delivery of housing first, in line with the most pressing need.
A small element of the budget relating to Coreys Mill Lane additional parking have been brought forward from 2021/22 to fund the safety audit.
4.1.3 Increases in Expenditure: Grants to Registered Providers has been increased by £610K in order to mitigate the risk of repayment of 1.4.1 receipts to the government. This additional spend is within Executive delegated limits as funding is ring fenced and can only be used to increase social housing provision in Stevenage.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Item 10: Appendix A: Q1 General Fund CapitalAppendix | 143 KB | Download |
PDF |
Item 10: Appendix B: Q1 HRA CapitalAppendix | 131 KB | Download |
PDF |
QUARTER 1 MONITORING REPORT 2020/21 (CAPITAL): GENERAL FUND AND HOUSING REVENUE ACCOUNTReport | 350 KB | DownloadRead as text |
Follow Executive (up to May 2024) at Stevenage and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Mar 2024 | Apologies for absence and declarations of interestApologies for absence were submitted on behalf of Councillors Richard Henry (Chair), Sandra Barr and [name removed]. ... | Decided | Open |
| 13 Mar 2024 | Minutes - 7 february 2024It was RESOLVED that the Minutes of the meeting of the Executive held on 7 February 2024 be approved as a correct rec... | Approved | Open |
| 13 Mar 2024 | Minutes of overview & scrutiny committee and select committeesThe Portfolio Holder for Environment and Performance thanked the Chair and Members of the Environment & Economy Selec... | Noted | Open |
| 13 Mar 2024 | Regeneration programme delivery updateThe Executive considered a report which provided an update on the projects within the Government’s Towns Fund program... | Agreed | Open |
| 13 Mar 2024 | Housing consumer standards - social housing (regulation) act 2023The Executive considered a report in respect of the Social Housing (Regulation) Act 2023, which introduced wide rangi... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.