SECOND QUARTER MONITORING REPORT FOR GENERAL FUND, HOUSING REVENUE ACCOUNT AND CAPITAL MONITORING

Noted Executive 4 papers

AI summaryStevenage Cabinet approved a marginal £1,380 General Fund overspend and £10 million of capital rephasing at the second quarter, with an HRA underspend of £165,000 and reserves forecast to stay above minimum levels.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedQ2 monitoring report approved with budget revisions
Money£10 million rephasedCapital spend moved to future years
What happens nextContinued monitoringOfficers to track demand-led HRA services
Who it affectsCouncil budgets and tenantsGeneral Fund, HRA and Capital Programme

What was decided

Cabinet approved the £1,380 projected net increase in General Fund expenditure for 2025/26, along with a £164,550 net decrease in Housing Revenue Account expenditure. Report 2.1

Members approved using £11,120 from the Extended Producer Responsibility reserve for an initial free supply of food waste caddy liners, and a £150,000 Revenue Contribution to Capital Outlay to fund urgent unplanned works. Report 2.2, 2.4

Cabinet approved rephasing £6.4 million of General Fund capital and £3.6 million of HRA capital from 2025/26 into future years, alongside several virements from the deferred works reserve. Report P139

Why

The General Fund overspend is driven by a 3.2% pay award exceeding the 3% budget assumption (£58,000), agency staffing in Stevenage Direct Services, insurance premium increases, additional audit fees, and a £150,000 transfer to the deferred works reserve. Report P15, P18, P16, P21, P24, P14

These pressures are largely offset by £208,000 of extra investment interest, £50,000 of insurance recharges, £20,000 of fuel savings, and £14,000 of additional street naming income. Report P30, P29, P28, P27

The HRA underspend comes mainly from an £801,000 interest saving due to delayed loan taking, partly offset by £200,000 each of overspends on void repairs and disrepair cases, and £99,000 on the in-house repairs team. Report P112, P106, P107, P108

What happens next

The HRA business plan is to be revised at Quarter 3 and presented to Cabinet for approval in November 2025, with capital funding to be adjusted accordingly. Report P128, P141

Officers will continue to monitor the demand-led HRA repair budgets over the second half of the year, and report on bank charges savings and the indoor market relocation in the next quarterly report. Report P89, P90, P151

A business unit review of Stevenage Direct Services is scheduled for later in the year to address ongoing agency and overtime pressures. Report P16

The money

  • £1,380 Projected net increase in General Fund expenditure 2025/26 Report P12, 2.1
  • £164,550 Projected net decrease in HRA expenditure 2025/26 Report P96
  • £6.4 Million General Fund capital rephased from 2025/26 to future years Report P124
  • £3.6 Million HRA capital rephased from 2025/26 to future years Report P127
  • £150,000 Revenue Contribution to Capital Outlay to fund urgent unplanned works Report P14, 2.4
  • £11,120 EPR reserve spend on initial food waste caddy liners Report 2.2, P22
  • £10,753,540 Original General Fund net budget for 2025/26 Report 3.1
  • £208K Additional investment interest income forecast Report P30
  • £801K HRA interest saving from delayed loan taking Report P112
  • £200,000 HRA overspend on void repairs at Q2 Report P106
  • £200,000 HRA overspend on disrepair cases Report P107
  • £0.822 Million Forecast Council Tax Collection Fund surplus for 2025/26 Report P47

Options considered

  • Chosen: Approve £1,380 General Fund net overspend. Within Cabinet delegated variation limit of £400,000 Report 2.1, P31
  • Chosen: Fund caddy liners from EPR reserve at £11,120. Supports launch of new weekly food waste collection and is best practice for participation Report 2.2, P22
  • Chosen: Add £150,000 to deferred works reserve via RCCO. Provides flexibility for urgent unplanned capital works given limited capital resources Report 2.4, P14
  • Chosen: Approve rephasing of £10 million capital to future years. Aligns with revised delivery timelines for The Oval, Kenilworth and other major schemes Report P126, P127
  • Chosen: Apply for depot charging grant for 40 electric vehicle points at Cavendish. Grant window closes November 2025; would fund 75% of cost with potential £78,000 annual revenue savings Report P138

Implications

  • Financial: General Fund and HRA balances are forecast to remain above minimum required levels at 31 March 2026 (£6,598,781 and £10.2 million respectively). Report P81, P115
  • Financial: HRA maintenance costs remain volatile and demand-led, posing a financial risk for the remaining quarters of 2025/26. Report P151
  • Legal: Members are reminded of their duty to set a balanced budget; no direct legal consequences arise from this monitoring report. Report P152
  • Equalities: None of the budget changes reported will alter existing equalities and diversity policies; any future adverse impacts will be addressed through Equality Impact Assessments in the budget-setting process. Report P154
  • Risk: Risk-based assessment of balances is reported at budget setting; both General Fund and HRA balances are projected above minimum thresholds. Report P155
  • Staffing: Salary budget forecast to overspend by £86,000, mainly agency cover in Stevenage Direct Services, plus the additional 0.2% pay award cost of £58,184 across services. Report P15, P16, P18, P19
  • Other: No direct climate change implications arise from the budget changes reported; climate considerations are embedded in the budget and policy setting process. Report P159

Who and where

  • Stevenage Borough Council General Fund services Report P12, P14
  • Council tenants in the Housing Revenue Account, particularly around void repairs and disrepair cases Report P106, P107
  • All residents due to receive free initial food waste caddy liners from March 2026 Report P22, P23
  • Residents and businesses paying Council Tax and Business Rates in the Borough Report P38, P55
  • Stevenage Direct Services staff and operations Report P16
  • Stevenage Works outreach programme participants and staff Report P17

Timeline

  • October 2025: Annual insurance renewal took effect, adding £75,000 across General Fund and HRA Report P21
  • 2026/27: Rephased capital spend of £6.4 million General Fund and £3.6 million HRA to be incurred Report P124, P127
  • November 2025: Deadline for depot charging grant application; indoor market relocation to Park Place planned to open Report P138, P90
  • March 2026: Launch of new weekly food waste collection service with initial free caddy liners Report P22
  • 31 March 2026: Projected General Fund balance of £6,598,781 and HRA balance of £10.2 million Report P81, P115

Plain English for the jargon

  • General Fund: The council's main revenue account for day-to-day services, funded mainly by Council Tax, business rates and government grants.
  • Housing Revenue Account (HRA): A separate ringfenced account for income and spending on council housing, funded mainly by rents.
  • RCCO: Revenue Contribution to Capital Outlay: a transfer from revenue budgets to fund capital spending.
  • EPR: Extended Producer Responsibility: a funding regime where producers pay for the cost of recycling their packaging.
  • Right to Buy: The statutory scheme allowing secure council tenants to buy their home at a discount.
  • Rephasing: Moving the planned timing of capital spending between financial years without changing the total budget.
  • Virement: The transfer of budget from one spending line to another within the same fund.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

Cabinet received a report detailing the Quarter 2 2025/26 financial review which highlighted a stable overall position for the Council, with a marginal projected overspend of £1,380 in the General Fund, largely driven by targeted investments in capital resilience, staffing pressures, and inflationary impacts such as pay awards and insurance premiums. Members were informed that the Council remained within its delegated budget variation limits, with reserves and balances forecast to remain above minimum thresholds. In relation to Capital, £10 million of expenditure had been rephased into future years and reflected revised delivery timelines for major housing and regeneration projects such as The Oval and Kenilworth. It was noted that the capital programme remained fully funded, with adjustments to financing reducing reliance on borrowing and revenue contributions due to higher-than-expected right to buy capital receipts. The Strategic Director and CFO advised that the General Fund 2025/26 budget now reflected the increase in the pay award. In relation to the Right to Buy receipts the Council had received, the Portfolio Holder for Housing advised that although tenants had the right to buy their Council properties, it was better for the Council to retain its council stock and retain the consequent rent revenue. Members thanked the Officers involved in the budgetary process for the substantial work in producing the report. It was
Word for word from the decision Stevenage published for this meeting. Source: democracy.stevenage.gov.uk

Follow this further

Built from Stevenage's papers

What the report saysPro

Report to Cabinet

Recommendations

General Fund

2.1That the 2025/26 second quarter projected net increase in General Fund expenditure of £1,380 be approved.

2.2That Members approve the use of EPR reserve funding for the initial supply of caddy liners, at a cost of £11,120.

2.3That Members note the proposed movement on reserves as detailed in paragraph 4.3.1.

2.4That Members approve Revenue Contribution to Capital Outlay (RCCO) of £150,000 to fund future urgent unplanned capital works.

1|Page Housing Revenue Account 2.5 That the 2025/26 second quarter net decrease in HRA expenditure of £164,550 be approved.

Capital Programme 2.6. That the General Fund capital budget re-phasing of £6.4 Million from 2025/26 to future years be approved. 2.7. That the Housing Revenue Account capital budget re-phasing of £3.6 Million from 2025/26 to future years be approved. 2.8. That net changes to budgets fully grant and external contributions funded of (£246K) in paragraph 4.9.2 be noted. 2.9. That General Fund virements in section 4.10 be approved. 2.10. That an additional £150K be added to the deferred works reserve funded by revenue contributions to capital in 2025/26. 2.11. That the proposed changes to the funding of the General Fund and HRA capital budgets in section 4.11 be approved.

3. BACKGROUND - GENERAL FUND

3.1Since the General Fund net budget of £10,753,540 was approved at February 2025 Council, Members have approved net budget changes of £28,460 as detailed in the chart below:1.1.3

2|Page 4. REASONS FOR RECOMMENDED COURSE OF ACTION AND OTHER OPTIONS

4.1General Fund – Budget Review

4.1.1 Following the second quarter review of the General Fund budgets officers are projecting an increase in the forecast budget spend for the year of £1,380.

4.1.2 The reasons for the overspend or less income are detailed below:

• Revenue Contribution to Capital (RCCO) £150K – as detailed in section 4.10.5 of this report, there is a shortfall in capital resources and, consequently, approval is sought to increase the deferred works reserve by £150K, from revenue reserves which are projected to be £6.599 Million and £93K above the Original Budget projection. Due to restricted availability of capital resources, only approved schemes are being considered for funding. Therefore, this contribution will provide additional flexibility to support any urgent unplanned works during 2025/26 and potentially beyond.

• The overall salary budget is forecast to overspend by £86K, primarily due to pressures within specific service areas. At the 1st Quarter, the pay budget increased by £262K, mainly relating to transitional vacancy.

i) Stevenage Direct Services £45K – this variance relates to additional agency staffing costs required to cover the weekend working, overtime, and sickness absence. Similar pressures have been experienced in previous years; therefore, a business unit review is scheduled to commence later in the year to address both the operational and financial challenges within the existing establishment structure.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
4 Appendix A General Fund Capital Strategy Q2Appendix 309 KB Download
PDF
4 Appendix B HRA Capital Strategy Q2Appendix 204 KB Download
PDF
4 Appendix C MRP Policy 2025-26 (Revised)Appendix 115 KB Download
PDF
SECOND QUARTER MONITORING REPORT FOR GENERAL FUND, HOUSING REVENUE ACCOUNT AND CAPITAL MONITORINGReport 627 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 18 attended
RH
Richard HenryChair, present
JT
Jeannette ThomasVice-Chair, present
MA
Myla ArcenoCommittee Member, present
RB
Rob BroomCommittee Member, present
CD
Coleen De FreitasCommittee Member, present
JH
Jackie HollywellCommittee Member, present
TP
Tom PlaterCommittee Member, apologies
LR
Loraine RossatiCommittee Member, present
SS
Simon SpellerCommittee Member, present
NW
Nigel WilliamsCommittee Member, present
LF
Luke FattorussoSecretary, expected
LJ
Lisa JeromeSecretary, expected

All 18 on the meeting page

On this subject at Stevenage

Search all
  1. SECOND QUARTER MONITORING REPORT FOR GENERAL FUND, HOUSING REVENUE ACCOUNT AND CAPITAL MONITORINGThis decision
  2. Second quarter revenue budget monitoring 2024/25 (including second quarter capital budget monitoring 2024/25)Approved
  3. Second quarter revenue budget monitoring 2023/24Decided
  4. First and second quarter capital budget monitoring 2023/24Decided
  5. Second quarter revenue monitoring report 2022/23 - general fund and housing revenue accountDecided
  6. Second quarter revenue monitoring report 2020/21 - general fundDecided

More from Stevenage Cabinet

All decisions
MeetingDecisionOutcome
10 Sep 2026 Apologies for absence and declarations of interestThere were no apologies for absence and no declarations of interest. Decided Open
10 Sep 2026 Minutes - cabinet 15 july 2026It was RESOLVED that the Minutes of the meeting of the Cabinet held on 15 July 2026 be approved as a correct record f... Approved Open
10 Sep 2026 Minutes of the overview and scrutiny and select committeesCabinet received a summary of the issues covered at the most recent meetings of the Overview and Scrutiny and Select ... Noted Open
10 Sep 2026 General fund medium term financial strategy update (2026/27 - 2030/31)Cabinet received a report updating the General Fund Medium Term Financial Strategy (MTFS) for 2026/27 to 2030/31, set... Noted Open
10 Sep 2026 Hra medium term financial strategy reviewCabinet received a report updating them on the Housing Revenue Account (HRA) Medium Term Financial Strategy (MTFS) fo... Noted Open