MINUTES - 7 JUNE 2022

Approved Finance 1 paper

Audit Committee approved this item on Wednesday 7 September 2022. Below is the council's own wording, with the papers it was decided on.

Item2

Resolved

It was RESOLVED that, subject to the replacement of “2029/20” with “2019/20” in the fifth paragraph of the preamble in Minute 5 – 2019/20 and 2020/21 External Audit of SBC Accounts – Update, the Minutes of the meeting of the Audit Committee held on 7 June 2022 be approved as a correct record and signed by the Chair.
Word for word from the decision Stevenage published for this meeting. Source: democracy.stevenage.gov.uk

Follow this further

Built from Stevenage's papers

What the report saysPro

Report to Audit Committee

STEVENAGE BOROUGH COUNCIL

AUDIT COMMITTEE MINUTES

Date: Tuesday, 7 June 2022 Time: 6.00pm Place: Council Chamber, Daneshill House, Danestrete, Stevenage

Present: Councillors: Teresa Callaghan (Chair), John Gardner (Vice-Chair), Myla Arceno, Stephen Booth, Alex Farquharson, Jackie Hollywell, Graham Lawrence CC, Maureen McKay and Loraine Rossati.

Start / End Start Time: 6.00pm Time: End Time: 6.52pm

1 APOLOGIES FOR ABSENCE AND DECLARATIONS OF INTEREST

Apologies for absence were received from Councillor Tom Wren and [name removed] (Independent Co-opted Non-voting Member).

There were no declarations of interest.

2 ELECTION OF VICE-CHAIR

It was moved, seconded and, following a vote, RESOLVED that Councillor John Gardner be elected as Vice-Chair of the Audit Committee for the 2022/23 Municipal Year.

3 MINUTES - 28 MARCH 2022

It was RESOLVED that the Minutes of the meeting of the Audit Committee held on 28 March 2022 be approved as a correct record and signed by the Chair.

4 TERMS OF REFERENCE

The Committee received a tabled set of revised Terms of Reference, which contained minor amendments.

It was RESOLVED that the Terms of Reference for the Audit Committee, as agreed by the Annual Council meeting on 25 May 2022, and with the minor amendments as per the version tabled at the meeting, be noted.

5 2019/20 AND 2020/21 EXTERNAL AUDIT OF SBC ACCOUNTS - UPDATE

The Committee received a verbal update from Ernst & Young in respect of the 2019/20 and 2020/21 External audit of SBC accounts.

Neil Harris (Ernst & Young) reminded Members that, at the joint Audit

1 Committee/Statement of Accounts Committee meeting held in late February 2022, they were advised that the 2019/20 audit of accounts was substantially complete, with a target of the end of April 2022 for full completion.

Neil explained that since then a national issue had arisen regarding how expenditure on replacement infrastructure was accounted for in local authority accounts. CIPFA was currently consulting in respect of this issue. This was very much a technical exercise to ensure that there was no material understatement or overstatement of infrastructure assets. Ernst & Young was waiting for the conclusion of this consultation process before signing off the 2019/20 accounts.

Neil also referred to an actuarial error relating to the 2019/20 accounts with regard to an overstatement of the Pension Fund assets concerning the Hertfordshire Building Control Consortium. An appropriate correction would therefore be made to the 2019/20 accounts.

Neil advised that he had agreed with the Strategic Director (CF) that the aim would be to conclude the 2029/20 audit by the end of July 2022.

In respect of the 2020/21 audit, Neil commented that fieldwork would be continuing throughout July 2022, although the external audit plan for the 2020/21 accounts would need to be reviewed before being presented to the Audit Committee.

Neil informed the Committee that he would be leaving Ernst & Young in early September 2022 to take up a senior position with the Financial Reporting Council.

In reply to a question from the Chair, Neil confirmed that he was committed to the completion of the 2019/20 audit. Ernst & Young was in the process of reviewing their Engagement Leads for Local Authority auditing. He undertook to ensure a smooth handover of duties, and agreed to advise the Committee of the name of the new Engagement Lead once appointed.

It was RESOLVED that the verbal update from Ernst & Young regarding the 2019/20 and 2020/21 External audit of SBC accounts be noted.

6 ANNUAL ASSURANCE STATEMENT AND ANNUAL REPORT 2021/22

The SIAS Client Audit Manager presented a report in respect of the SIAS Annual Assurance Statement and Annual Report 2021/22.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
MINUTES: 7 JUNE 2022Minutes 230 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 16 attended
TC
Teresa CallaghanChair, apologies
JG
John GardnerVice-Chair, apologies
MA
Myla ArcenoCommittee Member, present
SB
Stephen BoothCommittee Member, apologies
AF
Alex FarquharsonCommittee Member, present
JH
Jackie HollywellCommittee Member, present
GL
Graham Lawrence CCCommittee Member, apologies
MM
Maureen McKayCommittee Member, present
LR
Loraine RossatiCommittee Member, present
TW
Tom WrenCommittee Member, apologies
GG
Geoffrey GibbsCo-Optee, present
RS
Ramin ShamsSecretary, expected

All 16 on the meeting page

On this subject at Stevenage

Search all
  1. MINUTES - 7 JUNE 2022This decision
  2. Minutes - 11 june 2026Approved
  3. Minutes - cabinet 10 june 2026Approved
  4. Minutes - 10 june 2025Approved
  5. Minutes - cabinet 4 june 2025Approved
  6. Minutes - 24 june 2024Approved

More from Stevenage Audit Committee

All decisions
MeetingDecisionOutcome
2 Jun 2026 Sias annual assurance statement and internal audit report 2025/26RESOLVED that: · The Annual Assurance Statement and Internal Audit Annual Report 2025/26 be noted. · The results of t... Noted Open
2 Jun 2026 2025/26 annual governance statement and local code of corporate governanceRESOLVED that the report be noted. Noted Open
2 Jun 2026 Annual report of the audit committeeRESOLVED that the report be noted. Noted Open
2 Jun 2026 Exclusion of public and pressRESOLVED : 1. That, under Section 100(A) of the Local Government Act 1972, the press and public be excluded from the ... Decided Open
2 Jun 2026 Strategic risk registerRESOLVED that the report be noted. Noted Open