The SIAS Client Audit Manager presented a progress report with regard to the SIAS Internal Audit Plan 2022/23 (up to 19 August 2022). In reply to Members’ questions, the SIAS Client Audit Manager responded as follows: · The Cyber Security audit had identified gaps in the Council’s control framework to minimise cyber attacks . In particular, the Council only had a draft Information Security Policy and draft Cyber Incident Response Plan, and there had been insufficient capacity in the IT Team to manage cyber security due to the ongoing work regarding migration of the Council’s IT network to Windows 10. It was hoped that the high/medium priority recommendations would be actioned by December 2022. A Joint SBC/EHC Board had been established to closely monitor IT issues over the coming months, including the Windows 10 migration and cyber security; · The reason the migration to Windows 10 was taking a considerable time was due to work required to address and resolve inter-operability/integration issues of some of the considerable number of Council IT systems both during the migration and afterwards; and · It was confirmed that the follow up work with regard to the Landlord Health and Safety audit concerned improved processes in relation to the testing (for legionella, etc.) of water supplied to Council-owned buildings. It was
Word for word from the decision Stevenage published for this meeting.Source: democracy.stevenage.gov.uk
Members are recommended to: a) Note the Internal Audit Progress Report b) Note the Internal Audit Plan Changes c) Note the Status of Critical and High Priority Recommendations SIAS Internal Audit Progress Update Stevenage Borough Council
Contents
1 Introduction and Background 1.1 Purpose 1.2 Background
2 Audit Plan Update 2.1 Delivery of Internal Audit Plan and Key Findings 2.4 Internal Audit Plan Changes 2.5 Critical and High Priority Recommendations 2.7 Performance Management
Appendices: A Progress against the 2022/23 Internal Audit Plan B Implementation Status of Critical and High Priority Recommendations C Internal Audit Plan Items (April 2022 to March 2023) - Indicative start dates agreed with management D Assurance Definitions / Priority Levels SIAS Internal Audit Progress Update Stevenage Borough Council
1 Introduction and Background Purpose of Report
1.1To provide Members with: a) The progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s 2022/23 Internal Audit Plan to 19 August 2022. b) The findings for the period 1 April 2022 to 19 August 2022. c) Details of any changes required to the approved Internal Audit Plan. d) The implementation status of previously agreed audit recommendations. e) An update on performance management information to 19 August 2022.
Background
1.2Internal Audit’s Annual Plan for 2022/23 was approved by the Audit Committee at its meeting on 28 March 2022. The Audit Committee receive periodic updates against the Internal Audit Plan. This is the first update report for 2022/23.
1.3The work of Internal Audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit function is fulfilling its statutory obligations. It is considered good practice that progress reports also include details of changes to the agreed Annual Internal Audit Plan.
2 Audit Plan Update Delivery of Internal Audit Plan and Key Audit Findings
2.1As of 19 August 2022, 27% of the 2022/23 Internal Audit Plan days have been delivered (the calculation excludes contingency days that have not yet been allocated).
2.2The following final reports have been issued since the last Progress Report to the Audit Committee:
Date of Assurance Number of Audit Title Issue Level Recommendations Payroll (Assurance Mapping) Two Medium and Mar 2022 Reasonable 2021/22 One Low Priority Housing Rents 2021/22 Apr 2022 Substantial None One Medium and Debtors 2021/22 Apr 2022 Reasonable Three Low Priority One Medium Leaseholder Liability 2021/22 May 2022 Reasonable Priority One Medium and Housing Allocations 2021/22 Jun 2022 Reasonable One Low Priority Cyber Security (Assurance One High and Two Jul 2022 Limited Mapping) 2021/22 Medium Priority
Page 1 SIAS Internal Audit Progress Update Stevenage Borough Council
See definitions for the above assurance levels and recommendation priorities at Appendix D.
2.3The table below summarises the position regarding delivery of the 2022/23 approved projects to 19 August 2022. Appendix A provides a status update on each individual project within the 2022/23 Internal Audit Plan.
Status No. of Audits at this Stage % of Total Audits
Final Report Issued 1 3
Draft Report Issued 5 16 In Fieldwork/Quality 2 6 Review In Planning/Terms of 5 16 Reference Issued Allocated 18 59
Not Yet Allocated 0 0
Cancelled/Deferred 0 0
Total 31 100%
Internal Audit Plan Changes
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.