The Committee considered a report on the Contaminated Land Inspection Strategy following an external statutory consultation. It was RESOLVED that the Contaminated Land Inspection Strategy 2024-2029 be adopted subject to the track changes as set out in the report.
Word for word from the decision Stevenage published for this meeting.Source: democracy.stevenage.gov.uk
ADOPTION OF THE REVISED CONTAMINATED LAND INSPECTION STRATEGY
NON-KEY DECISION
Authors Christine Walker-Wells | 2247
Lead Officers Zayd Al-Jawad | 2257
Contact Officer Christine Walker-Wells | 2247
1 PURPOSE 1.1 To review and adopt the Council’s revised Contaminated Land Inspection Strategy.
2 RECOMMENDATIONS 2.1 That the Planning and Development Committee approves the adoption of the Contaminated Land Inspection Strategy 2024-2029, having completed external statutory consultation.
3 BACKGROUND 3.1 Section 78B(1) of Part 2A of the Environmental Protection Act 1990 (EPA 1990) places a duty on local authorities to inspect their areas to identify contaminated land and confers regulatory powers to deliver against that duty. 3.2 Contaminated Land Statutory Guidance produced by the Department for Environment, Food and Rural Affairs (DEFRA) in 2012 sets out how local authorities should meet these duties, including the need to have a written strategy setting out their strategic approach. The proposed Contaminated Land Inspection Strategy 2024-2029 attached at Appendix A is intended to meet this requirement and provides a brief overview of the contaminated land regime, its aims and objectives. 3.3 Any Part 2A inspection undertaken by the Council must be at its own expense and by its nature can consist of numerous phases under the supervision of environmental consultants. 3.4 Where contaminated land assessments conclude that there are unacceptable risks, as per Statutory Guidance, the Council must ensure these are addressed, typically through the completion of remedial works. Such works could comprise excavation of contaminated ground and sending to landfill, encapsulating the ground or cleaning the soil in situ. 3.5 Where no responsible party can be identified (e.g. landowner, developer, polluter), the cost may fall to the Council. Such costs have the potential to escalate to seven figure sums. 3.6 However, it is important to note that while Part 2A gives the Council powers to proactively deal with contaminated land, in almost all cases such land is assessed and dealt with through the development control system.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the press and publicRESOLVED : 1. That under Section 100(A) of the Local Government Act 1972, the press and public be excluded from the m...
26/00531/fph - 134 shephall viewIt was agreed that the matter could be discussed outside the meeting to consider whether any further action could be ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.