Local Enforcement Plan MARCH 2024 This document was classified as: OFFICIAL
Contents Page No. 1. INTRODUCTION; 2
2. PLANNING ENFORCEMENT PROCESS; 3
3. WHAT IS A BREACH OF PLANNING CONTROL 4
4. REPORTING A BREACH OF PLANNING CONTROL 6
5. HOW WE WILL INVESTIGATE AND ASSESS A BREACH 7
6. ASSESSING THE IMPACT AND WHETHER ACTION IS REQUIRED 9
7. PLANNING ENFORCEMENT ACTION AND POWERS AVAILABLE 10
8. SERVICE STANDARDS 11
APPENDIX 1 – TYPES OF ENFORCEMENT ACTION 12
The Five Lamps Thornaby
Stockton on Tees Local Enforcement Plan 1 This document was classified as: OFFICIAL
1. INTRODUCTION;
1.1The National Planning Policy Framework (NPPF) encourages effective enforcement action to maintain public confidence in the planning system. It recommends that local planning authorities (LPA’s) publish a local enforcement plan to help proactively manage planning enforcement in a way that is appropriate to their area. As set out in the NPPF, planning enforcement action is discretionary, and the local planning authority should act proportionately in responding to suspected breaches of planning control.
1.2Stockton-on-Tees Borough Council believes that planning compliance has an important role in ensuring that the policies of the Local Plan are effective and high standards of development are achieved across the Borough.
1.3The planning enforcement function sits within the Planning Services team and the purpose of this local enforcement plan is to set out our approach to processes and investigating alleged breaches of planning control.
Stockton on Tees Local Enforcement Plan 2 This document was classified as: OFFICIAL
2. PLANNING ENFORCEMENT PROCESS; 2.3. In certain cases, the investigation may require a site visit to establish whether a breach of planning control has taken place. There may also 2.1. Planning enforcement is a reactive service whereby requests are be some occasions where a series of visits are required to be able to made for potential breaches of control to be investigated. These establish if there is a breach in planning control. requests can come from the public, elected members, stakeholders, or council employees. 2.4. Where there is no breach of planning control, the investigation will be closed, the relevant parties informed, and no further action General process; taken. Where a matter has been previously investigated and no 2.2. Once a case is received it will be logged and allocated to an officer to breach of control was found, there will be no reinvestigation of the investigate. Initially the enforcement process involves an assessment case unless the complainant is able to provide substantive evidence as to whether there is a breach of control or not. of the alleged breach.
Figure 1: Main steps in an Enforcement investigation 2.5. If a breach of planning control has occurred, then a more detailed assessment of the breach and its associated impacts will often be required. In some circumstances the complainant may be advised that Initial assessment including additional evidence is required to assess the impacts and may be determining if there is a asked to provide diaries and records over the nature and type of breach and if so, case priority. activity. The use of photographs with a time/date stamp is always beneficial evidence.
Investigation including site 2.6. The council may also need to liaise with other council departments or visit(s) outside bodies to be able to form a view on the impacts of a breach in planning control.
2.7All of the information and evidence is then considered and a decision Decision on enforcement as to whether it is expedient to take enforcement action against any breach of planning control or not, is then taken.
Stockton on Tees Local Enforcement Plan 3 This document was classified as: OFFICIAL
3. WHAT IS A BREACH OF PLANNING CONTROL
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
LEP (March24) Final_ /4/24Report | 999 KB | DownloadRead as text |
PDF |
Planning (Development Management) and Adoption of Open Space /4/24Report | 522 KB | Download |
PDF |
Progress Update: Scrutiny Review of Planning (Development Management) and Adoption of Open SpaceReport | 141 KB | Download |
Follow Place Select Committee at Stockton-on-Tees and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Oct 2026 | Chair's Update and Select Committee Work ProgrammeAGREED the work programme be noted. <TRAILER_SECTION> | Agreed | Open |
| 14 Sep 2026 | Chair's Update and Select Committee Work ProgrammeAGREED the work programme be noted. <TRAILER_SECTION> | Agreed | Open |
| 13 Jul 2026 | Chair's Update and Select Committee Work ProgrammeAGREED that site visits would be arranged and the work programme be noted. | Agreed | Open |
| 15 Jun 2026 | Scrutiny Review of Governance of Capital ProjectsAGREED that: the Action Plan be approved a deadline date for refreshing the Concordat for Communication and Consultat... | Agreed | Open |
| 15 Jun 2026 | Chairs Update and Work Programme 2026-2027AGREED the work programme be noted and site visits arranged. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.