Proposed Changes to Ball Green Children's Centre (Forward Plan Item 57/01CS)
ApprovedExecutive1 paper
(archived) Executive and Members Board approved this item on Tuesday 28 August 2007. Below is the council's own wording, with the papers it was decided on.
(i) That approval is given to develop a split site Children’s Centre to serve the communities at Ball Green and Norton. (ii) That appointment of Cityworks as a single tender to be approved as contractor to complete the children’s centre works at the Ball Green site.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Report to (archived) Executive and Members Board, 8 pages
Financial implications
It is expected that all five Children’s Centre projects will be delivered with the allocated capital of £2,895,000 available. The Children’s Centre Initiative is centrally funded through the General SureStart Grant and will not impact on the City Council's formula spending share allocation.
Contractor Appointment The construction works for the Ball Green Children’s Centre have been estimated at £370,000. This does not exceed the threshold for European Procurement rules and so is not subject to these regulations.
D:\moderngov\data\published\Intranet\C00000127\M00000187\AI00005853\ChangestoBallGreenChildrensCentre0.doc page 2 of 8 Executive and Members Board Amendment to the Ball Green Children’s Centre.
Risk implications
The Phase 2 Children’s Centres initiative requires Local Authorities to deliver services in all the 30% disadvantaged communities. These services must be delivered by March 2008. If this target is not achieved, the DfES will not release the capital funding for these projects.
If a decision is taken that we are to follow the competitive tendering process there is a risk that the project will not be completed by 31st March 2008. See table below.
The implications of this could be capital clawback and abortive costs would need to funded through City Council funding.
Tendering process starts 12 Aug Tender report from Property Services 14 Sept Submit for appointment of contractor 14 Sept Implementation of EMB process 7 Nov Estimated construction period 90 days End date 21 March 2008 Designation deadline 31 March 2008 Equip centre and designation by TFC 2-4 weeks Estimated end date 14 April 2008
Recommendations
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow (archived) Executive and Members Board at Stoke-on-Trent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.