Resolved
That approval is given to change the location of the proposed Children’s Centre in Tunstall to the Community Centre site in High Street, Tunstall .
(archived) Executive and Members Board approved this item on Tuesday 28 August 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
That approval is given to change the location of the proposed Children’s Centre in Tunstall to the Community Centre site in High Street, Tunstall .
This report updates members on the proposed changes to the location of the Tunstall Children’s Centre, as previously reported in the Forward Plan issue 43, May – Aug 2006, item 43/01 CS
It is proposed to change the location of the Children’s Centre from the former Alexandra Pottery Works site in Tunstall, to the Community Centre, High Street, Tunstall.
The new site will be delivered within the funding available.
Chief Officer approval has already been obtained to build a Children’s Centre within the Tunstall area. This Centre which was to be built in partnership with Dransfield Development and based on the former Alexandra Pottery works in Tunstall, however due to the withdrawal of the PCT from this project and the subsequent risk that this development would not be built within the timescales set by the DfES, it was necessary and prudent that Property Services was instructed to identify an alternative site.
The site identified is the Community Centre building based in High Street, Tunstall, which will be available during November 2007 to enable refurbishment works to start.
If agreement is given to proceed with this recommendation, there will be a capital and revenue commitment from the General SureStart grant.
Implications Legal Financial Resources (include HR, Property, IT, resource) Equality and diversity Environment Risk Implications indicated here must be explained in the body of the report at section 6
D:\moderngov\data\published\Intranet\C00000127\M00000187\AI00005852\ChangestoTunstallChildrensCentre0.doc page 1 of 7 Executive and Members Board Proposed Changes to the Location of Tunstall Children’s Centre.
It is expected that all five, Phase 2, Children’s Centre projects will be delivered within the allocated capital of £2,895,000 and revenue funding available. The Children’s Centre Initiative is centrally funded through the General SureStart Grant and will not impact on the City Council's formula spending share allocation.
The estimated costs of locating a Children’s Centre on the former Alexandra Pottery site, in partnership with Dransfield Developments, amounts to £200,000 capital plus an annual charge of £40,570 for 25 years.
The estimated costs of locating a Children’s Centre at the Community Centre, High Street, Tunstall amounts to £350,000 plus an asset rental of £31,500 for 25 years.
The Phase 2 Children’s Centres initiative requires Local Authorities to deliver Children’s Centre core services in all of the 30% most disadvantaged communities by 2008.
If approval is not obtained to locate the Children’s Centre at the Community Centre alternative sites would need to be identified, therefore additional time spent on researching the area would delay the development of a Centre in this ward and due to the short timescales there would be an increased risk of capital and revenue claw-back by DfES.
D:\moderngov\data\published\Intranet\C00000127\M00000187\AI00005852\ChangestoTunstallChildrensCentre0.doc page 2 of 7 Executive and Members Board Proposed Changes to the Location of Tunstall Children’s Centre.
That approval is given to change the location of the proposed Children’s Centre in Tunstall to the Community Centre site in High Street, Tunstall.
D:\moderngov\data\published\Intranet\C00000127\M00000187\AI00005852\ChangestoTunstallChildrensCentre0.doc page 3 of 7 Executive and Members Board Proposed Changes to the Location of Tunstall Children’s Centre.
Report Purpose
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Proposed Changes to location of Tunstall Children's Centre (Forward Plan Item 57/01CS)Forward_plan | 7 pages | DownloadRead as text |
Follow (archived) Executive and Members Board at Stoke-on-Trent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 May 2009 | North Staffordshire Sub Regional Choice Based Lettings Scheme (Forward Plan Item 79/05 RH)To note and approve the inclusion of Stoke-on-Trent City Council with Newcastle Borough Council in the North Stafford... | Approved | Open |
| 27 May 2009 | City of CultureThat the Executive and Members Board approve in principle the recommendation that officers commence the work necessar... | Approved | Open |
| 27 May 2009 | Exclusion of the PublicResolved - That under Section 100(A )( 4) of the Local Government Act, 1972, the public be excluded from the meeting ... | Decided | Open |
| 27 May 2009 | Urgent Item of BusinessAgreed – That under Section 100(b )( 4) of the Local Government Act 1972, the following item of business be dealt wit... | Agreed | Open |
| 27 May 2009 | Transformation and Resources Overview and Scrutiny Committee - Recommendation in response to a Call-In - Proposal to re-phase and accelerate the transfer of services to the Strategic Partnership (Forward Plan Item 69/02 CR)That the Executive and Members Board re-affirm its original decision of 29 April 2009 that: Approval was given at the... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.