It was agreed that members would receive a modified version of the organigram and that the Director of Regeneration would submit monthly updates to appropriate committees. Following members concerns expressed regarding the provision of alternative facilities for user groups as works were being carried out it was agreed that a consultation meeting be held to assess the needs of the groups and to help provide alternative accommodation.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Report to (archived) Mitchell Memorial Youth Centre Committee
Summary
On the 15th November 2007, the City Council submitted a bid to the £30 million Community Assets Programme, funded by the Office of the Third Sector and administered by the Big Lottery Fund. On the 28th March 2008 The City Council received an in principle offer of £1,948,924 to support the delivery of the project, which represents the largest award administered by the programme. The City Council has completed a Capital Delivery plan for the Project which has been re-submitted to the Community Assets Programme on 14th January 2009. The delivery of the Capital Development Plan is subject to the final approval from the City Council for the funding and transfer of the asset.
An initial architectural feasibility study was undertaken internally which formed the basis of the cost estimate for the original application. Following the in principle award from the Big Lottery, an internal review of the original cost estimates associated with the original bid was undertaken which has indicated an increase in capital costs. A detailed cost plan was commissioned externally which confirms the increase in costs of the project.
4.0Background The application to the Community Assets Programme was submitted on 15th November 2007. The City Council received notification from the Big Lottery Fund on the 28th March 2008 that Stoke-on-Trent City Council has received an in principle offer of £1,948,924 to support the delivery of the Mitchell Memorial Youth Arts Centre Project, which represents the largest award administered by the Big Lottery Fund in the UK under this programme.
In August 2008 an additional application was submitted to the Coalfields Regeneration Trust for £285,200 to support the delivery of the programme and reduce the financial investment required from the City Council to deliver the project. An in principle approval was received in November 2008 from the Coalfields Regeneration Trust. th At City Council on 4 December 2008 it was agreed that the use of £300,000 from capital resources to appoint a) design consultants to update the detail design; and
Report Page 1 b) property consultants to undertake any necessary additional surveys prior to implementation of the project. th th A re-submission of the delivery plan has been made to CRT & the Big Lottery on 5 7 14 January 2009 which aligns with advised increase in capital cost of the scheme and the extended programme to March 2011 for scheme operation.
Procurement & Delivery
The design team selection process has been completed and a project steering group has been established to manage the project in consultation with representatives from the Committee and the user groups. th Following on from the approval at Full Council on 4 December 2008 to proceed with additional surveys to de-risk the project, the following work has been commissioned by the authority
i) Topographical & Building Measurement Survey ii) Building & Structural Survey iii) M&E / Utility interface Survey iv) Type 3 Asbestos Survey v) Geotechnical & Contamination Survey.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
6Mitchell Memorial Refurbishment ProjectThis decision
Hear about the next one first
Follow (archived) Mitchell Memorial Youth Centre Committee at Stoke-on-Trent and we tell you when its next papers are published, before the meeting rather than after it.
Refurbishment and Management UpdateIt was agreed that suggestions should be emailed to the Interim Manager and considered at the next meeting of the Com...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.