(archived) Mitchell Memorial Youth Centre Committee, Friday 4 February 2011 at 10.00am

Refurbishment and Management Update

Agreed Committee 1 paper

(archived) Mitchell Memorial Youth Centre Committee agreed this item on Friday 4 February 2011. Below is the council's own wording, with the papers it was decided on.

Item31

Resolved

It was agreed that suggestions should be emailed to the Interim Manager and considered at the next meeting of the Committee. Alan Hill confirmed that he was still in contact with founder members of the Mitchell Memorial Youth Theatre and would make some enquires. A discussion was also held on publicity for the launch event, the possibility of a plaque unveiling and the necessity for any plaques to be sited prominently at the Theatre. Alan Hill specifically requested that a plaque be placed above the seat where Mary Blakeman , the founder of the Mitchell Memorial Youth Arts Centre User Group, used to sit in the auditorium. Gerry Clarke, Principal Solicitor, stated that a condition of both grant agreements was that the Big Lottery Fund and the Coalfields Regeneration Trust must be notified of the date of the launch event, as they may want to send a representative. A motion moved by Councillor Kent- Baguley and seconded by Councillor Lyth “that an additional meeting of the Mitchell Memorial Youth Committee be arranged for Friday, 25 ... view the full minutes text for item 31.
Word for word from the decision Stoke-on-Trent published for this meeting. Source: moderngov.stoke.gov.uk

Follow this further

Built from Stoke-on-Trent's papers

What the report saysPro

Report to (archived) Mitchell Memorial Youth Centre Committee

Background

At full Council on 19th February it was agreed that • The City Council approves the arrangements for the delivery of the project. • An additional allocation of £1.83m of capital resources be approved • The future Revenue costs be underwritten (£158K year 1, max £150k/yr for following 4 yrs) • Offers of Financial assistance be accepted from BLF (£1.94m) & CRT (£0.285m)

On 15th April 2009 Following detailed assessments of the re-submitted Delivery Plans BLF have given funding approval for the scheme, which represents the highest level of grant award from the National Community Asset programme. CRT funding has also been approved. Both these funding streams are now being drawn down against the project. 2.0 Procurement & Delivery The design team selection process has been completed and a project steering group has been established to manage the project in consultation with representatives from the Committee and the user groups.

Following on from the approval at Full Council on 19th February 2009 to proceed with the project, the following work has been completed by the authority on the Capital build

• Initial Baseline Surveys completed • User Group Workshops initiated to capture requirements • Detailed Design carried out • Planning Permission Obtained for scheme • Building Regulations approval of the scheme • Following Cabinet approval, award of Principal Contractor role to J&S Seddon • Start on site commenced 12th October 2009 • Initial mobilisation secured site & erected hoardings • ‘Make it ’ branding incorporated into hoarding • Start on-site press release & photo shoot • Temporary roofing to main auditorium • Asbestos Removal completed • Demolition complete • Piling to front foundations installed • Blockwork & Brickwork to rear extensions installed • Front extension issued for Planning • Windows installed to Cartwright House • Crittall Windows delivered for main Theatre • Completion of first fix M&E to theatre • Front Extension approved by Planning • Contractor Pricing obtained for Extension • Engineers Estimate obtained for extension • Brickwork & Blockwork to rear extension complete • Roofing complete to rear extensions • Lift installation complete • Floor screed laid to extensions & café area • Second fix joinery including doors, skirting boards • Second fix M&E equipment including radiators, plumbing • Completion to all glazing • Final wall finishes being applied • Seats being delivered • Seating Installed to Auditorium & Balcony • Carpeting / Flooring installed • Partition Walls to Dance studio installed • Completion of Second Fix items to Main Theatre • Commissioning of audio, lighting, plumbing, etc In this period

• Foundation Construction to front extension • Café Floor construction • Preparation of holding down arrangements for Café Steelwork • Monitoring long lead-in items related to glazing • Finalisation of finishes to main building including installation of acoustic panelling

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Refurbishment and Management UpdateReport 91 KB DownloadRead as text

At this meeting

Whole meeting

More from Stoke-on-Trent (archived) Mitchell Memorial Youth Centre Committee

All decisions
MeetingDecisionOutcome
29 Jan 2009 Mitchell Memorial Refurbishment ProjectIt was agreed that members would receive a modified version of the organigram and that the Director of Regeneration w... Agreed Open