That approval is given to:- a. the Director of Central Services to accept an offer of grant from the Heritage Lottery Fund (HLF) for the restoration of Burslem Park, and subsequently to sign a contract with the grant-giving body, subject to being satisfied with all associated terms and conditions; b. seek tenders from appropriate design consultants to assist with the detailed design and specification, production of tendering documents and packages, and management of works contracts for the restoration project; and c. seek tenders from appropriate works contractors to undertake the delivery of the restoration project.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
a. the Director of Central Services to accept an offer of grant from the Heritage Lottery Fund (HLF) for the restoration of Burslem Park, and subsequently to sign a contract with the grant-giving body, subject to being satisfied with all associated terms and conditions;
b. seek tenders from appropriate design consultants to assist with the detailed design and specification, production of tendering documents and packages, and management of works contracts for the restoration project; and
c. seek tenders from appropriate works contractors to undertake the delivery of the restoration project.
Report Summary:
1.1Following earlier City Council approval, officers have been working with Burslem Park Partnership (a ‘friends’/community group) to secure funding (just over £2 million) from the Heritage Lottery Fund (HLF) for the comprehensive restoration of historic Burslem Park. This process started in 2006 when the Council initially bid for, and was awarded up to £50,000 by HLF towards the preparation of a full Stage 1 grant application, which was subsequently submitted in March 2008, following Executive approval in January 2008.
1.2The City Council was successful with the Stage 1 application which was approved in October 2008. Over the subsequent 12 months officers, supported by a consultancy team experienced in historic park restoration, developed the project details towards making a Stage 2 application which was submitted within the target deadline on 12th October 2009. HLF requires 6 months to consider the detailed funding application and a decision is expected in April 2010.
Report Page 1 1.3. In anticipation of, and subject to, a positive HLF decision, it is important from a timing and programming perspective, that the Council is in a position to formally confirm acceptance of the funding, and appoint appropriate design consultants, at the earliest opportunity to support the implementation of the restoration project. Consequently it is proposed to undertake some ‘advance’ work to seek and evaluate consultancy tenders between January and March 2010. If HLF funding is approved, then the Council will be able to appoint the successful tenderer almost immediately after formal confirmation. Alternatively, if the grant application is turned down, the City Council would obviously not proceed to appointing a consultant.
Supporting Information:
2.1Report Purpose
This report seeks approval to authorise acceptance of a grant offer for the project, and to obtain tenders from appropriate design consultants and works contractors to enable the delivery of the restoration project, subject to HLF approval of the funding submission.
2.2Project Timescale
The process of seeking funding from HLF is long, essentially because it is a two-stage process, and requires very detailed information which takes time to prepare, and consequently HLF’s evaluation and assessment timescale is quite long too. The key project milestones are:-
Bid to HLF for Planning Grant submitted September 2006 Completed
HLF award Planning Grant January 2007 Completed
Parks Consultant appointed to help prepare Stage 1 May 2007 Completed application
Submission of Stage 1 application to HLF March 2008 Completed
Stage 1 approval by HLF October 2008 Completed
Submission of Stage 2 application to HLF October 2009 Completed
Anticipated Stage 2 decision by HLF, and subsequent April 2010 formal City Council acceptance
Design consultant appointed to support the detailed delivery April 2010 of the project (assuming HLF approval)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.