Relocation of Burslem Library (Forward Plan Item 019)

Approved Executive 1 paper

Cabinet approved this item on Wednesday 27 January 2010. Below is the council's own wording, with the papers it was decided on.

Item153

Resolved

That Cabinet approves, in principle, the interim relocation of Burslem Library to the Ceramica Annexe in Burslem Town Centre, subject to satisfactory lease being established.
Word for word from the decision Stoke-on-Trent published for this meeting. Source: moderngov.stoke.gov.uk

Follow this further

Built from Stoke-on-Trent's papers

What the report saysPro

Report to Cabinet

Recommendations

1. For the Cabinet to approve, in principle, the interim relocation of Burslem Library to the Ceramica Annexe in Burslem Town Centre, subject to satisfactory lease being established.

Report Summary:

1.1Burslem Library has operated out of the ground floor of the Burslem School of Art building since November 2008. The accommodation in the School of Art is inadequate with insufficient space for the library to operate effectively. The space constraints mean the library is only able to offer a reduced service with fewer PC’s and books than would normally be provided. Use of the facility – as measured in terms of visits and issues – has declined dramatically with a reduction of 60% in the number of visits and 41% in the number of issues in the period from November 2008 to June 2009.

1.2This has been subject to discussions which have taken place on the viability of relocating the library and other council services to the Old Town Hall. The outcome of this is a recommendation to relocate the library to the Ceramica Annexe as soon as possible. It is felt that this represents a good use of the Annexe building and is the best solution for the Library service and for the people of Burslem.

1.3Protracted discussions have taken place on the viability of relocating the library and other council services to the old town hall. These are still subject to ongoing dialogue. In the meantime it is recommended the library service be relocated to the Ceramica Annexe. This is on an interim basis until the strategic service model for -

Report Page 1 of 7 and future use of - the Old Town Hall is fully determined.

Supporting Information:

Context

2.1Burslem Library was forced to vacate the Wedgwood Institute building in October 2008. This was as a consequence of serious maintenance and health and safety issues with the Institute and the fact that the building was no longer suited to the requirements of a modern library service. The Library was moved hastily to the School of Art across the road and commenced operating from there in early November that year. This was seen as a temporary move until a permanent location could be found.

2.2In the review of the 2004 Atkins Burslem Masterplan Hypostyle recommended that Burslem Library should consider re-locating to the annexe building of Burslem Old Town Hall.

2.3In the period from November 2008 to June 2009, visits to the library have dropped by an average of 60% per month compared with the previous year, while issues have reduced by 41%. There is now a genuine concern that the Library will become unsustainable unless action is taken quickly. Given the relatively small number of community facilities in the Burslem area, coupled with the concerns about the lack of footfall in the town centre, the loss of the Library would have serious consequences for the town and for local people. There would also be implications for literacy levels and educational attainment.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Relocation of Burslem Library (Forward Plan Item 019)Forward_plan 53 KB DownloadRead as text

At this meeting

Whole meeting

More from Stoke-on-Trent Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Extension to funding agreement between Stoke-on-Trent City Council and Thrive at Five (Notice of Decisions Reference: 2482)Agreed ( i ) - Approval is granted to extend the funding agreement between Stoke-on-Trent City Council and Thrive at ... Agreed Open
3 Nov 2026 Soft Block Fostering Options (Notice of Decisions Reference: 2468)Agreed ( i ) - That approval is granted to undertake a competitive procurement exercise for a soft block fostering co... Agreed Open
3 Nov 2026 Youth Justice Strategic Plan (Notice of Decisions Reference: 2470)Agreed - That Cabinet approves the Youth Justice Plan 2026/27 and recommends its adoption by the City Council. N.B. T... Agreed Open
3 Nov 2026 Reviewing powers for reducing anti-social behaviour including requiring the removal of facing coverings where necessary and appropriate (Notice of Decisions Reference: 2477)Agreed ( i ) – That Cabinet note the current Public Spaces Protection Orders (PSPOs) operating within Hanley and Long... Agreed Open
3 Nov 2026 Housing Revenue Account (HRA) Rent Setting Report 2027/28 (Notice of Decisions Reference: 2457)Agreed - That Cabinet recommends to City Council that, as part of the budget setting processes approval is given to: ... Agreed Open