The immediate replacement of 30 vehicles that have reached a point of being uneconomical for repair, to be financed via lease or outright purchase based upon an assessment of the best value for money solution. 2. Approval of the Vehicle Proposal Criteria detailed in Appendix 1of the report submitted to Cabinet. 3. That Cabinet agree in principle that 14 of the low risk vehicles are purchased outright at a cost of £416,000. The acquisition of these capital assets will need to be incorporated into the Capital Programme and will be fully funded from a revenue contribution via the Transport Reserve which stands at £433,000. This amendment will be proposed in an overarching review of the Capital Programme to be submitted to Council for approval in September 2011. 4. That Cabinet agree that the remaining 16 Vehicles be replaced through the use of 5 year operating leases at an annual cost of £255,000. These costs will continue to be financed through direct charges to Client Department against their existing revenue budgets. 5. That the Director of City Renewal, following consultation with the relevant Cabinet Member(s), be authorised to determine the most appropriate form of branding for use on City Council vehicles.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Report Title: Vehicle and Plant Replacement Programme
Date: 28th July 2011 Report of: Director of City Renewal Contact officer(s): Mark Smith, City Services Email: [email protected] Tel. 01782 232389 Cabinet Member Councillor Janine Bridges Cabinet Member for City Services Type of Decision Key Decision Forward Plan Ref: 155 Wards Affected: All Wards
1. Purpose of the Report: 1.1 This report is the first of two which together propose to drive down fleet purchase and maintenance costs. A comprehensive review of the fleet service is currently being undertaken and a full business case to propose future management and financing arrangements will be presented for consideration to a future Cabinet meeting. 1.2 Accordingly this report concentrates on vehicle replacement for 30 vehicles that are in urgent need of replacement to reduce the risk of front line operational failure and seeks to recommence the currently stalled vehicle replacement programme.
2. Recommendation(s) 2.1 The immediate replacement of 30 vehicles that have reached a point of being uneconomical for repair, to be financed via lease or outright purchase based upon an assessment of the best value for money solution. 2.2 Approval of the Vehicle Proposal Criteria detailed in Appendix 1. 2.3 That Cabinet agree in principle that 14 of the low risk vehicles are purchased outright at a cost of £416,000. The acquisition of these capital assets will need to be incorporated into the Capital Programme and will be fully funded from a revenue contribution via the Transport Reserve which stands at £433,000. This amendment will be proposed in an overarching review of the Capital Programme to be submitted to Council for approval in September 2011. 2.4 That Cabinet agree that the remaining 16 Vehicles be replaced through the use of 5 year operating leases at an annual cost of £255,000. These costs will continue to be financed through direct charges to Client Department against their existing revenue budgets.
Report Page 1 2.5 That the Director of City Renewal, following consultation with the relevant Cabinet Member(s), be authorised to determine the most appropriate form of branding for use on City Council vehicles.
3. Context and Implications 3.1 The recent cessation in the vehicle replacement programme and the poor management of the fleet service in recent years has resulted in a substandard fleet that struggles to provide and maintain a front line service. The Council paused its vehicle replacement programme until all the blue book savings had been signed off by Full Council. The Council should recommence the currently stalled vehicle replacement programme to prevent a serious service failure and excessive maintenance costs. 3.2 There are a number of front line vehicles that need to be replaced as they are becoming uneconomical to maintain. It is important, if the viability of the services is to be maintained, they are replaced at the earliest possible opportunity.
Other Implications to be taken into consideration: Legal: The Council can utilise an existing Buying Solutions Framework Contract for the purchase of the vehicles, this approach has been approved by Procurement and will avoid the cost of getting out to tender. Legal Services will also be instructed to carry out the legalities of joining the Framework
Financial: As detailed in the main body of the report, the Transport Services Manager is addressing the legacy issues associated with an ageing fleet that is experiencing escalating maintenance costs that are outstripping the cost savings associated with secondary and tertiary leases for older vehicles past the primary lease period.
The proposal to utilise the Transport Reserve of £433,000 to finance the outright purchase of a number of low risk vehicles, represents the first stage of a fundamental review of the management and financing of the vehicle fleet.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.