Resolved
That Cabinet notes the results of the Public Consultation carried out for the City Centre Public Realm Scheme and approves the progression of detailed designs, tender packages, procurement and construction of Phase 1 and Phase 2 improvements as detailed in this report. 2. That the Cabinet approve the proposed development of an Asset Management Plan for the City Centre Public Realm Scheme and provide an in principle commitment for revenue funding in the budget setting process for 2012/13 and future years, to maintain the scheme upon completion (£120,000). 3. That the Cabinet approve the appointment of a contractor for Phase 1 works with an option to include Phase 2 works, in accordance with the City Council’s procurement procedure as proposed in this report. 4. When considering the capital budget for 2013/14, consideration should be given to the allocation of £3.46m in order to carry out phase 3 works.