That Cabinet notes the progress being made in the wider property rationalisation review and the financial implications. 2. That Cabinet agrees, in principle, the disposal of the buildings noted in Appendix A of the report submitted to Cabinet following the proposed consolidation of staff into fewer buildings and the re-development of the remaining buildings. 3. For those properties listed at Appendix A of the report submitted to Cabinet that are currently not in operation, that Cabinet agree to delegate to the Assistant Chief Executive, in consultation with the Director of Place and the Cabinet Member for Regeneration, Planning and Transportation, authority to bring forward assets for marketing and development at the earliest opportunity to achieve best value for money. 4. Having agreed the disposal in principle, that Cabinet agree that consultation can be undertaken with relevant residents on customer access proposals and with staff on accommodation proposals. 5. That Cabinet receives a paper at its December meeting outlining the results of the consultations, and final proposals for disposal, re-development and relocation of staff. This is an Urgent Decision and is therefore not subject to call-in.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
CABINET City Wide Administrative Property Rationalisation
Date 24 October 2013 Report of Assistant Chief Executive Contact officer(s) Peter Lewis AD Finance Jo Tyzzer AD Regeneration Development and Planning Cabinet Member Cllr Rosenau - Cabinet Member for Regeneration, Planning and Transportation Type of Decision Key Decisions Wards Affected No ward implications at present
1. Purpose of Report 1.1 To bring Cabinet up to date on the progress of the wider property rationalisation review, the implications for those buildings due to be closed as a result of the Central Business District development, and the resulting financial implications of both projects.
1.2This item is an urgent decision due to the need to commence the consultation process with staff and other appropriate stakeholders at the earliest opportunity. The views received can then be used to inform any future reports required as part of the decision making process on this issue.
2. Recommendation(s) 2.1 That Cabinet notes the progress being made in the wider property rationalisation review and the financial implications.
2.2That Cabinet agrees, in principle, the disposal of the buildings noted in Annex A following the proposed consolidation of staff into fewer buildings and the re- development of the remaining buildings.
2.3For those properties listed at Annex A that are currently not in operation, that Cabinet agree to delegate to the Assistant Chief Executive, in consultation with the Director of Place and the Cabinet Member for Regeneration, Planning and Transportation, authority to bring forward assets for marketing and development at the earliest opportunity to achieve best value for money.
2.4Having agreed the disposal in principle, that Cabinet agree that consultation can be undertaken with relevant residents on customer access proposals and with
Report Page 1 staff on accommodation proposals. 2.5 That Cabinet receives a paper at its December meeting outlining the results of the consultations, and final proposals for disposal, re-development and relocation of staff.
3. Options 3.1 Do not consult. Due to the scale of the proposed changes it is considered that consultation, even at this early stage is essential and therefore the option not to consult is not considered. 3.2 Chose only the buildings originally considered under the original plan for Central Business District. This option would not allow us to consider the customer service and other projects which are so closely linked to property rationalisation and the need for maximising savings. 3.3 Alongside the core buildings various other property options were considered 1. Keeping all our fit-for-purpose small buildings, but with the high risk that there would still not be sufficient space and this would spread out a significant number of staff and so partially lose the benefits from bringing teams together. 2. Keeping Swann House, which has the benefit of retaining many Children’s Services staff where they are currently located. However, this option would still be short of 100 desk equivalent spaces, excluding any demand from partners, which is a significant risk. Additionally, just keeping Swann House means there would still be an issue accommodating the Council’s training requirements and the Music Service, as their space needs could not be met in one building. 3. Keeping the Civic Centre, together with the administrative part of Stoke Town Hall that was not originally proposed for disposal. This would provide sufficient general capacity and, additionally, flexibility to cater for the training and Music Service needs and transition during the moves.
Reason for Decision - how the proposal supports the Mandate for Change Make Stoke-on-Trent the place to bring business Support and develop existing business Work with people to promote independence and healthy lives Make Stoke-on-Trent a great city to live in An effective and confident council
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.