Item430

Resolved

That Cabinet note the results of the consultation. 2. That Cabinet confirmed the intention, as outlined in the report to Cabinet on 24 October 2013, to dispose of buildings, consolidate staff into fewer buildings and agree that work can continue to plan for the refurbishment of the buildings that are to be retained. 3. That Cabinet agree that colocation of partners, where value for money can be demonstrated, is an objective of the property rationalisation programme. 4. That Cabinet agree the establishment of a steering group of officers and Cabinet Members to provide guidance and direction to the property rationalisation programme.
Word for word from the decision Stoke-on-Trent published for this meeting. Source: moderngov.stoke.gov.uk

Follow this further

Built from Stoke-on-Trent's papers

What the report saysPro

Report to Cabinet, 6 pages

Open

CABINET City Wide Administrative Property Rationalisation

Date 19 December 2013 Report of Assistant Chief Executive Contact officer(s) Jo Tyzzer AD Regeneration Development and Planning

Cabinet Member Cllr Rosenau - Cabinet Member for Regeneration, Planning and Transportation Type of Decision Key Decision Wards Affected All Wards

1. Purpose of Report 1.1 To inform Cabinet of the results of the resident and staff consultation on the proposed administrative property rationalisation that was outlined in the report submitted to Cabinet on 24 October 2013 and confirm the direction of travel on disposal and re-development of buildings and relocation of staff prior to final financial details being finalised for the capital programme update in February 2014.

2. Recommendation(s) 2.1 That Cabinet note the results of the consultation.

2.2That Cabinet confirms the intention, as outlined in the report to Cabinet on 24 October 2013, to dispose of buildings, consolidate staff into fewer buildings and agrees that work can continue to plan for the refurbishment of the buildings that are to be retained.

2.3That Cabinet agrees that colocation of partners, where value for money can be demonstrated, is an objective of the property rationalisation programme.

2.4That Cabinet agree the establishment of a steering group of officers and Cabinet Members to provide guidance and direction to the property rationalisation programme.

3. Options 3.1 Option 1 Remain in current buildings. Remaining in the current buildings would not allow the savings noted in this paper to be achieved and would not take up the Report Page 1 opportunity of further savings and service improvements that are expected from bringing teams together in the same building. 3.2 Option 2 Chose only the buildings originally considered under the original plan for Central Business District. This option would not allow us to consider the customer service and other projects which are so closely linked to property rationalisation and the need for maximising savings 3.3 Option 3 Continue with planning to dispose of the buildings as outlined in the October cabinet report consolidating staff into 3 main universal hubs, 3 other hubs and other buildings as previously noted. This is still the preferred option as it provides the most optimum solution and is supported by the results of the consultation.

Reason for Decision - how the proposal supports the Mandate for Change  Make Stoke-on-Trent the place to bring business  Support and develop existing business  Work with people to promote independence and healthy lives X  Make Stoke-on-Trent a great city to live in x  An effective and confident council X

Other Implications to be taken into consideration: Legal

Financial Outline costs and savings were provided in the report to Cabinet on 24 October 2013. Further details are being developed to be fed into the capital programme refresh in February 2014

Human Resources As noted in the previous report to Cabinet, there will be significant changes in the way staff work with the introduction of agile working; a key requirement of success for the property rationalisation proposals. Adequate resourcing will also be needed to manage the programme and cultural change.

Equality Impact / Equality requirements will be planned into the construction Human Rights and refurbishment of the applicable buildings. considerations

Public Health None

Report Page 2 Environmental Environmental aspects will be designed into buildings where Impact appropriate. Introduction of agile working will reduce the amount of travel that staff need to undertake.

Public Services The social value act will be used within relevant building (Social Value) Act contracts to promote local procurement 2012

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
City Wide Administrative Property RationalisationReport 6 pages DownloadRead as text
PDF
Property rationalisation consultation charts (2).docxReport 3 pages Download
PDF
Staff Engagement.docReport 194 KB Copy on its way

At this meeting

Whole meeting

Who was there

18 of 20 attended
MP
Councillor Mohammed Pervez Leader of the CouncilChair, present
PS
Councillor Paul Shotton Deputy Leader of the Council, Cabinet Member for Economic DevelopmentCabinet Member, present
JB
Councillor Janine Bridges Cabinet Member for Housing, Neighbourhoods, and Community SafetyCabinet Member, present
TC
Councillor Terry Crowe Cabinet Member for Finance, Procurement and CommissioningCabinet Member, present
AD
Councillor Alan Dutton Cabinet Member for Transformation and ResourcesCabinet Member, present
GH
Councillor Gwen Hassall Cabinet Member for Social CareCabinet Member, present
AK
Councillor Adrian Knapper Cabinet Member for Health and WellbeingCabinet Member, present
SP
Councillor Shaun Pender Cabinet Member for EducationCabinet Member, present
AP
Councillor Andy Platt Cabinet Member for Green Enterprises and Clean CityCabinet Member, present
RR
Councillor Ruth Rosenau Cabinet Member for Regeneration, Planning and TransportationCabinet Member, present
JV
John van de LaarschotOfficer, present
EB
Elayne BatesOfficer, present

All 20 on the meeting page

On this subject at Stoke-on-Trent

Search all
  1. City Wide Administrative Property RationalisationThis decision
  2. Proposed City Wide Special Educational Needs and Disability (SEND) Provision PlanAgreed
  3. City Wide Administrative Property RationalisationAgreed
  4. Citywide Services Fees and Charges 2008/09 (Forward Plan Item 65/01 CM)Approved
  5. City Wide Highway Monitoring and Management (Forward Plan 64/01 RH)Approved

More from Stoke-on-Trent Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Extension to funding agreement between Stoke-on-Trent City Council and Thrive at Five (Notice of Decisions Reference: 2482)Agreed ( i ) - Approval is granted to extend the funding agreement between Stoke-on-Trent City Council and Thrive at ... Agreed Open
3 Nov 2026 Soft Block Fostering Options (Notice of Decisions Reference: 2468)Agreed ( i ) - That approval is granted to undertake a competitive procurement exercise for a soft block fostering co... Agreed Open
3 Nov 2026 Youth Justice Strategic Plan (Notice of Decisions Reference: 2470)Agreed - That Cabinet approves the Youth Justice Plan 2026/27 and recommends its adoption by the City Council. N.B. T... Agreed Open
3 Nov 2026 Reviewing powers for reducing anti-social behaviour including requiring the removal of facing coverings where necessary and appropriate (Notice of Decisions Reference: 2477)Agreed ( i ) – That Cabinet note the current Public Spaces Protection Orders (PSPOs) operating within Hanley and Long... Agreed Open
3 Nov 2026 Housing Revenue Account (HRA) Rent Setting Report 2027/28 (Notice of Decisions Reference: 2457)Agreed - That Cabinet recommends to City Council that, as part of the budget setting processes approval is given to: ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies