That Cabinet agree to the timetable for the production of the Joint Local Plan which was appended to the Cabinet report. 2. That Cabinet agree to the creation of a Joint Advisory Group to support the delivery of the Joint Local Plan and that in the interests of expediency the determination of the membership and terms of reference for the Joint Advisory Group be delegated to the Director of City Renewal (Place) in consultation with the Cabinet Member for Regeneration, Planning and Transportation. 3. That Cabinet agree to the production of a Joint Statement of Community Involvement with Newcastle-under-Lyme Borough Council.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Date 27th March 2014 Report of Director of City Renewal (Place) Contact officer(s) Joanne Tyzzer, Assistant Director (Regeneration, Planning and Development) Cabinet Member Councillor Ruth Rosenau : Cabinet Member for Regeneration, Planning, and Transportation Type of Decision Policy Framework Wards Affected No Ward Implications
1. Purpose of Report 1.1 The purpose of the report is:- • To set out a proposed timetable for the production of a joint Local Plan in partnership with Newcastle-under-Lyme Borough Council; • To update Cabinet on the formal stance of Newcastle-under-Lyme Borough Council on this matter; and • To identify the establishment of a Joint Advisory Group to support the preparation of the Joint Local Plan.
2. Recommendation(s) 2.1 That Cabinet agree to the timetable for the production of the Joint Local Plan which is appended to this report.
2.2That Cabinet agree to the creation of a Joint Advisory Group to support the delivery of the Joint Local Plan and that in the interests of expediency the determination of the membership and terms of reference for the Joint Advisory Group be delegated to the Director of City Renewal (Place) in consultation with the Cabinet Member for Regeneration, Planning and Transportation
2.3That Cabinet agree to the production of a Joint Statement of Community Involvement with Newcastle-under-Lyme Borough Council.
Report Page 1 3. Options Considered 3.1 On 19th December 2013, the Cabinet resolved to prepare a joint Local Plan with Newcastle-under-Lyme Borough Council and that officers at both authorities work together to reach agreement on a timetable for its preparation.
3.2There are no set options as the production of a plan making programme or timetable is a statutory requirement which has to be published on the council’s website once agreed and kept up to date.
3.3A number of issues have been factored into the timetabling process to ensure it is robust and can help to deliver a sound plan at examination. These issues include: • statutory and best practice planning requirements; • governance arrangements at both council’s; • early and meaningful consultation throughout the process; • the amount of evidence base required.
3.4It is important to ensure that the consultation undertaken as part of the Local Plan is done to an appropriate standard to enable the plan, as far as possible, to reflect a collective vision for the sustainable development of the area.
3.5The length of time the plan takes to produce is also relevant to its examination of soundness. Given there is a large amount of evidence based assessment required to underpin the plan it is important that this does not become out of date by the time the plan gets to examination. Similarly the process also has a bearing on investor confidence and public perception.
3.6As set out within the report the timetable would provide the framework for the preparation of the Local Plan but would not preclude additional stages of public consultation if they are required and allows adequate time for the democratic process to be followed. The programme deliberately takes account of optimum points in the decision making cycle to engage the public at key stages in the preparation of the Local Plan.
3.7The production of a joint Statement of Community Involvement has also been included. This is a statutory function which is required to ensure the Plan is found sound and to ensure early and meaningful public engagement.
3.8The suggested timetable reflects the most expedient and deliverable process and therefore represents the best strategic fit in balancing the issues involved. The timetable has been agreed with officers at Newcastle-under-Lyme Borough Council and has been recently approved by their Cabinet at a meeting on 5th March 2014.
Reason for Decision - how the proposal supports the Mandate for Change Make Stoke-on-Trent the place to bring business X Support and develop existing business X
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.