Resolved
That the Highways Section is authorised to procure the Highways Term Contractor to deliver the construction of three new playing pitches at Abbey Lane, Abbey Hulton , as approved by the planning approval No.55962.
Cabinet approved this item on Thursday 27 March 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Highways Section is authorised to procure the Highways Term Contractor to deliver the construction of three new playing pitches at Abbey Lane, Abbey Hulton , as approved by the planning approval No.55962.
Open
Cabinet Provision of new Playing Pitches at Abbey Lane, Abbey Hulton
Date 27th March 2014 Report of Director of City Renewal (Place) Contact officer(s) Joanne Tyzzer, Assistant Director (Regeneration, Planning and Development) Julie Jeffries, Programme Manager Cabinet Member Councillor Ruth Rosenau Cabinet Member for Regeneration Type of Decision Key Decision (Notice of Decisions Ref: 482) Wards Affected Abbey Hulton & Townsend
1. Purpose of Report 1.1 This report seeks authority for the Highways Section to deliver the scheme, through the Highways Term Contractor, to construct the three new playing pitches at Abbey Lane, Abbey Hulton as detailed in the full planning approval No.55962.
1.2The pitches are required to be delivered to unlock land to allow the PFI5 project to progress.
2. Recommendation(s) 2.1 That the Highways Section is authorised to procure the Highways Term Contractor to deliver the construction of three new playing pitches at Abbey Lane, Abbey Hulton, as approved by the planning approval No.55962.
3. Options Considered 3.1 The Highways and Transportation Divisions Term Contractor have been procured through the OJEU process. The Term Contractor for Minor Works is awarded to GallifordTry and they will be undertaking the work as the Term Contractor. The Term Contractors’ Sub Contractor is TurfDry who specialise in constructing sports pitches, therefore the pitches will be constructed to the correct standards. This delivery option was also chosen to ensure that timescales are met and there are no implications on the PFI programme.
Report Page 1 Reason for Decision - how the proposal supports the Mandate for Change Make Stoke-on-Trent the place to bring business Support and develop existing business Work with people to promote independence and healthy lives X Make Stoke-on-Trent a great city to live in X An effective and confident council X
Other Implications to be taken into consideration: Legal Formal arrangements made by Highways Team with the Term Contractor.
Financial Housing Capital Programme 2013/14 2014/15 Total
£ £ £
Works 5,000 491,320 496,320 Including 7.5% contingencies 0 37,223 37,223
Total Expenditure 5,000 528,543 533,543
Approved Budget 550,000
Balance (16,457)
Notes: 1. The cost estimate is based on GallifordTry Term Contractor Rates 2. Based on current rates. Rates subject to annual increase if Term Contractor instructed after March 2014.
As can be seen from the above table the capital cost of the proposal is £533,543 as against an approved budget of £550,000. The variance will provide a budget saving.
Revenue 2013/14 2014/15 Total
£ £ £
Highways Fees 19,535 20,465 40,000 Trees and Topographical survey 3,918 0 3,918 Ecology Survey 528 0 528 URS Noise Survey 3,830 0 3,830
Report Page 2 SOTCC Planning Fees 1,690 0 1,690 Rights of Way 0 12,000 12,000 Coal Authority Report 198 0 198 Flood Risk Assessment 1,450 0 1,450 Archaeological Survey 270 0 270 Public Open Space Advert 365 0 365
Total Expenditure 31,784 32,4650 64,249
Approved Budget 31,784 32,465 64,249
Balance 0 0 0
As can be seen from the above table the Revenue cost of the proposal is £64,249 and this will be met from the PFI revenue budget.
The intention is to lease the site to a third party who will then be responsible for maintaining the pitches. If this does not happen, the City Council will have to cover the cost of maintaining the pitches from existing budget allocations.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Provision of new Playing Pitches at Abbey Lane, Abbey Hulton (Notice of Decisions Ref: 482)Decisions | 6 pages | DownloadRead as text |
Follow Cabinet at Stoke-on-Trent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Nov 2026 | Extension to funding agreement between Stoke-on-Trent City Council and Thrive at Five (Notice of Decisions Reference: 2482)Agreed ( i ) - Approval is granted to extend the funding agreement between Stoke-on-Trent City Council and Thrive at ... | Agreed | Open |
| 3 Nov 2026 | Soft Block Fostering Options (Notice of Decisions Reference: 2468)Agreed ( i ) - That approval is granted to undertake a competitive procurement exercise for a soft block fostering co... | Agreed | Open |
| 3 Nov 2026 | Youth Justice Strategic Plan (Notice of Decisions Reference: 2470)Agreed - That Cabinet approves the Youth Justice Plan 2026/27 and recommends its adoption by the City Council. N.B. T... | Agreed | Open |
| 3 Nov 2026 | Reviewing powers for reducing anti-social behaviour including requiring the removal of facing coverings where necessary and appropriate (Notice of Decisions Reference: 2477)Agreed ( i ) – That Cabinet note the current Public Spaces Protection Orders (PSPOs) operating within Hanley and Long... | Agreed | Open |
| 3 Nov 2026 | Housing Revenue Account (HRA) Rent Setting Report 2027/28 (Notice of Decisions Reference: 2457)Agreed - That Cabinet recommends to City Council that, as part of the budget setting processes approval is given to: ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.