That Cabinet approve the proposed approach to delivery of the Phase 3 of the City Centre Public Realm Improvement Scheme through a re-tender exercise. 2. That Cabinet award delegated authority to the Director of City Renewal (Place) in consultation with the relevant Cabinet member, to accept tenders for the revised scheme.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Open CABINET City Centre Public Realm Phase 3 - Revision To Scheme and Re-Tender
Date: 24 April 2014 Report to: Director of City Renewal Contact officer(s): Joanne Tyzzer, Assistant Director (Regeneration, Planning and Development) Kevin Bell, Strategic Manager (Regeneration & Development) Mark Collins, Development Programme Manager Martin Lewis, Project Manager Cabinet Member Councillor Ruth Rosenau: Cabinet Member for Regeneration Planning and Transportation Type of Decision Non Key Decision (Notice Issued) Wards Affected: Etruria and Hanley
1. Purpose of the Report: 1.1 The report outlines the proposed revisions to Phase 3 of the City Centre Public Realm Improvement Scheme and outlines the proposed approach to deliver the scheme through a re-tender exercise.
2. Recommendation(s) 2.1 To approve the proposed approach to delivery of the Phase 3 of the City Centre Public Realm Improvement Scheme through a re-tender exercise.
2.2To award delegated authority to the Director of City Renewal (Place) in consultation with the relevant Cabinet member, to accept tenders for the revised scheme.
3. Options Considered 3.1 Phase 3 of the City Centre Public Realm Improvement Scheme was previously tendered through the Midland Highway Alliance Framework MSF/1 via a mini competition. 3.2 The City Council has considered various options to deliver the scheme both within the allocated project budget / timeframe and in a compliant manner to external funding parties in order to minimise risk to the council and its partners. 3.3 In order to ensure that the project is delivered within allocated budget, and as
Report Page 1 a result of the Midland Highway Alliance Framework now expiring, the city council will now re-tender the works through an European Regional Development Fund (ERDF) compliant tender process.
Reason for Decision - how the proposal supports the Mandate for Change Make Stoke-on-Trent the place to bring business x Support and develop existing business x Work with people to promote independence and healthy lives Make Stoke-on-Trent a great city to live in x An effective and confident council x
Other Implications to be taken into consideration: Legal: A procurement process will be conducted in accordance with EU procurement law and the City Council’s Contract Procedure rules. In addition part of the works are financed by the European Regional Development Fund (ERDF) Programme 2007 - 13 which prescribes procurement guidelines.
Financial: Phase 3 of the Public Realm Improvements Programme has an approved budget of £5.76m within an overall programme of £11.55m that benefits from £3.8m of ERDF capital funding. This was approved by Cabinet on 19th December 2013. The proposed cost breakdown and approved funding profile is set out below:
TOTAL 11.55 Financed by: ERDF 3.80 Council 7.75 Total 11.55 financing
The overall project budget for Phase 3 of the programme is £5.76m. However, pre-tender estimates are yet to be developed for the reduced scope of the scheme and therefore further analysis of the budget is not available at this time. The expenditure will be financed as set out in the table below and
Report Page 2 will need to be contained within the approved capital budget of £5.76m. The estimated value of ERDF grant is subject to confirmation of the final scope to be tendered and there is a risk that the grant may be reduced as a result of a reduced scope, which would therefore reduce the total of the approved capital budget.
£m Total Expenditure 5.76 Financed by: ERDF Grant 1.65 City Council resource 4.11 Total Financing 5.76
Existing revenue budgets and staff resources will continue to be utilised to develop the revised proposal.
The procurement of the revised scheme will need to:
• Be fully compliant with ERDF National Procurement Requirements ERDF-GN-1-004 to avoid risks of subsequent grant claw-back.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.