That Cabinet notes progress to date. 2. That Cabinet approves moving beyond Gateway 00 (scoping work and preparation of tenders) to Gateway 01 to appoint consultants to progress the work streams packages up to the outcome of the initial project workshop. 3. That Cabinet endorses the subsequent gateways as identified herein and approves the progression of the project through these gateways in anticipation of the need for earlier work stream outcomes. This approval is subject to there being appropriate project gateway control and reporting to the HS2 Boards and no significant changes to the Programme or significant increase in the rate of expenditure. In the event of significant changes to the anticipated Programme, Cabinet approval will be sought before proceeding through the subsequent Gateway. This is an urgent decision and therefore, not subject to call-in.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Cabinet High Speed Rail – HS2 Business Case Gateway
Date: 24th April 2014 Report to: Director of City Renewal Contact officer(s): Pete Price, Assistant Director (Place Management) Stephen Voce, Interim Commercial Manager Cabinet Member Councillor Ruth Rosenau: Cabinet Member for Regeneration, Planning and Transportation Type of Decision Key Decision (Urgent Decision) Wards Affected: No Ward Implications
1. Purpose of the Report: 1.1 To provide an update as to progress of the procurement activity within the HS2 project and to seek approval to continue to beyond the first gateway to appoint the work stream consultants to progress the technical appraisal and other associated activity.
1.2The report to City Council : HS2 Business Case Development – 20th March 2014 established that in developing the Stoke route case, expenditure would be controlled via a series of gateway approvals. Each gateway will be subject to an appropriate level of appraisal and scrutiny but due to Government’s emerging timescale, it has been necessary to accelerate the gateway approval regime.
1.3This report seeks Cabinet endorsement of this appraisal and gateway approval and is therefore requested as an urgent item. Stakeholder engagement to date has informed the view that there will be a reduced period during which the DfT will properly assess alternative proposals. This urgent report has been produced in anticipation of this truncation of the decision timeline, and to endorse an accelerated approach by the Council to ensure the Stoke case is sufficiently developed.
2. Recommendation(s) 2.1 That Cabinet notes progress to date.
2.2That Cabinet approves moving beyond Gateway 00 (scoping work and preparation of tenders) to Gateway 01 to appoint consultants to progress the work streams packages up to the outcome of the initial project workshop.
Report Page 1 2.3 That Cabinet endorses the subsequent gateways as identified herein and approves the progression of the project through these gateways in anticipation of the need for earlier work stream outcomes. This approval is subject to there being appropriate project gateway control and reporting to the HS2 Boards and no significant changes to the Programme or significant increase in the rate of expenditure. In the event of significant changes to the anticipated Programme, Cabinet approval will be sought before proceeding through the subsequent Gateway.
3. Options Considered 3.1 Do Nothing:
I.e. Withhold permission to progress through gateway one
this will prevent the entering into contract with the work stream consultants, rendering the Council unable to develop its technical business case and to respond to query’s from DfT in relation to the Council’s submission to date.
3.2I.e. Withhold approval of all subsequent gateways
this will severely limit the Council’s ability to progress its business case to Government in sufficient time.
3.3Progress as outlined herein:
This will allow the project to enter into agreements with those tendering consultants who have been evaluated as the most advantageous. It will also enable the Council to continue to develop and demonstrate a compelling and robust business case to align the HS2 route through Stoke-on-Trent in time for this to be understood and taken up by key stakeholders.
Reason for Decision - how the proposal supports the Mandate for Change Make Stoke-on-Trent the place to bring business Support and develop existing business Work with people to promote independence and healthy lives Make Stoke-on-Trent a great city to live in An effective and confident council
Other Implications to be taken into consideration: Legal: Entering into contract with the work stream consultants will establish a number of binding agreements. The proposed terms of appointment would enable the Council to terminate at subsequent gateway’s however thereby helping to manage expenditure.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.