That the General Fund provisional (pre-audit) outturn of £64.573m ( an underspend of £2.230m) for 2013/14 be noted. 2. That the Housing Revenue Account provisional (pre-audit) outturn overspend of £0.408m against the budget be noted. 3. That the capital investment provisional (pre-audit) outturn for 2013/14 is £99.079m, be noted. 4. That new earmarked reserves as set out at Appendix Ai of the report submitted to Cabinet are agreed. 5. That Directors and portfolio holders continue to implement action plans where pressures exist to reduce the impact of any overspends during 2014/15 and progress savings in early development for 2015/16. 6. That Directors continue to review the use of external support.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Provisional Outturn 2013/14 Date 29 May 2014 Report of Interim Assistant Director - Financial Services Contact officer(s) Peter Lewis Interim Assistant Director - Financial Services Kerry Cartlidge Finance and Commercial Manager Cabinet Member Cllr Terry Crowe Finance, Procurement and Commissioning Type of Decision Information only Wards Affected No Ward Implications
1. Purpose of Report 1.1 To summarise the financial position of the General Fund, Capital Investment Programme and Housing Revenue as at the end of March 20141. 1.2 The 2013/14 provisional outturn for the General Fund is an underspend of £2.230m. Following the annual challenge of the balance sheet, it has been possible to release a number of earmarked reserves (£2.010m); after setting aside the amount agreed to underpin the 2014/15 budget (£3.683m), this will result in an increase to the general reserve of £0.557m. 1.3 The yearend Capital Investment Programme provisional outturn for 2013/14 is £99.079m representing an underspend of £19.870m variance against the MTFS forecast in February. The majority of the underspend will be profiled into future years. 1.4 At the end of the financial year 2013/14 the HRA is showing an overspend of £0.408m against the original budget, which will be set against the Housing general reserve.
1 The provisional outturn figures are prepared early in May using the best and most complete information available to the city Council at that time. During the period from the provisional outturn to the signing of the accounts by the s151 officer (end of June) further information may be received that may alter any estimates applied; where a change is considered material an amendment to the outturn will be made and reported in the Statement of Accounts.
Report Page 1 2. Recommendations 2.1 That the General Fund provisional (pre-audit) outturn of £64.573m (an underspend of £2.230m) for 2013/14 be noted. 2.2 That the Housing Revenue Account provisional (pre-audit) outturn overspend of £0.408m against the budget be noted. 2.3 That the capital investment provisional (pre-audit) outturn for 2013/14 is £99.079m, be noted. 2.4 That new earmarked reserves as set out at Appendix Ai are agreed. 2.5 That Directors and portfolio holders continue to implement action plans where pressures exist to reduce the impact of any overspends during 2014/15 and progress savings in early development for 2015/16. 2.6 That Directors continue to review the use of external support.
3. Options Considered 3.1 There are no options associated with this report.
Reason for Decision - how the proposal supports the Mandate for Change Make Stoke-on-Trent the place to bring business Support and develop existing business Work with people to promote independence and healthy lives Make Stoke-on-Trent a great city to live in An effective and confident council
Other Implications to be taken into consideration: Legal None
Financial The general fund has a gross turnover of circa £1.3 billion (£700m expenditure and £600m income). The provisional outturn for 2013/14 is an underspend of £2.230m (0.2% turnover). After taking account of commitments to support 2015/16 budget the general reserve will increase by £0.557m (this will stand at circa £8.5m as at 1 April 2014).
Human Resources None
Equality Impact / None Human Rights considerations
Public Health None
Report Page 2 Environmental None Impact
Public Services None (Social Value) Act 2012
Impact on Customers/Partners Services are being delivered in accordance with the MTFS agreed in February 2013.
Background papers and information sources Capital Programme Update 2013/14–2015/16 – City Council 17 October 2013 Budget Setting Report 2013/14 – City Council 28 February 2013 HRA Rent Setting Report 2013/14 – City Council 24 January 2013
Enclosures Appendix Ai New Reserves Appendix Aii Reserves Summary Appendix B Capital Investment Programme Provisional Outturn 2013/2014 Appendix C HRA Provisional Outturn 2013/14
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.