Coal Bed Methane Project – Decision Report

Approved Executive 1 paper

Cabinet approved this item on Thursday 29 May 2014. Below is the council's own wording, with the papers it was decided on.

Item501

Resolved

That Cabinet notes that in its current form the CBM project has failed to pass a key gateway criteria . 2. That Cabinet approves Option 1 (as below) - that the project should not progress further unless and until market conditions improve and/or technical conditions are identified that will enable the project to become commercially viable.
Word for word from the decision Stoke-on-Trent published for this meeting. Source: moderngov.stoke.gov.uk

Follow this further

Built from Stoke-on-Trent's papers

What the report saysPro

Report to Cabinet, 11 pages

Open

Cabinet Coal Bed Methane Project – Decision Report

Date 29th May 2014 Report of Director of City Renewal (Place) Contact officer(s) Trevor Whittaker, Assistant Director (Green Enterprises) Andrew Briggs, Client Manager for Energy (Green Enterprises) Cabinet Member Councillor Andy Platt: Cabinet Member for Green Enterprises Type of Decision Non Key Decision Wards Affected No Ward Implications

1. Purpose of Report 1.1 The purpose of this report is to advise Cabinet of the status of the Coal Bed Methane (CBM) project and to recommend that the project does not progress further for the foreseeable future, as it has been determined that it failed to pass a key gateway because: • A procurement exercise has determined that there is currently no private sector interest to invest in the project as a development partner with the Council. • Using specialist advice we have determined that the project is currently commercially unviable due to the estimated current costs of extraction and distribution.

2. Recommendation(s) 2.1 That Cabinet notes that in its current form the CBM project has failed to pass a key gateway criteria.

2.2That Cabinet approves Option 1 (as below) - that the project should not progress further unless and until market conditions improve and/or technical conditions are identified that will enable the project to become commercially viable.

3. Options Considered Two key events have impacted the project: • Firstly, that no prospective development companies have come forward through the Council’s competitive procurement process for a suitable

Report Page 1 Version 10: 20/05/14 joint venture partner to bid for the Petroleum Extraction and Development Licence (PEDL) following significant changes in the market conditions surrounding unconventional hydrocarbons, and:

• Secondly that technical and commercial assessment of our Reference Project, using specialist technical advice based on the current project definition and constraints around extraction techniques to be utilised, as a consequence shown the project to be less viable than the lowest net cash generation position predicted in the paper of 5th September 2013. A key factor is that the gas recovery rate estimated in September 2013 was based on data from the high level studies and advice, (referred to as High Recovery rate). In March 2014, our detailed technical appraisal of local reserves has arrived at a lower estimated recovery rate (referred to as a Low Recovery rate) over the predicted life of the well with a 90% chance of recovery at this rate. This is based on the technical/exploitation model developed and with no fracking or other enhancement of gas recovery. This developed technical assessment has led to consideration of the options below.

3.1Option 1: To suspend the project until such time as market conditions and/or technical conditions are identified that enable the project to become commercially viable and enable a private sector development partner to be secured to work with the City Council in making a full application for the PEDL.

3.2Option 2: To proceed without a development partner which would require the City Council to submit a “drill or drop” application for the unallocated Stoke PEDL blocks. This would not be attractive to Department of the Environment and Climate Change (DECC) compared to a firm commitment to drill, as required under a full application, but in any case would incur the Council in significant expenditure and then be subject to reputational risk if the Council could not subsequently secure a development partner.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Coal Bed Methane Project: Decision ReportDecisions 11 pages DownloadRead as text

More from Stoke-on-Trent Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Extension to funding agreement between Stoke-on-Trent City Council and Thrive at Five (Notice of Decisions Reference: 2482)Agreed ( i ) - Approval is granted to extend the funding agreement between Stoke-on-Trent City Council and Thrive at ... Agreed Open
3 Nov 2026 Soft Block Fostering Options (Notice of Decisions Reference: 2468)Agreed ( i ) - That approval is granted to undertake a competitive procurement exercise for a soft block fostering co... Agreed Open
3 Nov 2026 Youth Justice Strategic Plan (Notice of Decisions Reference: 2470)Agreed - That Cabinet approves the Youth Justice Plan 2026/27 and recommends its adoption by the City Council. N.B. T... Agreed Open
3 Nov 2026 Reviewing powers for reducing anti-social behaviour including requiring the removal of facing coverings where necessary and appropriate (Notice of Decisions Reference: 2477)Agreed ( i ) – That Cabinet note the current Public Spaces Protection Orders (PSPOs) operating within Hanley and Long... Agreed Open
3 Nov 2026 Housing Revenue Account (HRA) Rent Setting Report 2027/28 (Notice of Decisions Reference: 2457)Agreed - That Cabinet recommends to City Council that, as part of the budget setting processes approval is given to: ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies