Agreed ( i ) - That Cabinet approve the delivery of an Etruria Valley Full Fibre Network. Agreed (ii) - That Cabinet approve the procurement of works and services associated with the installation of a full fibre network. Agreed (iii) - That Cabinet approve the commitment of £570,000 from the current capital programme allocation for Ceramic Valley in the MTFS in order to deliver the Etruria Valley Full Fibre Network. Agreed (iv) - That subject to approval of 2.1, 2.2 and 2.3, Cabinet agree to grant delegated authority to the Director of Place, Growth and Prosperity in consultation with the Cabinet Members for Regeneration, Transport & Heritage, Cabinet Member for Finance & Partnerships and Education & Economy to enter into partnership agreements and land agreements as necessary to deliver the project and any related works.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Cabinet Member for Regeneration, Transport and Heritage Report of Cabinet Member for Finance and Partnerships Cabinet Member for Education and Economy Contact officer(s) Steve Lovatt – Enterprise Zone Programme Manager Type of Decision Executive Key Decision - Notice of Decisions Ref: 783 Wards Affected Etruria and Hanley
Stronger Together Priorities and how they are applicable: Support our businesses to thrive, delivering investment in our towns and communities The differentiator that the City would have over and above other competitor-urban centres would include: a gigabit enabled Enterprise Zone site with broadband speeds that are unavailable in most other cities access to gigabit services (1000mbps or above) more competitive pricing for broadband services capability to attract digital technology and financial technology businesses a development site that is “future proofed” in terms of broadband Support our residents to fulfil their potential The benefits to our residents would be: access to gigabit services (1000mbps or above) lower price services through a more competitive market concessionary services to both council and social housing residents A commercial council, well governed and fit for purpose, driving efficiency in everything we do From a commercial perspective: The City Council will own the fibre and will receive a guaranteed revenue income from that ownership A full fibre enabled enterprise zone site is more commercially attractive and will support the achievement of our Enterprise Zone objectives
1. Reason and Purpose of Report:
1.1The report seeks Cabinet approval to finance and deliver a Full Fibre Broadband project on the Etruria Valley site within the Ceramic Valley Enterprise Zone. The proposals would enable a City Council owned independent broadband fibre network, funded by the City Council and leased out to private sector telecoms operators.
Page 1 Version 5 : 17/05/18 2. Recommendation(s):
2.1That Cabinet approve the delivery of an Etruria Valley Full Fibre Network.
2.2That Cabinet approve the procurement of works and services associated with the installation of a full fibre network.
2.3That Cabinet approve the commitment of £570,000 from the current capital programme allocation for Ceramic Valley in the MTFS in order to deliver the Etruria Valley Full Fibre Network.
2.4That subject to approval of 2.1, 2.2 and 2.3, Cabinet agree to grant delegated authority to the Director of Place, Growth and Prosperity in consultation with the Cabinet Members for Regeneration, Transport & Heritage, Cabinet Member for Finance & Partnerships and Education & Economy to enter into partnership agreements and land agreements as necessary to deliver the project and any related works.
3. Summary of Main Points: 3.1 A key requirement for the sites within the Ceramic Valley Enterprise Zone is ultrafast broadband connectivity. The Etruria Valley site does not currently have access to ultrafast broadband (100mbps or above) and there are nearby residential areas that do not have access to superfast broadband (24mbps or above). An Etruria Valley gigabit fibre network owned by the City Council enables significant opportunities with regard to our competitiveness.
3.2A development site that is “future proofed” in terms of broadband is more commercially attractive and will support the achievement of our Enterprise Zone objectives. A full fibre enabled enterprise zone site will provide access to gigabit services and is likely to attract digital technology and financial technology businesses with higher value jobs.
3.3Our intention is to run fibre through the section of the Stoke-on-Trent Private Optical Network (SPON) in the Etruria Valley area, connecting fibre to premise. This will provide the capacity for fibre to premise connection for 5,000 homes and businesses.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.