Cabinet, Tuesday 21 April 2026 at 1.00pm

Fire Safety Improvements to High Rise Residential Blocks (Notice of Decisions Reference: 2396)

Agreed Executive 1 paper

AI summaryCabinet agreed fire safety improvements to seven high-rise council blocks, accepting £4.6725M initial Cladding Safety Scheme funding from Homes England to assess and remediate cladding fire risks.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedRetrospective delegation to accept grant and amend HRA capital programme
Money£4.6725M initial grant£667,500 Pre-Tender Support per building, seven blocks
What happens nextSubmit full funding applicationWithin 5 months of signing the Pre-Tender Support Agreement
Who it affectsSeven high-rise residential blocksIn Blurton, Burslem and Hanley wards

What was decided

Cabinet noted the submission of Cladding Safety Scheme funding applications to Homes England on 28 November 2025 covering seven council-owned high-rise blocks. Report 1.0

Cabinet granted retrospective delegated authority to the S151 Officer, in consultation with the Corporate Director of Housing, Regeneration and Operations and the Cabinet Member, to accept the grant terms and sign the funding agreement. Report 1.0

Subject to funding being received, Cabinet delegated authority to the S151 Officer to amend the HRA capital investment programme and take all steps needed to fulfil the grant agreement. Report 1.0, 8.1

Why

The Council has a legal duty to remediate fire safety risks in its high-risk residential buildings, and accessing CSS funding allows all works to be expedited and managed under one programme rather than phased. Report 6.0, 7.1, 8.2

Seven buildings were appraised as having a 'medium-intolerable' risk from external wall finishing, with no sprinkler coverage, and are eligible for CSS funding with no requirement to match fund.

Council-owned buildings over 18 metres and seven storeys are categorised as 'higher risk' under the Building Safety Act 2022 and are subject to the Regulatory Reform (Fire Safety) Order 2005. Report 8.2

What happens next

Sign the Pre-Tender Support grant agreement, then submit a costed application for full funding within 5 months, with evidence of qualifying expenditure submitted monthly to Homes England.

Cost and evaluate the two FRAEW-recommended remediation options: Option A full sprinkler systems or Option B removal of polycarbonate stairwell covering, and develop a procurement strategy.

Engage specialist consultancy support, either through an existing professional services contract or another professional framework, to prepare the full funding application within the required timeframe.

The money

  • £4.6725M Initial Pre-Tender Support grant offer received in February 2026 across seven buildings
  • £667,500 Pre-Tender Support grant per building
  • £4.2M Existing HRA capital investment programme allocation for sprinkler systems over 2026/27 to 2028/29 Report 8.1
  • over £1 billion Government investment announced on 11 June 2025 to accelerate social housing remediation

Options considered

  • Chosen: Apply to the Cladding Safety Scheme for grant funding. Enables all works to be expedited and managed under one programme, freeing capital for other priorities Report 7.1
  • Rejected: Fully fund the remediation works from the HRA capital programme. Would require phased delivery over several years due to budget pressures Report 7.1
  • Rejected: Option A: install full sprinkler systems. Under evaluation alongside Option B as a FRAEW-recommended remediation option
  • Rejected: Option B: remove polycarbonate stairwell covering. Under evaluation alongside Option A as a FRAEW-recommended remediation option

Implications

  • Financial: Successful grant award would reduce existing HRA capital commitments, allowing the £4.2M to be redistributed to other cost centres; unsuccessful outcome leaves the sprinkler project viable within existing budget. Report 8.1
  • Legal: Council must comply with the Regulatory Reform (Fire Safety) Order 2005, the Building Safety Act 2022, the Subsidy Control Act 2022 and the Funding Agreement terms, including planning and building regulation consents. Report 8.2
  • Legal: Leaseholders will not be recharged for funded works under Schedule 8 of the Building Safety Act. Report 8.2
  • Risk: Key risk is the 5-month deadline to submit a costed full funding application, dependent on engaging specialist consultancy support; delays must be agreed with Homes England to avoid withdrawal of Pre-Tender Support.
  • Equalities: No Equality Impact Assessment required and no impact on social inequalities identified. Report 9.2, 9.3
  • Climate: No environmental impact identified from the proposals. Report 9.4
  • Staffing: No human resources implications identified. Report 9.1

Who and where

  • Residents and leaseholders in seven high-rise residential blocks in Blurton, Burslem and Hanley Report P24
  • Social housing tenants in the Council's circa 17,500 home stock
  • Wards: Blurton, Burslem Park, Etruria and Hanley Report P24

Timeline

  • 2019: Phased sprinkler installation programme commenced across all 16 high-rise buildings
  • July 2023: Homes England Cladding Safety Scheme formally launched
  • 11 June 2025: Government announced over £1 billion of new investment to accelerate social housing remediation
  • 28 November 2025: Council submitted CSS funding applications in respect of eligible high-rise buildings
  • February 2026: Council received initial Pre-Tender Support grant offer of £4.6725M
  • 21 April 2026: Cabinet decision to grant delegated authority Report P2
  • Within 5 months of signing the Pre-Tender Support Agreement: Deadline to submit full funding application to Homes England
  • 2026/27 to 2028/29: Three-year HRA capital investment programme period for sprinkler works

Plain English for the jargon

  • Cladding Safety Scheme (CSS): Government-funded programme administered by Homes England to meet the cost of addressing life safety fire risks associated with cladding on residential buildings over 11 metres.
  • FRAEW (PAS 9980:2022): Fire Risk Appraisal of External Walls, a mandatory assessment by a Homes England approved panel assessor for buildings over 11 metres.
  • Pre-Tender Support (PTS): An advance payment of 15% of estimated works costs under CSS, forming part of the total grant awarded, used to develop the works package and procurement strategy.
  • HRA: Housing Revenue Account, the ring-fenced account that funds the Council's own housing stock.
  • S151 Officer: The Council's statutory chief finance officer, responsible for the proper administration of financial affairs.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item186

Resolved

Agreed ( i ) - That Cabinet notes the submission of Cladding Safety Scheme funding applications to Homes England, the detail of which was outlined in part 3 of the report submitted. Agreed (ii) - That Cabinet grants approval to delegate authority retrospectively to the Corporate Director of Resources (S151 Officer), in consultation with the Corporate Director of Housing, Regeneration and Operations and Cabinet Member for Housing, Planning, Improvement and Governance to accept the terms and sign the grant funding agreement. Agreed (iii) - That, subject to the receipt of funding, Cabinet grants delegated authority to the S151 Officer in consultation with the Corporate Director of Housing, Regeneration and Operation and the Cabinet Member for Housing, Planning, Improvement and Governance, to: · Make the necessary amendments to Council’s Housing Revenue Account (HRA) capital investment programme, and · take all necessary steps to fulfil the requirements of the grant agreement.
Word for word from the decision Stoke-on-Trent published for this meeting. Source: moderngov.stoke.gov.uk

Follow this further

Built from Stoke-on-Trent's papers

What the report saysPro

Report to Cabinet, 5 pages

Cabinet

Tuesday, 21 April 2026

Open

Fire Safety Improvements to High Rise Residential Blocks

Report of Corporate Director of Housing, Regeneration and Operations - Carol Gibbs Cabinet Member for Housing, Planning, Improvement and Governance

Purpose of Report To provide an update to Cabinet on the planned position of fire safety improvements to Housing Revenue Account (HRA) owned ‘high risk’ high-rise residential blocks, to inform Members of the outcome of applications to Homes England for funding to support improvement works via the Cladding Safety Scheme, and to seek retrospective delegated approval to accept the grant and procure the necessary works.

1.0Recommendations 1.1 That Cabinet notes the submission of Cladding Safety Scheme funding applications to Homes England, the detail of which is outlined in part 3 of this report. 1.2 That Cabinet grants approval to delegate authority retrospectively to the Corporate Director of Resources (S151 Officer), in consultation with the Corporate Director of Housing, Regeneration and Operations and Cabinet Member for Housing, Planning, Improvement and Governance to accept the terms and sign the grant funding agreement. 1.3 That, subject to the receipt of funding, Cabinet grants delegated authority to the S151 Officer in consultation with the Corporate Director of Housing, Regeneration and Operation and the Cabinet Member for Housing, Planning, Improvement and Governance, to:  Make the necessary amendments to Council’s Housing Revenue Account (HRA) capital investment programme, and  take all necessary steps to fulfil the requirements of the grant agreement.

2.0Background and Introduction 2.1 The Homes England Cladding Safety Scheme (CSS) was formally launched in July 2023. The CSS is part of the wider Building Remediation Portfolio whose objectives include ensuring that residents are safe from risks associated with unsafe cladding (and other external wall materials). 2.2 The key objective of the CSS is to ensure that any fire safety risks associated with cladding are addressed as quickly as possible to ensure that residents are safe, and feel safe, in their homes. The CSS will offer funding for buildings which meet the technical eligibility criteria and for applicants who meet the Responsible Entity criteria. This includes funding for works which leaseholders would ordinarily be obliged to pay for under the terms of their lease, but who now qualify for protection from costs associated with works to cladding. 2.3 On 11 June 2025, government announced over £1 billion of new investment to accelerate the remediation of social housing, by giving social housing providers equal access to government funding as that afforded to private building owners. This means the CSS will now fund cladding remediation on social rented homes that meet the criteria. 2.4 To be eligible for funding, the building must:  be over 11 metres high, being for residential or mixed‑use building with residential units.  be owned by the Grant Recipient.  have a Fire Risk Appraisal of External Walls (FRAEW) (PAS 9980:2022) by an assessor from the Homes England approved panel (mandatory since November 2023), which recommends work to address life safety fire risks associated with cladding and the external wall system.  Work has NOT started before 10 January 2022. 2.5 The Council made applications to the scheme on 28 November 2025 in respect of the Council-owned high-rise residential buildings potentially meeting the eligibility criteria.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Fire Safety Improvements to High Rise Residential Blocks (Notice of Decisions Reference: 2396)Decisions 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Stoke-on-Trent

Search all
  1. Fire Safety Improvements to High Rise Residential Blocks (Notice of Decisions Reference: 2396)This decision
  2. Phase 2 - Fire Safety Improvements to High Rise Residential Blocks (Notice of Decisions Reference: 2429)Agreed

More from Stoke-on-Trent Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Extension to funding agreement between Stoke-on-Trent City Council and Thrive at Five (Notice of Decisions Reference: 2482)Agreed ( i ) - Approval is granted to extend the funding agreement between Stoke-on-Trent City Council and Thrive at ... Agreed Open
3 Nov 2026 Soft Block Fostering Options (Notice of Decisions Reference: 2468)Agreed ( i ) - That approval is granted to undertake a competitive procurement exercise for a soft block fostering co... Agreed Open
3 Nov 2026 Youth Justice Strategic Plan (Notice of Decisions Reference: 2470)Agreed - That Cabinet approves the Youth Justice Plan 2026/27 and recommends its adoption by the City Council. N.B. T... Agreed Open
3 Nov 2026 Reviewing powers for reducing anti-social behaviour including requiring the removal of facing coverings where necessary and appropriate (Notice of Decisions Reference: 2477)Agreed ( i ) – That Cabinet note the current Public Spaces Protection Orders (PSPOs) operating within Hanley and Long... Agreed Open
3 Nov 2026 Housing Revenue Account (HRA) Rent Setting Report 2027/28 (Notice of Decisions Reference: 2457)Agreed - That Cabinet recommends to City Council that, as part of the budget setting processes approval is given to: ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies