Phase 2 - Fire Safety Improvements to High Rise Residential Blocks (Notice of Decisions Reference: 2429)
AgreedExecutive1 paper
AI summaryStoke-on-Trent Cabinet approves delegated authority to accept £3.3375M Homes England grant for fire safety works to five high-rise blocks, with full funding application due within five months.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedTo accept grant and procure fire safety works
Money£3.3375M pre-tender support£0.6675M each for five blocks, no match funding required
What happens nextFull funding application within 5 monthsAfter signing the Pre-Tender Support Agreement
Who it affectsFive high-rise blocks and residentsPenkhull, Southern, Dibden, Westwood and Wellington Courts
What was decided
Cabinet noted the submission of five grant funding applications to Homes England for the remaining eligible high-rise blocks. Report 1.0
Cabinet approved accepting the grant and entering the Grant Funding Agreement, delegating authority to the S151 Officer to accept future grants. Report 1.0
Delegated authority was granted to amend the HRA capital investment programme and procure contracts for professional services, subject to funding receipt. Report 1.0
Why
The Council has a legal duty to remediate fire safety risks in its high-rise residential buildings, and grant funding lets works proceed under one programme rather than phased over years. Report 6.0, 7.0
Government made over £1 billion available from 11 June 2025 so social housing providers can access equal funding to private building owners, with no requirement to match fund.
Three of the blocks (Penkhull, Southern and Dibden) already had sprinklers installed between 2021 and 2026, and Homes England will fund only the leaseholder share of those costs.
What happens next
Submit the application for full funding to deliver the recommended remediation works within 5 months of signing the Pre-Tender Support Agreement.
Engage specialist consultancy support, either via an existing professional services contract or another framework, to produce the costed application.
Submit evidence of qualifying expenditure monthly to Homes England to draw grant, and keep residents and leaseholders informed throughout.
The money
£0.6675M Pre-Tender Support grant offer for each of the five buildings
£3.3375M Total Pre-Tender Support grant for the five buildings
£1.1M Capital expenditure on already installed sprinklers across three blocks
£8.281M Major refurbishment programme for Westwood and Wellington Courts approved by Cabinet in January 2026
over £1 billion New government investment announced on 11 June 2025 for social housing remediation
Options considered
Chosen: Apply for and accept Homes England grant funding for the five blocks. Enables all works to be expedited and managed under one programme, freeing capital for other areas of need Report 7.0
Rejected: Fully fund the necessary works from the Council's own budget. Would require phasing over several years due to budget pressures
Rejected: Westwood and Wellington: Option A, install full sprinkler systems. PTS activity will evaluate which options attract funding within the existing costed scheme
Rejected: Westwood and Wellington: Option B, remediate the ground floor external wall finish. PTS activity will evaluate which options attract funding within the existing costed scheme
Implications
Financial: Any grant funding above actual expenditure cannot be committed and must be returned to Homes England, creating a financial pressure if wrongly spent.
Financial: Retrospective contribution towards the £1.1M spent on the three blocks will be redirected back into capital investment budgets.
Financial: If the project exceeds forecasted spend, robust project management is needed to mitigate additional cost.
Legal: The Council must comply with the Regulatory Reform (Fire Safety) Order 2005, the Building Safety Act 2022, the Subsidy Control Act 2022, and section 19 of the Housing and Regeneration Act 2008.
Legal: Leaseholders cannot be recharged for funded works under Schedule 8 of the Building Safety Act.
Risk: Failure to submit the full funding application within 5 months could lead Homes England to withdraw the Pre-Tender Support.
Equalities: No Equality Impact Assessment is required and the proposals do not impact on social inequalities.
Climate: The proposals will not impact on the environment.
Who and where
Residents and leaseholders of Penkhull, Southern and Dibden Courts Report P22
Residents and leaseholders of Westwood and Wellington Courts Report P22
Wards of Hanley Park, Joiner's Square and Shelton, and Hartshill Park and Stoke Report P22
Timeline
11 June 2025: Government announced over £1 billion for social housing remediation
28 November 2025: Council submitted grant funding applications for twelve high-rise buildings
January 2026: Cabinet approved the £8.281M major refurbishment programme for Westwood and Wellington Courts
April 2026: Cabinet approved acceptance of grant funding for seven other buildings (Pedley, Robinson, Arthur Cotton, Port Vale, Boundary, Brookfield and Forest Courts)
During April 2026: Council received initial Pre-Tender Support grant offer of £3.3375M for the five blocks
14 July 2026: Cabinet considered this report on the five remaining blocks Report P2, P4
Within 5 months of signing the PTS Agreement: Application for full funding must be submitted
Over the next 3 years: Capital spend for Westwood and Wellington refurbishment is already in the business plan
Plain English for the jargon
HRA: Housing Revenue Account, the ringfenced account for council housing income and spending
PTS: Pre-Tender Support, an advance of Homes England grant funding to cover costing and evaluation of remediation options
S151 Officer: The council's statutory Chief Finance Officer, responsible for proper financial administration
High-rise block: Residential building over 11 metres in height, within the scope of the Building Safety Act 2022
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item30
Resolved
Agreed ( i ) - That Cabinet notes the submission of five grant funding applications to Homes England, the detail of which is outlined in part 3 of this report. Agreed (ii) - That Cabinet notes and approves the decision to accept the grant and enter into the Grant Funding Agreement with Homes England and delegates authority to the Corporate Director of Resources (S151 Officer), in consultation with the Corporate Director of Housing, Regeneration and Operations and Cabinet Member for Safe and Resilient Communities and Housing, to accept any future grants. Agreed (iii) - That, subject to the receipt of funding, Cabinet grants delegated authority to the S151 Officer in consultation with the Corporate Director of Housing, Regeneration and Operation and the Cabinet Member for Safe and Resilient Communities and Housing, to: · Make the necessary amendments to the Council’s Housing Revenue Account (HRA) capital investment programme, and · take all necessary steps to fulfil the requirements of the grant agreement including procuring and awarding contracts via a compliant procurement process for all professional services required.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Phase 2 - Fire Safety Improvements to High Rise Residential Blocks
Report of Corporate Director of Housing, Regeneration and Operations - Carol Gibbs Cabinet Member for Safe and Resilient Communities and Housing
Purpose of Report To provide an update to Cabinet on the continued planned position of fire safety improvements to Housing Revenue Account (HRA) owned ‘high risk’ high-rise residential blocks, to inform Members of the Homes England grant funding to support improvement works and seek retrospective delegated approval to accept and enter into the grant and procure the necessary works in respect of the remaining eligible blocks.
1.0Recommendations 1.1 That Cabinet notes the submission of five grant funding applications to Homes England, the detail of which is outlined in part 3 of this report. 1.2 That Cabinet notes and approves the decision to accept the grant and enter into the Grant Funding Agreement with Homes England and delegates authority to the Corporate Director of Resources (S151 Officer), in consultation with the Corporate Director of Housing, Regeneration and Operations and Cabinet Member for Safe and Resilient Communities and Housing, to accept any future grants. 1.3 That, subject to the receipt of funding, Cabinet grants delegated authority to the S151 Officer in consultation with the Corporate Director of Housing, Regeneration and Operation and the Cabinet Member for Safe and Resilient Communities and Housing, to: Make the necessary amendments to the Council’s Housing Revenue Account (HRA) capital investment programme, and take all necessary steps to fulfil the requirements of the grant agreement including procuring and awarding contracts via a compliant procurement process for all professional services required.
2.0Background and Introduction 2.1 On 11 June 2025, government announced over £1 billion of new investment to accelerate the remediation of social housing, by giving social housing providers equal access to government funding as that afforded to private building owners. This means grant funding is available for remediation work with no requirement to match fund on social rented homes that meet the criteria. Prior to this date, any remediation works carried out could only attract funding towards a proportion of the costs as they relate to Leaseholders. 2.2 The Council made applications for grant funding on 28 November 2025 in respect of the twelve high-rise residential buildings potentially meeting the eligibility criteria. 2.3 In April 2026, Cabinet approved the acceptance of grant funding in respect of seven buildings (Pedley, Robinson, Arthur Cotton, Port Vale, Boundary, Brookfield and Forest Courts). 2.4 This report addresses applications for grant funding in respect of the remaining five blocks (Penkhull, Southern, Dibden, Westwood and Wellington Courts), details of which are found below in section 3.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.