Stoke-on-Trent City Council
Cabinet, Tuesday 14 July 2026 at 1.00pm

Phase 2 - Fire Safety Improvements to High Rise Residential Blocks (Notice of Decisions Reference: 2429)

Agreed Executive 1 paper

AI summaryStoke-on-Trent Cabinet approves delegated authority to accept £3.3375M Homes England grant for fire safety works to five high-rise blocks, with full funding application due within five months.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedTo accept grant and procure fire safety works
Money£3.3375M pre-tender support£0.6675M each for five blocks, no match funding required
What happens nextFull funding application within 5 monthsAfter signing the Pre-Tender Support Agreement
Who it affectsFive high-rise blocks and residentsPenkhull, Southern, Dibden, Westwood and Wellington Courts

What was decided

Cabinet noted the submission of five grant funding applications to Homes England for the remaining eligible high-rise blocks. Report 1.0

Cabinet approved accepting the grant and entering the Grant Funding Agreement, delegating authority to the S151 Officer to accept future grants. Report 1.0

Delegated authority was granted to amend the HRA capital investment programme and procure contracts for professional services, subject to funding receipt. Report 1.0

Why

The Council has a legal duty to remediate fire safety risks in its high-rise residential buildings, and grant funding lets works proceed under one programme rather than phased over years. Report 6.0, 7.0

Government made over £1 billion available from 11 June 2025 so social housing providers can access equal funding to private building owners, with no requirement to match fund.

Three of the blocks (Penkhull, Southern and Dibden) already had sprinklers installed between 2021 and 2026, and Homes England will fund only the leaseholder share of those costs.

What happens next

Submit the application for full funding to deliver the recommended remediation works within 5 months of signing the Pre-Tender Support Agreement.

Engage specialist consultancy support, either via an existing professional services contract or another framework, to produce the costed application.

Submit evidence of qualifying expenditure monthly to Homes England to draw grant, and keep residents and leaseholders informed throughout.

The money

  • £0.6675M Pre-Tender Support grant offer for each of the five buildings
  • £3.3375M Total Pre-Tender Support grant for the five buildings
  • £1.1M Capital expenditure on already installed sprinklers across three blocks
  • £8.281M Major refurbishment programme for Westwood and Wellington Courts approved by Cabinet in January 2026
  • over £1 billion New government investment announced on 11 June 2025 for social housing remediation

Options considered

  • Chosen: Apply for and accept Homes England grant funding for the five blocks. Enables all works to be expedited and managed under one programme, freeing capital for other areas of need Report 7.0
  • Rejected: Fully fund the necessary works from the Council's own budget. Would require phasing over several years due to budget pressures
  • Rejected: Westwood and Wellington: Option A, install full sprinkler systems. PTS activity will evaluate which options attract funding within the existing costed scheme
  • Rejected: Westwood and Wellington: Option B, remediate the ground floor external wall finish. PTS activity will evaluate which options attract funding within the existing costed scheme

Implications

  • Financial: Any grant funding above actual expenditure cannot be committed and must be returned to Homes England, creating a financial pressure if wrongly spent.
  • Financial: Retrospective contribution towards the £1.1M spent on the three blocks will be redirected back into capital investment budgets.
  • Financial: If the project exceeds forecasted spend, robust project management is needed to mitigate additional cost.
  • Legal: The Council must comply with the Regulatory Reform (Fire Safety) Order 2005, the Building Safety Act 2022, the Subsidy Control Act 2022, and section 19 of the Housing and Regeneration Act 2008.
  • Legal: Leaseholders cannot be recharged for funded works under Schedule 8 of the Building Safety Act.
  • Risk: Failure to submit the full funding application within 5 months could lead Homes England to withdraw the Pre-Tender Support.
  • Equalities: No Equality Impact Assessment is required and the proposals do not impact on social inequalities.
  • Climate: The proposals will not impact on the environment.

Who and where

  • Residents and leaseholders of Penkhull, Southern and Dibden Courts Report P22
  • Residents and leaseholders of Westwood and Wellington Courts Report P22
  • Wards of Hanley Park, Joiner's Square and Shelton, and Hartshill Park and Stoke Report P22

Timeline

  • 11 June 2025: Government announced over £1 billion for social housing remediation
  • 28 November 2025: Council submitted grant funding applications for twelve high-rise buildings
  • January 2026: Cabinet approved the £8.281M major refurbishment programme for Westwood and Wellington Courts
  • April 2026: Cabinet approved acceptance of grant funding for seven other buildings (Pedley, Robinson, Arthur Cotton, Port Vale, Boundary, Brookfield and Forest Courts)
  • During April 2026: Council received initial Pre-Tender Support grant offer of £3.3375M for the five blocks
  • 14 July 2026: Cabinet considered this report on the five remaining blocks Report P2, P4
  • Within 5 months of signing the PTS Agreement: Application for full funding must be submitted
  • Over the next 3 years: Capital spend for Westwood and Wellington refurbishment is already in the business plan

Plain English for the jargon

  • HRA: Housing Revenue Account, the ringfenced account for council housing income and spending
  • PTS: Pre-Tender Support, an advance of Homes England grant funding to cover costing and evaluation of remediation options
  • S151 Officer: The council's statutory Chief Finance Officer, responsible for proper financial administration
  • High-rise block: Residential building over 11 metres in height, within the scope of the Building Safety Act 2022
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item30

Resolved

Agreed ( i ) - That Cabinet notes the submission of five grant funding applications to Homes England, the detail of which is outlined in part 3 of this report. Agreed (ii) - That Cabinet notes and approves the decision to accept the grant and enter into the Grant Funding Agreement with Homes England and delegates authority to the Corporate Director of Resources (S151 Officer), in consultation with the Corporate Director of Housing, Regeneration and Operations and Cabinet Member for Safe and Resilient Communities and Housing, to accept any future grants. Agreed (iii) - That, subject to the receipt of funding, Cabinet grants delegated authority to the S151 Officer in consultation with the Corporate Director of Housing, Regeneration and Operation and the Cabinet Member for Safe and Resilient Communities and Housing, to: · Make the necessary amendments to the Council’s Housing Revenue Account (HRA) capital investment programme, and · take all necessary steps to fulfil the requirements of the grant agreement including procuring and awarding contracts via a compliant procurement process for all professional services required.
Word for word from the decision Stoke-on-Trent published for this meeting. Source: moderngov.stoke.gov.uk

Follow this further

Built from Stoke-on-Trent's papers

What the report saysPro

Report to Cabinet, 5 pages

Cabinet

Tuesday, 14 July 2026

Open

Phase 2 - Fire Safety Improvements to High Rise Residential Blocks

Report of Corporate Director of Housing, Regeneration and Operations - Carol Gibbs Cabinet Member for Safe and Resilient Communities and Housing

Purpose of Report To provide an update to Cabinet on the continued planned position of fire safety improvements to Housing Revenue Account (HRA) owned ‘high risk’ high-rise residential blocks, to inform Members of the Homes England grant funding to support improvement works and seek retrospective delegated approval to accept and enter into the grant and procure the necessary works in respect of the remaining eligible blocks.

1.0Recommendations 1.1 That Cabinet notes the submission of five grant funding applications to Homes England, the detail of which is outlined in part 3 of this report. 1.2 That Cabinet notes and approves the decision to accept the grant and enter into the Grant Funding Agreement with Homes England and delegates authority to the Corporate Director of Resources (S151 Officer), in consultation with the Corporate Director of Housing, Regeneration and Operations and Cabinet Member for Safe and Resilient Communities and Housing, to accept any future grants. 1.3 That, subject to the receipt of funding, Cabinet grants delegated authority to the S151 Officer in consultation with the Corporate Director of Housing, Regeneration and Operation and the Cabinet Member for Safe and Resilient Communities and Housing, to:  Make the necessary amendments to the Council’s Housing Revenue Account (HRA) capital investment programme, and  take all necessary steps to fulfil the requirements of the grant agreement including procuring and awarding contracts via a compliant procurement process for all professional services required.

2.0Background and Introduction 2.1 On 11 June 2025, government announced over £1 billion of new investment to accelerate the remediation of social housing, by giving social housing providers equal access to government funding as that afforded to private building owners. This means grant funding is available for remediation work with no requirement to match fund on social rented homes that meet the criteria. Prior to this date, any remediation works carried out could only attract funding towards a proportion of the costs as they relate to Leaseholders. 2.2 The Council made applications for grant funding on 28 November 2025 in respect of the twelve high-rise residential buildings potentially meeting the eligibility criteria. 2.3 In April 2026, Cabinet approved the acceptance of grant funding in respect of seven buildings (Pedley, Robinson, Arthur Cotton, Port Vale, Boundary, Brookfield and Forest Courts). 2.4 This report addresses applications for grant funding in respect of the remaining five blocks (Penkhull, Southern, Dibden, Westwood and Wellington Courts), details of which are found below in section 3.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Phase 2: Fire Safety Improvements to High Rise Residential Blocks (Notice of Decisions Reference: 2429)Decisions 5 pages DownloadRead as text

At this meeting

Whole meeting
16Minutes of Last Meeting (23/06/26)On the agenda 20Progression of proposals for local government reorganisation and devolution in Stoke-on-Trent and Staffordshire (Notice of Decisions Reference: 2419)Agreed 21Vehicle & Plant Hire Framework (Notice of Decisions Reference: 2411)Agreed 2218+ Care Homes Contracts and Updating of the Residential Charging Policy (Notice of Decisions Reference: 2413)Agreed 23VCSE integrated Wellbeing Pathways Re-Commission (Notice of Decisions Reference: 2401)Agreed 24School-based Nursery Capital Grant 2027-2030 (Notice of Decisions Reference: 2422)Agreed 25Schools Capital Programme 2026-27 (Notice of Decisions Reference: 2421)Agreed 26Future Delivery Model for Bentilee Nursery School (Notice of Decisions Reference: 2416)Agreed 27Proposed establishment of contract frameworks for repairs and maintenance works to Housing Revenue Account owned stock (Notice of Decisions Reference: 2415)Agreed 28Adoption of a new Civil Penalties Policy for Private Sector Housing (Notice of Decisions Reference: 2402)Agreed 29Renters Right Delegation 2025 (Notice of Decisions Reference: 2420)Agreed
30Phase 2 - Fire Safety Improvements to High Rise Residential Blocks (Notice of Decisions Reference: 2429)This decision
31IT Network Hardware Refresh (Notice of Decisions Reference: 2428)Agreed 32Review of Policy on the Regulation of Investigatory Powers Act 2000 (Notice of Decisions Reference: 2450)Agreed 33Packmoor - Feedback from the recent Masterplan consultation and approval of the preferred Masterplan option (Notice of Decisions Reference: 2418)Agreed 34Stoke-on-Trent Local Plan 2020-2040: Publication Plan (Regulation 19) (Notice of Decisions Reference: 2388)Agreed 35Exclusion of the PublicOn the agenda 36Renewal of Social Care System (Liquid Logic) (Notice of Decisions Reference: 2407) (Para. 3)Private 37Development Agreement for Etruscan Square sites, Hanley (Notice of Decisions Reference: 2349) (Para. 3)Private

More from Stoke-on-Trent Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Extension to funding agreement between Stoke-on-Trent City Council and Thrive at Five (Notice of Decisions Reference: 2482)Agreed ( i ) - Approval is granted to extend the funding agreement between Stoke-on-Trent City Council and Thrive at ... Agreed Open
3 Nov 2026 Soft Block Fostering Options (Notice of Decisions Reference: 2468)Agreed ( i ) - That approval is granted to undertake a competitive procurement exercise for a soft block fostering co... Agreed Open
3 Nov 2026 Youth Justice Strategic Plan (Notice of Decisions Reference: 2470)Agreed - That Cabinet approves the Youth Justice Plan 2026/27 and recommends its adoption by the City Council. N.B. T... Agreed Open
3 Nov 2026 Reviewing powers for reducing anti-social behaviour including requiring the removal of facing coverings where necessary and appropriate (Notice of Decisions Reference: 2477)Agreed ( i ) – That Cabinet note the current Public Spaces Protection Orders (PSPOs) operating within Hanley and Long... Agreed Open
3 Nov 2026 Housing Revenue Account (HRA) Rent Setting Report 2027/28 (Notice of Decisions Reference: 2457)Agreed - That Cabinet recommends to City Council that, as part of the budget setting processes approval is given to: ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies