What was decided
Cabinet agreed to transfer mining related objects left at the Chatterley Whitfield site to the Friends group, based on an inventory they will provide, and gave the Head of Legal, Governance, Culture and Heritage delegated authority to transfer any further objects found in future and to take all necessary steps to conclude the transfer. Report 1.1, P42
Cabinet adopted the development themes for the site, including exploiting renewable energy resources, options for data centre development, re-use of buildings and other commercial, cultural, training and heritage uses. Report 1.4, 3.18, 3.19, P12, 3.21, 3.22
Cabinet approved use of external specialist advisors, delegated authority to the Corporate Director for Housing, Regeneration and Operations to take all steps needed, agreed to work with stakeholders to secure and apply grant funding, and supported use of £185,000 from Capital Contingency for the next phase of work. Report P43, P57
Why
Officers said the artefact transfer is the best way to preserve items the Friends have already been guarding, and gives them formal title for the benefit of the city, with reversion to the council if the Friends cease to operate. Report P42, 6.1, P44
The development plan is presented as the best route to a commercially sustainable future for the site, enabling protection of heritage while generating income, with phased priorities including solar PV, targeted building refurbishment, data centre deployment, a training and apprenticeship centre, the BL9 access route and the heat network. Report P43, 3.26, 3.22, 3.23, P45
What happens next
The Head of Legal, Governance, Culture and Heritage will draw up a legal agreement for the artefact transfer, with the Friends required to acknowledge the council cannot guarantee title. Report P62
The Corporate Director for Housing, Regeneration and Operations will commission external specialist advisors to develop the investment case, undertake studies and present options to market between August 2026 and March 2027, covering minewater heat, ground conditions, data centre liaison, grid connection, planning, refurbishment, heat network and a training academy. Report 3.27, P40, P41, P38
Capital budget of £185,000 to be vired from Capital Contingency to the Chatterley Whitfield Development scheme, within the approved 2026/27 MTFS, with around £3,000 per year additional revenue needed for new CCTV. Report P57, P58, P59
The money
- £185,000 Vired from Capital Contingency to Chatterley Whitfield Development scheme for next phase of work Report P57
- circa £3,000 per year Additional ongoing revenue cost for extra CCTV cameras, not covered by existing budgets Report P59
Options considered
- Chosen: Transfer artefacts to Chatterley Whitfield Friends. Ensures preservation; alternatives would leave assets on an informal basis or return them to a council with no capacity to safeguard them Report 1.1, P44, 6.1
- Chosen: Adopt development plan themes and use external specialist advisors. Best way to secure a commercially sustainable future and protect council interests in site energy resources Report 1.4, P43, P45
- Rejected: Do nothing. Custody of artefacts unresolved and site would continue to deteriorate, with ongoing unaffordable costs and loss of development opportunities Report 7.1, P44, P45
Implications
- Financial: £185,000 vired from Capital Contingency within the 2026/27 MTFS; if the scheme does not progress, costs incurred become a revenue pressure, and an extra circa £3,000 per year is needed for new CCTV. Report P57, P59
- Legal: Each project will need its own legal advice on governance, procurement, subsidy control, planning and property; the site has constraints including scheduled monument protection, country park protection, restrictive covenants (e.g. limiting land to museum use), leases and excluded mines and minerals; the council cannot evidence or guarantee title to the artefacts. Report P60, P61, P62
- Equalities: An Equality Impact Assessment is not required for the report, but the proposal is expected to bring employment, education and skills opportunities to a local area where there is currently a deficit. Report P66, P68
- Climate: Proposals are expected to have a positive environmental impact by developing a contaminated brownfield site, using sustainable energy for data centre power and cooling, and supplying heat via a network to reduce carbon dioxide emissions; full environmental impact assessment will be required. Report P70, P26, P27
- Risk: Council remains at feasibility stage and is quantifying and assessing risk through due diligence, which will continue and inform any financial decisions on business cases. Report 5.1
- Staffing: No human resources implications arising from the report. Report P64
Who and where
- Baddeley, Milton and Norton wards Report P72
- Chatterley Whitfield Friends, as recipients of the transferred mining artefacts and ongoing partner Report 6.1
- Historic England, given the site's Scheduled Monument and Heritage at Risk status and priority building works
- Data centre developers, energy providers and training partners being engaged during the August 2026 to March 2027 work programme Report P41, P38
Timeline
- August 2026 to March 2027: Proposed programme of activities arising from the 2025/26 work programme, covering minewater heat, ground conditions, data centre liaison, grid connection, planning, refurbishment, heat network and training academy Report P40, P41
- 2026-09-08: Cabinet decision taken
Plain English for the jargon
- Chatterley Whitfield: Former deep coal mine and first underground mining museum in Britain, now a Scheduled Monument covering about 100 hectares, owned by Stoke-on-Trent City Council
- Black to Green: Council programme aimed at creating a catalyst for investment in the site through renewable energy, data centres and a heritage hub
- DHN (District Heat Network): A piped system for distributing heat from a central source, here from minewater heat and data centre waste heat, to nearby buildings
- Minewater heat: Low-grade heat recovered from flooded former mine workings and upgraded with heat pumps for use in buildings
- UTES: Underground Thermal Energy Storage, the seasonal storage of heat underground