Proposed Options for Ten Council-Owned Tower Blocks (Notice of Decisions Reference: 2461)
AgreedExecutive4 papers
AI summaryStoke-on-Trent Cabinet backs refurbishment-only and hybrid options for ten council tower blocks, dropping the 2023 plan to redevelop all ten as no longer financially viable. Two options go to a six-week resident consultation.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedOption 1b (refurbish all) and Option 3 (hybrid 7+3)
Money£32.8M to £42.4M capital costHybrid option around £32.8M, full refurbishment around £42.4M
What happens nextSix-week resident consultationA more detailed proposal will return to Cabinet after feedback
Who it affectsTen HRA high-rise blocks374 units, of which 309 are social housing
What was decided
Cabinet noted the external 'High-Rise H Blocks Options Appraisal' and rescinded the January 2023 in-principle decision (NOD 2010) to redevelop all ten blocks because it is no longer financially viable. Report P2
Cabinet approved two options to take to consultation: Option 1b (retention and enhanced refurbishment of all sites) and Option 3 (hybrid: enhanced refurbishment of 7 blocks, demolition and land banking of 3). Report P5
Authority to run the consultation was delegated to the Corporate Director of Housing, Regeneration and Operation, in consultation with the Cabinet Member for Safe and Resilient Communities and Housing, with a further detailed proposal to return to Cabinet after feedback.
Why
The report weighed capital cost, long-term asset performance and compliance, and resident outcomes, asking which option offers best value over the asset life, compliance with current and future safety standards, long-term revenue pressure reduction, and a manageable risk profile. Report P3, P4, P17, P18
Demolishing all ten and rebuilding was the most expensive at around £113.32M and the full demolition and land-banking option would lose 374 units without a long-term plan for the land, while full refurbishment offered a short-term fix but did not represent value for money over the asset life. Report P5, P9
Refurbishment could require repaying Homes England Cladding Safety Scheme grant (around £6.675M, or about £2.0025M for the 3 blocks under the hybrid), and retrofit is limited by existing layout and structure, with potential building safety regulator delays. Report P9, P11, P13
What happens next
The Corporate Director and Cabinet Member will commence a formal six-week consultation with residents and stakeholders of the affected blocks on Options 1b and 3.
A more detailed proposal will be brought back to Cabinet for consideration once consultation feedback is received.
The money
£20.78M Capital cost, Option 1a minimum refurbishment of all 10 blocks Report P5
£42.4M Capital cost, Option 1b enhanced refurbishment of all 10 blocks Report P5
£10.56M Capital cost, Option 2a demolish and land bank all 10 blocks Report P5
£113.32M Capital cost, Option 2b demolish and rebuild all 10 blocks Report P5
£32.8M Capital cost, Option 3 hybrid: enhanced refurbishment of 7 blocks plus demolition and land bank of 3 Report P5
£4.2M Reduction in planned capital works revenue, Option 1b Report P6, P8
£1.8M Reduction in planned capital works revenue, Option 3 Report P6, P8
£5.7M Revenue impact, Option 2a, funded through reserves or savings Report P6, P8
£0.5M Revenue impact, Option 2b, funded through reserves or savings Report P6, P8
£6.675M Potential repayment of Homes England Cladding Safety Scheme grant under full refurbishment scenarios Report P9
£2.0025M Potential repayment of Cladding Safety Scheme grant for the 3 blocks under Option 3 Report P9
Options considered
Rejected: Option 1a: minimum refurbishment of all 10 blocks (like for like). Short-term resolution but does not represent value for money over the asset life; payback beyond 50 years Report P5, P9
Chosen for consultation: Option 1b: enhanced refurbishment of all 10 blocks. Retains 374 units, addresses fire safety, energy efficiency, damp and mould; enables continued use and improvements in energy performance Report P5, P9, P11
Rejected: Option 2a: demolish and land bank all 10 blocks. Loss of 374 units with no long-term plan for the land; negative area impact and reduced revenue; may require Cladding Safety Scheme grant repayment Report P5, P9, P11
Rejected: Option 2b: demolish and rebuild all 10 blocks. Capital cost around £113.32M; lower longer-term maintenance but not best value for money and 5+ year programme Report P5, P9
Chosen for consultation: Option 3: hybrid - enhanced refurbishment of 7 highest performing blocks and demolish/land bank 3 lowest performing. Retains 260 units for a considerable period, reduced revenue impact, and lower capital cost than full refurbishment Report P5, P9
Rejected: Previous in-principle decision to redevelop all 10 blocks (NOD 2010, January 2023). No longer a financially viable option
Implications
Financial: Capital borrowing required for both options, with payback periods of 30+ years and refinancing after 30 years; Option 1b reduces revenue by around £4.2M, Option 3 by around £1.8M. Report P5, P6, P8
Legal: Homes England Cladding Safety Scheme grant (around £6.675M in total, about £2.0025M for the 3 blocks under Option 3) may need to be repaid if blocks are demolished or timescales slip. Report P9
Risk: Refurbishment work is subject to potential delays from Building Safety Regulator (BSR) applications and unknown issues, with each block estimated at 2 to 2.5 years. Report P13
Equalities: Loss of 374 units under full demolition, or 114 fewer affordable units under Option 3, against a waiting list where one and two bed demand in Hanley and Joiners Square represents 602 applicants (38% of the waiting list, May 2026). Report P13
Climate: Refurbishment retains embodied carbon in existing structures; demolition of structurally sound buildings raises the carbon footprint though operational efficiency improves. Report P15
Staffing: Hybrid option would require ongoing security and monitoring on the three demolition and land-bank sites, with potential fly-tipping and antisocial behaviour risk. Report P11
Who and where
Residents of all ten council-owned HRA high-rise blocks (374 units, of which 309 are social housing) Report P9
Leaseholders in blocks under consideration (buy-back negotiations of 1 to 1.5 years noted under demolition scenarios) Report P13
Households on the housing waiting list, particularly the 602 applicants (38%) seeking one and two bedroom accommodation in Hanley and Joiners Square (May 2026 figures) Report P13
Wider communities in the surrounding neighbourhoods, including through place-making, regeneration, and the risk of antisocial behaviour and fly-tipping on demolition sites Report P11, P13
Timeline
January 2023: Cabinet approved in-principle decision to redevelop all ten blocks (NOD 2010), now rescinded
May 2026: Waiting list snapshot cited in the report: 602 one and two bed applicants in Hanley and Joiners Square (38% of waiting list) Report P13
2026 (date of Cabinet decision): Two options approved to take forward to a six-week consultation
6 weeks (consultation): Formal consultation with residents and stakeholders of the affected blocks
After consultation: A more detailed proposal will return to Cabinet for consideration
Circa 2 to 2.5 years per block: Indicative duration for refurbishment works, running in a phased programme with overlap Report P13
Around 5 years (Option 3, 7 blocks) and around 6 years (Option 1b, all 10 blocks): Indicative total programme durations cited in the options table Report P13
Plain English for the jargon
HRA: Housing Revenue Account: the ring-fenced account local authorities use for income and spending on council housing.
NOD: Notice of Decision: the formal record of an executive decision taken by a council.
BSR: Building Safety Regulator: the body responsible for overseeing the safety of higher-risk buildings in England.
HHRS: Housing Health and Safety Rating System: the method used to assess housing conditions and hazards.
Cladding Safety Scheme: A Homes England grant programme that funds remediation of unsafe cladding on residential buildings.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item63
Resolved
Agreed ( i ) – That Cabinet notes the contents and findings of the externally commissioned report ‘High- Rise H Blocks Options Appraisal’ (Appendix 1). Agreed (ii) – That Cabinet rescinds the previous ‘in principle’ decision to redevelop all ten blocks, as approved by Cabinet in January 2023 (NOD 2010), on the basis that it is no longer a financially viable option. Agreed (iii) – That Cabinet approves the following two options to take forward to consultation: · Option (1b) – Retention and refurbishment of all sites to an enhanced standard; and · Option (3) – Hybrid of investment (enhanced refurbishment to 7 blocks and demolition and land bank sites relating to 3 blocks). Agreed (iv) – That Cabinet delegates authority to the Corporate Director of Housing, Regeneration and Operation in consultation with the Cabinet Member for Safe and Resilient Communities and Housing to commence consultation with residents and stakeholders of the affected blocks in respect of the preferred options specified in paragraph 1.3 of this report. Agreed (v) – That Cabinet notes that following consultation, a more detailed proposal will follow for Cabinet to consider once feedback is received.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Evaluation of Options This appraisal compares the implications of refurbishing the existing 10 HRA high-rise residential blocks with demolition and redevelopment.
It is assessed against:
Financial - Value for money Long term asset performance, including compliance Resident outcomes
Options: Option 1 – Retain & refurbish all 10 Option 2 - Demolish all 10 blocks Option 3 - Hybrid blocks (a) (b) (a) (b) Enhanced refurbishment Minimum Enhanced Refurbishment Demolish and land bank Demolish and Rebuild (7 highest performing blocks) Consideration Refurbishment (like for like / same nr of + Demolition and landbank (3 units) lowest performing block) Financial Capital cost (circa) £20.78M £42.4M £10.56M £113.32M £32.8M
Pay-back Period Capital borrowing Capital borrowing Capital borrowing Beyond industry standard, Capital borrowing modelled modelled on interest modelled on interest only modelled on interest only Proval software, against on interest only borrowing – only borrowing – borrowing – 30year+, borrowing – 30year+, the acceptable 30year+, refinancing after 30year+, refinancing refinancing after term. refinancing after term. development parameters term. after term. of 50+ years. Affordability / Retention of blocks Consideration to uplifting Loss of blocks negates the New development would Loss of 3 blocks negates the Viability enables continued rents / increasing revenue planned capital sprinkler allow higher / market rents planned capital sprinkler revenue from rents. As within the legal Rent programme, resulting in a to be set to enable better programme, resulting in a the HRA will not be Setting framework. reduction of £4.2M cost recovery – would this reduction of £1.8M planned generating further Enhanced refurbishment planned capital works. still not reach viability? capital works. income via increased may enable a justifiable Future proof major costs units from the dwelling, reason to levy service for leaseholders by this will result in a introducing a sinking fund.
1|Page Appendix 2– Cabinet Report July 2026
financial pressure. For charges to increase HRA For this scenario the this scenario the impact revenue. impact on revenue is circa is circa £0.5M, funded £5.7M, funded through through either reserves either reserves or savings or savings.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.