Stoke-on-Trent City Council
Cabinet, Tuesday 8 September 2026 at 1.00pm

Proposed Options for Ten Council-Owned Tower Blocks (Notice of Decisions Reference: 2461)

Agreed Executive 4 papers

AI summaryStoke-on-Trent Cabinet backs refurbishment-only and hybrid options for ten council tower blocks, dropping the 2023 plan to redevelop all ten as no longer financially viable. Two options go to a six-week resident consultation.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedOption 1b (refurbish all) and Option 3 (hybrid 7+3)
Money£32.8M to £42.4M capital costHybrid option around £32.8M, full refurbishment around £42.4M
What happens nextSix-week resident consultationA more detailed proposal will return to Cabinet after feedback
Who it affectsTen HRA high-rise blocks374 units, of which 309 are social housing

What was decided

Cabinet noted the external 'High-Rise H Blocks Options Appraisal' and rescinded the January 2023 in-principle decision (NOD 2010) to redevelop all ten blocks because it is no longer financially viable. Report P2

Cabinet approved two options to take to consultation: Option 1b (retention and enhanced refurbishment of all sites) and Option 3 (hybrid: enhanced refurbishment of 7 blocks, demolition and land banking of 3). Report P5

Authority to run the consultation was delegated to the Corporate Director of Housing, Regeneration and Operation, in consultation with the Cabinet Member for Safe and Resilient Communities and Housing, with a further detailed proposal to return to Cabinet after feedback.

Why

The report weighed capital cost, long-term asset performance and compliance, and resident outcomes, asking which option offers best value over the asset life, compliance with current and future safety standards, long-term revenue pressure reduction, and a manageable risk profile. Report P3, P4, P17, P18

Demolishing all ten and rebuilding was the most expensive at around £113.32M and the full demolition and land-banking option would lose 374 units without a long-term plan for the land, while full refurbishment offered a short-term fix but did not represent value for money over the asset life. Report P5, P9

Refurbishment could require repaying Homes England Cladding Safety Scheme grant (around £6.675M, or about £2.0025M for the 3 blocks under the hybrid), and retrofit is limited by existing layout and structure, with potential building safety regulator delays. Report P9, P11, P13

What happens next

The Corporate Director and Cabinet Member will commence a formal six-week consultation with residents and stakeholders of the affected blocks on Options 1b and 3.

A more detailed proposal will be brought back to Cabinet for consideration once consultation feedback is received.

The money

  • £20.78M Capital cost, Option 1a minimum refurbishment of all 10 blocks Report P5
  • £42.4M Capital cost, Option 1b enhanced refurbishment of all 10 blocks Report P5
  • £10.56M Capital cost, Option 2a demolish and land bank all 10 blocks Report P5
  • £113.32M Capital cost, Option 2b demolish and rebuild all 10 blocks Report P5
  • £32.8M Capital cost, Option 3 hybrid: enhanced refurbishment of 7 blocks plus demolition and land bank of 3 Report P5
  • £4.2M Reduction in planned capital works revenue, Option 1b Report P6, P8
  • £1.8M Reduction in planned capital works revenue, Option 3 Report P6, P8
  • £5.7M Revenue impact, Option 2a, funded through reserves or savings Report P6, P8
  • £0.5M Revenue impact, Option 2b, funded through reserves or savings Report P6, P8
  • £6.675M Potential repayment of Homes England Cladding Safety Scheme grant under full refurbishment scenarios Report P9
  • £2.0025M Potential repayment of Cladding Safety Scheme grant for the 3 blocks under Option 3 Report P9

Options considered

  • Rejected: Option 1a: minimum refurbishment of all 10 blocks (like for like). Short-term resolution but does not represent value for money over the asset life; payback beyond 50 years Report P5, P9
  • Chosen for consultation: Option 1b: enhanced refurbishment of all 10 blocks. Retains 374 units, addresses fire safety, energy efficiency, damp and mould; enables continued use and improvements in energy performance Report P5, P9, P11
  • Rejected: Option 2a: demolish and land bank all 10 blocks. Loss of 374 units with no long-term plan for the land; negative area impact and reduced revenue; may require Cladding Safety Scheme grant repayment Report P5, P9, P11
  • Rejected: Option 2b: demolish and rebuild all 10 blocks. Capital cost around £113.32M; lower longer-term maintenance but not best value for money and 5+ year programme Report P5, P9
  • Chosen for consultation: Option 3: hybrid - enhanced refurbishment of 7 highest performing blocks and demolish/land bank 3 lowest performing. Retains 260 units for a considerable period, reduced revenue impact, and lower capital cost than full refurbishment Report P5, P9
  • Rejected: Previous in-principle decision to redevelop all 10 blocks (NOD 2010, January 2023). No longer a financially viable option

Implications

  • Financial: Capital borrowing required for both options, with payback periods of 30+ years and refinancing after 30 years; Option 1b reduces revenue by around £4.2M, Option 3 by around £1.8M. Report P5, P6, P8
  • Legal: Homes England Cladding Safety Scheme grant (around £6.675M in total, about £2.0025M for the 3 blocks under Option 3) may need to be repaid if blocks are demolished or timescales slip. Report P9
  • Risk: Refurbishment work is subject to potential delays from Building Safety Regulator (BSR) applications and unknown issues, with each block estimated at 2 to 2.5 years. Report P13
  • Equalities: Loss of 374 units under full demolition, or 114 fewer affordable units under Option 3, against a waiting list where one and two bed demand in Hanley and Joiners Square represents 602 applicants (38% of the waiting list, May 2026). Report P13
  • Climate: Refurbishment retains embodied carbon in existing structures; demolition of structurally sound buildings raises the carbon footprint though operational efficiency improves. Report P15
  • Staffing: Hybrid option would require ongoing security and monitoring on the three demolition and land-bank sites, with potential fly-tipping and antisocial behaviour risk. Report P11

Who and where

  • Residents of all ten council-owned HRA high-rise blocks (374 units, of which 309 are social housing) Report P9
  • Leaseholders in blocks under consideration (buy-back negotiations of 1 to 1.5 years noted under demolition scenarios) Report P13
  • Households on the housing waiting list, particularly the 602 applicants (38%) seeking one and two bedroom accommodation in Hanley and Joiners Square (May 2026 figures) Report P13
  • Wider communities in the surrounding neighbourhoods, including through place-making, regeneration, and the risk of antisocial behaviour and fly-tipping on demolition sites Report P11, P13

Timeline

  • January 2023: Cabinet approved in-principle decision to redevelop all ten blocks (NOD 2010), now rescinded
  • May 2026: Waiting list snapshot cited in the report: 602 one and two bed applicants in Hanley and Joiners Square (38% of waiting list) Report P13
  • 2026 (date of Cabinet decision): Two options approved to take forward to a six-week consultation
  • 6 weeks (consultation): Formal consultation with residents and stakeholders of the affected blocks
  • After consultation: A more detailed proposal will return to Cabinet for consideration
  • Circa 2 to 2.5 years per block: Indicative duration for refurbishment works, running in a phased programme with overlap Report P13
  • Around 5 years (Option 3, 7 blocks) and around 6 years (Option 1b, all 10 blocks): Indicative total programme durations cited in the options table Report P13

Plain English for the jargon

  • HRA: Housing Revenue Account: the ring-fenced account local authorities use for income and spending on council housing.
  • NOD: Notice of Decision: the formal record of an executive decision taken by a council.
  • BSR: Building Safety Regulator: the body responsible for overseeing the safety of higher-risk buildings in England.
  • HHRS: Housing Health and Safety Rating System: the method used to assess housing conditions and hazards.
  • Cladding Safety Scheme: A Homes England grant programme that funds remediation of unsafe cladding on residential buildings.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item63

Resolved

Agreed ( i ) – That Cabinet notes the contents and findings of the externally commissioned report ‘High- Rise H Blocks Options Appraisal’ (Appendix 1). Agreed (ii) – That Cabinet rescinds the previous ‘in principle’ decision to redevelop all ten blocks, as approved by Cabinet in January 2023 (NOD 2010), on the basis that it is no longer a financially viable option. Agreed (iii) – That Cabinet approves the following two options to take forward to consultation: · Option (1b) – Retention and refurbishment of all sites to an enhanced standard; and · Option (3) – Hybrid of investment (enhanced refurbishment to 7 blocks and demolition and land bank sites relating to 3 blocks). Agreed (iv) – That Cabinet delegates authority to the Corporate Director of Housing, Regeneration and Operation in consultation with the Cabinet Member for Safe and Resilient Communities and Housing to commence consultation with residents and stakeholders of the affected blocks in respect of the preferred options specified in paragraph 1.3 of this report. Agreed (v) – That Cabinet notes that following consultation, a more detailed proposal will follow for Cabinet to consider once feedback is received.
Word for word from the decision Stoke-on-Trent published for this meeting. Source: moderngov.stoke.gov.uk

Follow this further

Built from Stoke-on-Trent's papers

What the report saysPro

Report to Cabinet

Appendix 2– Cabinet Report July 2026

Evaluation of Options This appraisal compares the implications of refurbishing the existing 10 HRA high-rise residential blocks with demolition and redevelopment.

It is assessed against:

 Financial - Value for money  Long term asset performance, including compliance  Resident outcomes

Options: Option 1 – Retain & refurbish all 10 Option 2 - Demolish all 10 blocks Option 3 - Hybrid blocks (a) (b) (a) (b) Enhanced refurbishment Minimum Enhanced Refurbishment Demolish and land bank Demolish and Rebuild (7 highest performing blocks) Consideration Refurbishment (like for like / same nr of + Demolition and landbank (3 units) lowest performing block) Financial Capital cost (circa) £20.78M £42.4M £10.56M £113.32M £32.8M

Pay-back Period Capital borrowing Capital borrowing Capital borrowing Beyond industry standard, Capital borrowing modelled modelled on interest modelled on interest only modelled on interest only Proval software, against on interest only borrowing – only borrowing – borrowing – 30year+, borrowing – 30year+, the acceptable 30year+, refinancing after 30year+, refinancing refinancing after term. refinancing after term. development parameters term. after term. of 50+ years. Affordability / Retention of blocks Consideration to uplifting Loss of blocks negates the New development would Loss of 3 blocks negates the Viability enables continued rents / increasing revenue planned capital sprinkler allow higher / market rents planned capital sprinkler revenue from rents. As within the legal Rent programme, resulting in a to be set to enable better programme, resulting in a the HRA will not be Setting framework. reduction of £4.2M cost recovery – would this reduction of £1.8M planned generating further Enhanced refurbishment planned capital works. still not reach viability? capital works. income via increased may enable a justifiable Future proof major costs units from the dwelling, reason to levy service for leaseholders by this will result in a introducing a sinking fund.

1|Page Appendix 2– Cabinet Report July 2026

financial pressure. For charges to increase HRA For this scenario the this scenario the impact revenue. impact on revenue is circa is circa £0.5M, funded £5.7M, funded through through either reserves either reserves or savings or savings.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
App. 2 Evaluation of Proposed Options for Ten Council-Owned Tower BlocksReport 424 KB DownloadRead as text
PDF
App. 3 Draft Consultation PlanReport 449 KB Download
PDF
App. 4 Financial AppraisalReport 218 KB Download
PDF
Proposed Options for Ten Council-Owned Tower Blocks (Notice of Decisions Reference: 2461)Decisions 340 KB Download

At this meeting

Whole meeting

Who was there

13 of 20 attended
JA
Councillor Jane Ashworth OBEChair, present
AW
Councillor Amjid Wazir OBECabinet Member, apologies
SJ
Councillor Sarah Jane ColcloughCabinet Member, present
FG
Councillor Finlay Gordon-McCuskerCabinet Member, present
SH
Councillor Sarah HillCabinet Member, apologies
MK
Councillor Majid KhanCabinet Member, present
DW
Councillor Duncan WalkerCabinet Member, apologies
LW
Councillor Lynn WatkinsCabinet Member, apologies
LD
Councillor Lauren DavisonCabinet Support Member, apologies
WA
Councillor Waseem AkbarCabinet Support Member, in attendance
CR
Councillor Chris RobinsonCabinet Support Member, in attendance
JR
Jon RouseOfficer, present

All 20 on the meeting page

More from Stoke-on-Trent Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Extension to funding agreement between Stoke-on-Trent City Council and Thrive at Five (Notice of Decisions Reference: 2482)Agreed ( i ) - Approval is granted to extend the funding agreement between Stoke-on-Trent City Council and Thrive at ... Agreed Open
3 Nov 2026 Soft Block Fostering Options (Notice of Decisions Reference: 2468)Agreed ( i ) - That approval is granted to undertake a competitive procurement exercise for a soft block fostering co... Agreed Open
3 Nov 2026 Youth Justice Strategic Plan (Notice of Decisions Reference: 2470)Agreed - That Cabinet approves the Youth Justice Plan 2026/27 and recommends its adoption by the City Council. N.B. T... Agreed Open
3 Nov 2026 Reviewing powers for reducing anti-social behaviour including requiring the removal of facing coverings where necessary and appropriate (Notice of Decisions Reference: 2477)Agreed ( i ) – That Cabinet note the current Public Spaces Protection Orders (PSPOs) operating within Hanley and Long... Agreed Open
3 Nov 2026 Housing Revenue Account (HRA) Rent Setting Report 2027/28 (Notice of Decisions Reference: 2457)Agreed - That Cabinet recommends to City Council that, as part of the budget setting processes approval is given to: ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies