(1) That the Capital Budget for 2007/08 be increased by £5,892,100, as detailed in Appendix B, for slippage financed by the capital receipts as budgeted for in 2006/07. (2) That the budget amendments outlined in the report be approved. NOTE : This item is subject to call-in to Overview and Scrutiny B
Word for word from the decision Stratford-on-Avon published for this meeting.Source: democracy.stratford.gov.uk
SUBJECT: Capital Outturn 2006/07 and Capital Slippage LEAD OFFICER: SARAH PITTAWAY CONTACT ON 01789 260416 LEAD MEMBER/ PORTFOLIO HOLDER: LYNDA ORGAN
SUMMARY This report provides the Executive with details of the Capital Outturn 2006/07.
RECOMMENDATION (1) That the Capital Budget be increased by £5,892,100 as detailed in Appendix B in 2007/08 for slippage financed by the capital receipts as budgeted for in 2006/07; and (2) That the budget amendments outlined in section 2.1 and 2.2 of the report be approved.
1 BACKGROUND/INFORMATION 1.1 The Capital Programme for 2006/07 was originally agreed totalling £10,113,950. With the amendments agreed by the Executive to date the total Capital Budget for 2006/07 totals £10,967,982. The final Capital Expenditure (subject to audit and the overall closure of the accounts) totals £5,782,624, an underspend of £5,185,358. Details of the expenditure compared to budget for each scheme is shown in Appendix A.
2 OPTIONS AVAILABLE TO THE COMMITTEE 2.1 The following amendments are proposed to the 2006/07 Capital Programme:- 2.1.1 Digital Challenge £240,000 – an amendment is proposed to remove the income and expenditure budgets for this project and establish a code within the Balance Sheet instead. This has a net nil impact on the Capital Budget. 2.1.2 S.106 Developer Contributions – the Council has received a ring-fenced off- site developer contribution of £427,000 in respect of affordable housing. 2.1.3 World Class Stratford 2.1.3.1 In relation to the World Class Stratford Project, it is necessary to bring to the attention of members the fact that a contract’s expenditure has exceeded its original contract value by 10%. The Contract is with Urban Practitioners (UP) to develop an Urban Design Framework for the Town. As a result of additional work requested by the Council and key stakeholders,
EXECUTIVE 30 APRIL 2007 ITEM NO 9 PAGE 1 UP have been given contract variations that now total a sum that is 12.1% more than the original contract sum. The additional costs are fully met by Advantage West Midlands, who have provided an additional grant sum of £100,000 towards the UDF work and for work associated with developing some aspects of the framework further. As the contract expenditure now exceeds 10% of the original contract value, it is necessary to report this fact to comply with the Council’s Constitution. 2.2 Explanations of notable variances and progress on schemes are included within Appendix A. Details of some of the more significant variances are shown below:- Head of Revenues & Housing 2.2.1 Affordable Housing Investment Programme Budget £3,122,400, Spending £1,119,028, Underspend £2,003,372
The Council has a commitment to spend £2m for affordable housing. Slippage of £2,003,300 is requested as slippage to 2007/08.
Head of Change and Performance 2.2.2 E.Government Budget £1,082,600, Spending £1,047,319 Underspend £35,281 Slippage to 2007/08 is requested in order to complete the E-Government Ceapital Programme of works, as detailed in the report to the Executive on 5th September 2005.
Slippage of £50,200 is requested to 2007/08.
Head of Community Services 2.2.3 Area Committee Capital Grants Budget £440,932, Spending £175,508, Underspend £265,424
Slippage of £263,000 is requested in respect of Capital Grants commitments to be rolled forward.
2.2.4 CCTV Equipment Budget £182,700, Spending £88,030, Underspend £94,670 All £94,600 underspend is requested as slippage to 2007/08.
2.2.5 Wellesbourne Community Hall Budget £1,257,600, Spending £20, Underspend £1,257,580 All £1,257,500 underspend is requested as slippage to 2007/08.
EXECUTIVE 30 APRIL 2007 ITEM NO 9 PAGE 2 World Class Stratford 2.2.6 World Class Stratford Project Budget £1,123,000, Spending £801,668, Underspend £321,332
Slippage of £321,300 is requested to be slipped to 2007/08.
Head of Environment 2.2.7 DEFRA Recycling & Waste project. Budget £50,000, Spending £0, Underspend £50,000
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.